Question

In: Accounting

Use the following information regarding Musketeer Novelties: Activity Activity Costs Cost driver Product design $212,000 1,500...

Use the following information regarding Musketeer Novelties:

Activity Activity Costs Cost driver

Product design $212,000 1,500 design hours

Product scheduling $180,000 400 Set ups

Machining $600,000 5,000 machine hours

Material Handling $160,000 4,000 Pallet moved

Cost and activity with procuring 2,000 units of a Blueblob Bobblehead are as follows:

Direct Materials: $5,400

Direct Labor: $1,200

Design Hours: 5

Set-Ups: 3

Labor Hours 40

Machine Hours 18

Pallets Moved 10

United produced 400

1.) Develop activity rates for each of the four activities of Musketeer Novelties

2.) What is the product cost for ONE Blueblob Bobblehead using ABC (ACTIVITY BASE COSTING) rates for applying overhead?

3.)What is the product cost of one Blueblob bobblehead if Musketeer Novelties uses a plant-wide overhead rate based on machine hours. (assume 5,000 machine hours plant-wide)

Solutions

Expert Solution

1
Activity Activity Cost Cost Driver ABC Rate
Product design 212000 1500 design hrs 141.33 per Design hr
Product scheduling 180000 400 set ups 450 per setup
Machining 600000 5000 machine hrs 120 per machine hr
Material Handling Costs 160000 4000 pallet moved 40 per pallet moved
Total OH 1152000
2
Particulars Amt ($)
Direct Material 5400
Direct Labour 40 Labour hrs 30 per Labour hr 1200
Overheads NO's (A) ABC Rate (B) C = A x B
Product design 5 hrs 141.33 per Design hr 707
Product scheduling 3 set ups 450 per setup 1350
Machining 18 Machine hrs 120 per machine hr 2160
Material Handling Costs 10 Pallets moved 40 per pallet moved 400 4617
Total Cost for producing 2000 units 11217
NO. of Units 2000
Product cost for ONE Blueblob Bobblehead (ABC) 5.61
3
If Musketeer Novelties uses a plant-wide overhead rate based on machine hours, then
Overhead Recovery Rate (OHRR) will be
Total Overhead Cost (a) 1152000
Total Plant Machine hrs 5000
OHRR 230.40 per machine hr
Particulars Amt ($)
Direct Material 5400.00
Direct Labour 1200.00
Overhead Cost 18 Machine hrs 230.40 per Machine hr 4147.20
Total Cost for producing 2000 units 10747.20
NO. of Units 2000
Product cost for ONE Blueblob Bobblehead (ABC) 5.37

