In: Accounting
A quality control activity analysis indicated the following four activity costs of a manufacturing department:
|
1 |
Rework |
$37,440.00 |
|
2 |
Inspecting incoming raw materials |
51,840.00 |
|
3 |
Warranty work |
25,920.00 |
|
4 |
Process improvement effort |
172,800.00 |
|
5 |
Total |
$288,000.00 |
| Amount Descriptions | |
| Appraisal | |
| External failure | |
| Internal failure | |
| Lead time | |
| Prevention | |
| Setup time |
Sales are $1,200,000. Prepare a cost of quality report. Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries. Round percents to one decimal place.
|
Cost of Quality Report |
|
1 |
Quality Cost Classification |
Quality Cost |
Percent of Total Quality Cost |
Percent of Total Sales |
|
2 |
||||
|
3 |
||||
|
4 |
||||
|
5 |
||||
|
6 |
Total |