In: Accounting
Use the following information regarding Musketeer Novelties:
Activity Activity Costs Cost driver
Product design $212,000 1,500 design hours
Product scheduling $180,000 400 Set ups
Machining $600,000 5,000 machine hours
Material Handling $160,000 4,000 Pallet moved
Cost and activity with procuring 2,000 units of a Blueblob Bobblehead are as follows:
Direct Materials: $5,400
Direct Labor: $1,200
Design Hours: 5
Set-Ups: 3
Labor Hours 40
Machine Hours 18
Pallets Moved 10
United produced 400
1.) Develop activity rates for each of the four activities of Musketeer Novelties
2.) What is the product cost for ONE Blueblob Bobblehead using ABC (ACTIVITY BASE COSTING) rates for applying overhead?
3.)What is the product cost of one Blueblob bobblehead if Musketeer Novelties uses a plant-wide overhead rate based on machine hours. (assume 5,000 machine hours plant-wide)
1 | ||||
Activity | Activity Cost | Cost Driver | ABC Rate | |
Product design | 212000 | 1500 design hrs | 141.33 per Design hr | |
Product scheduling | 180000 | 400 set ups | 450 per setup | |
Machining | 600000 | 5000 machine hrs | 120 per machine hr | |
Material Handling Costs | 160000 | 4000 pallet moved | 40 per pallet moved | |
Total OH | 1152000 | |||
2 | ||||
Particulars | Amt ($) | |||
Direct Material | 5400 | |||
Direct Labour | 40 Labour hrs | 30 per Labour hr | 1200 | |
Overheads | NO's (A) | ABC Rate (B) | C = A x B | |
Product design | 5 hrs | 141.33 per Design hr | 707 | |
Product scheduling | 3 set ups | 450 per setup | 1350 | |
Machining | 18 Machine hrs | 120 per machine hr | 2160 | |
Material Handling Costs | 10 Pallets moved | 40 per pallet moved | 400 | 4617 |
Total Cost for producing 2000 units | 11217 | |||
NO. of Units | 2000 | |||
Product cost for ONE Blueblob Bobblehead (ABC) | 5.61 | |||
3 | ||||
If Musketeer Novelties uses a plant-wide overhead rate based on machine hours, then | ||||
Overhead Recovery Rate (OHRR) will be | ||||
Total Overhead Cost (a) | 1152000 | |||
Total Plant Machine hrs | 5000 | |||
OHRR | 230.40 | per machine hr | ||
Particulars | Amt ($) | |||
Direct Material | 5400.00 | |||
Direct Labour | 1200.00 | |||
Overhead Cost | 18 Machine hrs | 230.40 per Machine hr | 4147.20 | |
Total Cost for producing 2000 units | 10747.20 | |||
NO. of Units | 2000 | |||
Product cost for ONE Blueblob Bobblehead (ABC) | 5.37 |