Question

In: Finance

We have two independent and mutually exclusive projects, A and B. Project A requires an initial...

We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1500, and will yield $800 of cash inflows for the next three years. Project B requires an initial investment of $5000, and will yield $1,500 of cash inflows for the next five years. The required return on each project is 10%.                                                                                                                                        (13 marks total)

a.   What are the net present values of Project A and Project B?                

b.   What is the problem with using the NPV investment criterion in this case? What alternative criterion should be used?                                                               (1 mark)

c.   Which project should be chosen?                                              

The cash flows and required return given are all in nominal terms. Given that the inflation rate is 3%, answer the following questions:

d.   What is the real rate of return based on the exact Fisher equation?       (1 mark)

e.   What are the real cash flows from Project A and Project B?                

f.    What are the real net present values of Project A and Project B? (Hint: The real NPV should be the same as the nominal NPV.)                                             

g.         Which project should be chosen based on the real cash flows and real rate of return?          

Solutions

Expert Solution

a)

Statement showing NPV of project A

Year Cash flow PVIF @ 10% PV
A B C = A x B
1 800 0.9091 727.27
2 800 0.8264 661.16
3 800 0.7513 601.05
Total fo PV 1989.48
Less : Initial Investment 1500
NPV 489.48

Thus NPV of project A = $489.48

Statement showing NPV of project B

Year Cash flow PVIF @ 10% PV
A B C = A x B
1 1500 0.9091 1363.64
2 1500 0.8264 1239.67
3 1500 0.7513 1126.97
4 1500 0.6830 1024.52
5 1500 0.6209 931.38
Total fo PV 5686.18
Less : Initial Investment 5000
NPV 686.18

Thus NPV of project B = $686.18

b) Here both the project have different life period. i.e project A is of 3 years and project B has 5 years. Thus NPV method might not provide proper solution. Instead equivalent annual benefit should be found for both the project

Equivalent annual benefit for project A = NPV of project A / PVIFA(10%,3)

=489.48/2.4869

= 196.83 $

Equivalent annual benefit for project B = NPV of project B / PVIFA(10%,5)
= 686.18/3.7908

= 181.01 $

c) Since Equivalent annual benefit for project A is more than Equivalent annual benefit for project B , project A should be selected

d) Real rate of return = (1+ Nominal rate of interest)/(1+ Inflation rate) - 1

Nominal rate of interest = 10%

Inflation rate = 3%

Real rate of return = (1+10%)/(1+3%) - 1

=(1+0.1)/(1+0.03) - 1

= 1.1/1.03 - 1

= 1.067961 - 1

= 0.067961

i.e 6.7961 %


Related Solutions

We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1500, and will yield $800 of cash inflows for the next three years. Project B requires an initial investment of $5000, and will yield $1,500 of cash inflows for the next five years. The required return on each project is 10%. a. What are the net present values of Project A and Project B? b. What is the problem with using the...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1000, and will yield $500 of cash inflows for the next three years. Project B requires an initial investment of $3,500, and will yield $1,000 of cash inflows for the next five years. The required return on both projects is 10%.                                                                                                      (13 marks total) a. What are the net present values of Project A and Project B? b. What is...
Projects A and B are mutually exclusive projects. Project A requires an initial investment today of...
Projects A and B are mutually exclusive projects. Project A requires an initial investment today of $300 and generates expected cash flows of $100 at the end of each of the next 5 years. Project B requires an initial investment today of $130 and generates expected cash flows of $55 at the end of each of the next 5 years. a. If you plotted the NPV profiles, what would be the "crossover rate" in the graph? (Note you are not...
1. There are two mutually exclusive projects. Project A requires a $600,000 initial investment and is...
1. There are two mutually exclusive projects. Project A requires a $600,000 initial investment and is expected to provide $120,000 annual net cash inflows for 6 years. Project B requires a $740,000 initial investment and is expected to provide $200,000 annual net cash inflows for 4 years. Which project should you accept according to IRR method when your cost of capital is 10%? A. Project A B. Project B C. Both D. Neither of these 2. Leveraged IRR: A. estimates...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project A provides cash inflows of $32,000 a year for three years while Project B produces a cash inflow of $44,400 a year for two years. Which project(s) should be accepted if the discount rate is 10 percent? What if the discount rate is 12.5 percent?
A company is considering two mutually exclusive projects Adept and Boffo. Project Adept requires an initial...
A company is considering two mutually exclusive projects Adept and Boffo. Project Adept requires an initial investment of $100,000 and is expected to generate after-tax cash flows of $45,000 per year for three years. Project Boffo requires an initial investment of $150,000 and is expected to generate after-tax cash flows of $50,000 per year for four years. The appropriate discount rate is 10%. What is the crossover rate for projects Adept and Boffo? 4.06% 16.65% 12.59% 7.77%
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial investment for...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial investment for each project is $40,000. Project A will generate cash inflows equal to $15,625 at the end of each of the next five years; Project B will generate only one cash inflow in the amount of $79,500 at the end of the fifth year (i.e., no cash flows are generated in the first four years). The required rate of return of Ace Inc. is 10...
You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost)...
You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost) associated with Project A is $60,000, whereas the initial cash outlay associated with Project B is $80,000. The required rate of return for both projects is 10%. The expected annual free cash flows from each project are as follows: Year Project A Project B 0 - 60,000 -80,000 1 13,000 15,000 2 13,000 15,000 3 13,000 15,000 4 13,000 15,000 5 13,000 15,000 6...
Mutually exclusive Projects Project A Project B Project C Initial cash Outlay        (50,000)       (60,000)...
Mutually exclusive Projects Project A Project B Project C Initial cash Outlay        (50,000)       (60,000)        (40,000) Required Rate of Return 11% 8% 13% Cash Flows:       Inflow Year 1 10,000 30000 8,000 Inflow Year 2 15,000 50000 20,000 Inflow Year 3 20,000 5000 20,000 Inflow Year 4 25,000 5000 20,000 Inflow Year 5 30,000 2000 15,000 Step 1 Your first assignment as a financial analysis manager at Caledonia Products is to evaluate three new capital budget proposals. You have...
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows...
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows of CF0, CF1, CF2, CF3, CF4, CF5. (Years 0-5). Project B has cash flow of CF0, CF1, CF2, CF3. The discount rate for the projects is 10.5%. a) Analyze these two projects and recommend a project to accept. b) Carefully outline all your analysis and reasoning and discuss your methodologies for arriving at your solution in detail. Project A Project B CF0 (4,650.00) (8,300.00)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT