Question

In: Accounting

A quality control activity analysis indicated the following four activity costs of a hotel. Verifying credit...

A quality control activity analysis indicated the following four activity costs of a hotel.

Verifying credit card information

523,600

Customer service training

261,800

Discounting room rates due to poor customer service

130,900

Correcting charges to customer invoices

392,700

Total

$1,309,000

Sales are $7,700,000 for the year. Prepare a cost of quality report.

Present percentage values to one decimal place.

Cost of Quality Report

Quality Cost Classification

Quality Cost

Percent of Total Quality Cost

Percent of Total Sales

Prevention

$

%

%

Appraisal

$

%

%

Internal Failure

$

%

%

External Failure

$

%

%

Total

$


Solutions

Expert Solution

Cost of Quality Report
Quality Cost Classification Quality Cost Percent of Total Quality Cost Percent of Total Sales
Prevention 261800 20.00% 3.4%
Appraisal 523600 40.00% 6.8%
Internal Failure 392700 30.00% 5.1%
External Failure 130900 10.00% 1.7%
Total 1309000
Sales 7700000
Prevention Costs are costs incurred to avoid or minimize the number of defects at first place.
So, Customer Service Training is Prevention Cost
Appraisal Costs are costs incurred to identify defective products before they are shipped to customers
Verifying CC information
Internal Failure costs incurred to remove defects from the products
Correcting Charges to customer invoices
External Failure Costs includes warranties, replacements etc
Discounting Room Rates due to poor customer Services are external failure

Related Solutions

A quality control activity analysis indicated the following four activity costs of a hotel: Inspecting cleanliness...
A quality control activity analysis indicated the following four activity costs of a hotel: Inspecting cleanliness of rooms $468,000 Processing lost customer reservations 156,000 Rework incorrectly prepared room service meal 78,000 Employee training 78,000 Total $780,000 Sales are $3,900,000. Prepare a cost of quality report. Round percent of sales to one decimal place.
A quality control activity analysis indicated the following four activity costs of a manufacturing department: 1...
A quality control activity analysis indicated the following four activity costs of a manufacturing department: 1 Rework $37,440.00 2 Inspecting incoming raw materials 51,840.00 3 Warranty work 25,920.00 4 Process improvement effort 172,800.00 5 Total $288,000.00 Amount Descriptions Appraisal External failure Internal failure Lead time Prevention Setup time Sales are $1,200,000. Prepare a cost of quality report. Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries. Round percents to one decimal...
Schedule of Activity Costs Quality Control Activities Activity Cost Product testing $55,000 Assessing vendor quality 26,000...
Schedule of Activity Costs Quality Control Activities Activity Cost Product testing $55,000 Assessing vendor quality 26,000 Recalls 18,000 Rework 29,000 Scrap disposal 8,000 Product design 30,000 Training machine operators 46,000 Warranty work 12,000 Process audits 22,000 ​ From the provided schedule of activity costs, compute the percentage of non-value-added activities. Round to one decimal place. HTML EditorKeyboard Shortcuts
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $48,600 Training of machine operators...
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $48,600 Training of machine operators 26,900 Processing returned products 19,800 Scrap processing (disposal) 25,700 Rework 6,600 Preventative maintenance 31,100 Product design 45,200 Warranty work 8,000 Finished goods inspection 23,600 From the above schedule of activity costs, determine the non-value-added costs. $52,100 $120,900 $60,100 $235,500
Read the following control activity and answer the questions below: The audit client indicated that they...
Read the following control activity and answer the questions below: The audit client indicated that they reviewed actual sales revenue data against forecasts on a monthly basis. Required: a) Identify what type of control activity this is and state whether it is a preventative or detective control. b) Suggest an appropriate test of control for this specific control activity. c) For part 2 above, identify which audit procedure is being used in your suggested test of control. d) Assume that...
Identify and explain the four control levels associated with activity-based costing
Identify and explain the four control levels associated with activity-based costing
This problem is based on one of the topics, Costs of Quality, in chapter four of...
This problem is based on one of the topics, Costs of Quality, in chapter four of your class textbook - Managing Quality: Integrating the Supply Chain, 6th Edition by S. Thomas Foster. An example is solved for you in the text. Study the chapter and solve the following problems. Statement of the problem The Colorado Manufacturing Company of Boulder, CO has gathered the following quality-related costs. You are hired as a consultant to evaluate these costs and to make recommendations...
how can variance analysis be used to analyze and control costs
how can variance analysis be used to analyze and control costs
Fischer Company identified the following activities, costs, and activity drivers: Activity Expected Costs Expected Activity Handling...
Fischer Company identified the following activities, costs, and activity drivers: Activity Expected Costs Expected Activity Handling Parts 425,000 25,00 parts in stock Inspecting Parts 390,000 940 batches Processing Purchase Orders 220,000 440 orders Designing Packaging 230,000 5 models a. Compute a plantwide overhead rate assuming the company assigns overhead based on 70,000 budgeted direct labor hours (Round to two decimals). b. Compute separate rates for each of the four activities using the activity-based costing.
Describe the relationship between the four (4) main costs of quality and how are they are...
Describe the relationship between the four (4) main costs of quality and how are they are related.                                                                                                         