Related Solutions

Use the following information regarding Musketeer Novelties: Activity Activity Costs Cost driver Product design $212,000 1,500...
Use the following information regarding Musketeer Novelties: Activity Activity Costs Cost driver Product design $212,000 1,500 design hours Product scheduling $180,000 400 Set ups Machining $600,000 5,000 machine hours Material Handling $160,000 4,000 Pallet moved Cost and activity with procuring 2,000 units of a Blueblob Bobblehead are as follows: Direct Materials: $5,400 Direct Labor: $1,200 Design Hours: 5 Set-Ups: 3 Labor Hours 40 Machine Hours 18 Pallets Moved 10 United produced 400 1.) Develop activity rates for each of the...
The following budgeted information is available for Zeta Company: Activity Budgeted Cost Activity Driver Consumption of...
The following budgeted information is available for Zeta Company: Activity Budgeted Cost Activity Driver Consumption of Drivers for Zeta’s Product Lines Total Activity Driver Product A Product B Processing & Testing Developing test programs $400,000 Engineering hours 10,000 2,500 7,500 Making probe cards 58,750 Development hours 4,000 400 3,600 Testing products 300,000 Test hours 20,000 2,000 18,000 Setups 40,000 Number of batches 100 55 45 Engineering design 80,000 Number of change orders 60 9 51 Handling lots 90,000 Number of...
Assuming activity-cost pools are used, what are the activity-cost driver rates for design changes, setups, and...
Assuming activity-cost pools are used, what are the activity-cost driver rates for design changes, setups, and inspections cost pools? a. $200 per change, $64 per setup, $5 per inspection b. $180 per change, $76 per setup, $4 per inspection c. $150 per change, $64 per setup, $4 per inspection d. $180 per change, $76 per setup, $5 per inspection e. $200 per change, $5 per setup, $64 per inspection Short Answer The following costs are attributed to the Quilt Company:...
Consider the following data for a clinical laboratory: Activity Annual Costs Cost Driver Test A Test...
Consider the following data for a clinical laboratory: Activity Annual Costs Cost Driver Test A Test B Test C Test D Total Units Allocation Receive specimen $             10,000 Number of tests 2,000 1,500 1,000 500 5,000 $            2.00 Equipment set-up                  25,000 Number of minutes per test 5 5 10 10 30 $      833.33 Run test               100,000 Number of minutes per test 1 5 10 20 36 $ 2,777.78 Record results                  10,000 Number of minutes per test 2 2 2 4 10              1,000 Transmit...
Pinter Company had the following environmental activities and product information: 1. Environmental activity costs Activity Costs...
Pinter Company had the following environmental activities and product information: 1. Environmental activity costs Activity Costs Design products (to reduce pollution) $ 72,000      Test for contamination 128,000      Treat toxic waste 400,000      Operate pollution control equipment 320,000      2. Driver data Solvent X Solvent Y Design hours 1,600           800           Testing hours 2,800           3,600           Pounds of waste 300           7,700           Machine hours 1,600           30,400           3. Other production data Solvent X Solvent Y Nonenvironmental production costs $1,344,000      $1,952,000      Units produced 160,000      160,000      Required: 1. Calculate...
Pinter Company had the following environmental activities and product information: 1. Environmental activity costs Activity Costs...
Pinter Company had the following environmental activities and product information: 1. Environmental activity costs Activity Costs Design products (to reduce pollution) $ 118,800      Test for contamination 211,200      Treat toxic waste 660,000      Operate pollution control equipment 528,000      2. Driver data Solvent X Solvent Y Design hours 2,600           4,000           Testing hours 4,700           12,900           Pounds of waste 500           21,500           Machine hours 2,600           85,400           3. Other production data Solvent X Solvent Y Nonenvironmental production costs $3,080,000      $6,028,000      Units produced 440,000      440,000      Required: 1. Calculate...
27) A preliminary stage cost driver links costs of resources consumed in an activity center to:...
27) A preliminary stage cost driver links costs of resources consumed in an activity center to: 1. batch-level activities 2. products 3. cost functions 4. focused factories 5. other activity centers 28)In the step method of service center allocation, the number of allocation steps equals the number of: 1. activities performed in all operating departments. 2. service centers. 3. operating departments. 4. service centers plus operating departments. 5. activities performed in all service centers. 30)Activity based costing: 1. uses fewer...
Activity Driver Driver Frequency Cost of Activity Direct Labor Direct Labor Hours                   50,000 $ 1,250,000.00...
Activity Driver Driver Frequency Cost of Activity Direct Labor Direct Labor Hours                   50,000 $ 1,250,000.00 Vacuuming Machine Hours                      2,000 $       62,000.00 Set-up Job                      5,000 $     200,000.00 Testing Tests made                      5,000 $       60,000.00 Customer service Orders taken                      1,200 $       30,000.00 Invoicing Invoices mailed                      2,400 $       48,000.00 Total $ 1,650,000.00 Activity Pool Opening Pump Repair Pool Cleaning Materials 350 1000 50 Direct Labor Hours 15 40 2 Vacuuming 3 0 2 Set-up 1 1 1 Testing...
Using activity analysis, AAA Company has identified the appropriate cost driver for maintenance costs in a...
Using activity analysis, AAA Company has identified the appropriate cost driver for maintenance costs in a factory as the number of machine hours. The maintenance costs have been observed as follows within the relevant range of 5,000 to 8,000 machine-hours. Month Maintenance Cost Machine Hours January $7,100 5,600 February $8,500 7,100 March $7,400 5,000 April $8,200 6,500 May $9,950 7,300 June $9,800 8,000 July $7,800 6,200 Using the high-low method, determine the variable maintenance cost per machine hour and the...
2) Gable Company uses three activity cost pools. Each pool has a cost driver. Information for...
2) Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 380,120 Number of machine hours 88,400 Designing costs 86,400 Number of design hours 9,000 Setup costs 74,672 Number of batches 525 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Product A Product B Product C Number of machine hours...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT