Question

In: Accounting

PLEASE ANSWER IN EXCEL WITH WORK. An investor has projected three possible scenarios for a project...

PLEASE ANSWER IN EXCEL WITH WORK. An investor has projected three possible scenarios for a project as follows: Pessimistic- NOI will be $200,000 the first year, and then decrease 2 percent per year over a five year holding period. The property will sell for 1.8 million after five year. Most Likely- NOI will be level at $200,000 per year for the next five years(level NOI) and the property will sell for 2 million. Optimistic- NOI will be 200,000 the first year and increase 3 percent per year over a 5 year holding period. The property will then sell for 2.2 million The asking price for the property is 2 million. The investor thinks there is about a 30 percent probability for the pessimistic scenario, a 40 percent probability for the most likely scenario, and a 30 percent probability for the optimistic scenario. a. Compute the IRR for each scenario. b. Compute the expected IRR c. Compute the variance and standard deviation of the IRRs. d. Would this project be better than one with a 12 percent expected return and a standard deviation of 4 percent?

Solutions

Expert Solution

Answer:

  • IRR (pessimistic) = 7.93%
  • IRR (most likely) = 10.00%
  • IRR (optimistic) = 12.12%
  • Expected IRR = 10%
  • Variance of IRR = 0.0263%
  • Standard deviation of IRR = 1.6216%
  • Current project is better than alternative project

Step-by-step explanation

The IRR for each scenario is shown in the table below.

The IRR was calculated using the Excel function IRR().

The expected IRR is 0.30(7.93%) + 0.4(10.00%) + 0.3(12.12%) = 10%

The variance is 0.30(7.93%-10%)2 + 0.4(10.00%-10%)2 + 0.3(12.12%-10%)2 = 0.0263%

The standard deviation is (0.0263%)0.5 = 1.6216%

Comparing the risk-return characteristics:

  • Alternative project generates a return of 12% / 4% = 3 times per unit of risk
  • Current project generates a return of 10% / 1.62% = 6.18 times per unit of risk.

.

Therefore, the current project is better than the alternative project.


Related Solutions

An investor has three possible scenarios for a project as follows: Pessimistic – NOI will be...
An investor has three possible scenarios for a project as follows: Pessimistic – NOI will be $220,000 for the first year, and then decrease by 3 percent per year over a five-year holding period. The property will sell for $1.7 million after five years. Most likely – NOI will be level at $220,000 per year for the next five years and the property will sell for $2.5 million Optimistic – NOI will be $220,000 the first year and increase 3...
Project: replace existing equipment There are three possible scenarios for the cost savings the company could...
Project: replace existing equipment There are three possible scenarios for the cost savings the company could capture with the new equipment: Scenario 1: the company captures cost savings of $40,000/year (30% likelihood of occurring), Scenario 2: cost savings of $35,000/year (10% likelihood), and Scenario 3: cost savings of $30,000/year (60% likelihood). Initial investment: ($200,000) for replacement equipment, plus a positive revenue of $20,000 selling the replaced equipment in the used equipment market (NOTE: treat as scrap value at beginning of...
(Please answer this question in an excel format if possible.) Please provide very detailed explanation and...
(Please answer this question in an excel format if possible.) Please provide very detailed explanation and answers if possible. The Poster Bed Company believes that its industry can best be classified as monopolistically competitive. An analysis of the demand for its canopy bed has resulted in the following estimated demand function for the bed: P ¼ 1760 12Q The cost analysis department has estimated the total cost function for the poster bed as TC ¼ 1 3 Q3 15Q2 þ...
(Please answer this question in an excel format if possible.) The Poster Bed Company believes that...
(Please answer this question in an excel format if possible.) The Poster Bed Company believes that its industry can best be classified as monopolistically competitive. An analysis of the demand for its canopy bed has resulted in the following estimated demand function for the bed: P ¼ 1760 12Q The cost analysis department has estimated the total cost function for the poster bed as TC ¼ 1 3 Q3 15Q2 þ 5Q þ 24;000 a. Calculate the level of output...
Can you please answer the question in an excel with the calculation if possible. T&J manufacturing...
Can you please answer the question in an excel with the calculation if possible. T&J manufacturing has a factory that produces custom kitchen cabinets. It has multiple product lines. Materials and labor for the cabinets are determined by each job. To simplify the assignment, we will assume the following average costs. The materials include $1,000 for the wood and other direct materials of $200. Both items listed are on a per job basis. It requires 20 hours of labor on...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 123,422.00 123,422.00 123,422.00 123,422.00 123,422.00 Cost of Goods 69,079.00 69,079.00 69,079.00 69,079.00 69,079.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 22,072.20 22,072.20 22,072.20 22,072.20 22,072.20 Investment in NWC 1,152.00 540.00 540.00 540.00 540.00 540.00 Investment in Gross PPE 110,361.00 The firm has a capital structure of 48.00% debt and 52.00% equity. The cost of debt is 9.00%, while the cost of...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 136,856.00 136,856.00 136,856.00 136,856.00 136,856.00 Cost of Goods 62,752.00 62,752.00 62,752.00 62,752.00 62,752.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 20,519.20 20,519.20 20,519.20 20,519.20 20,519.20 Investment in NWC 1,171.00 542.00 542.00 542.00 542.00 542.00 Investment in Gross PPE 102,596.00 The firm has a capital structure of 33.00% debt and 67.00% equity. The cost of debt is 8.00%, while the cost of...
A firm has projected the following financials for a possible project: Year 0 1 2 3...
A firm has projected the following financials for a possible project: Year 0 1 2 3 4 5 Sales 128,086 128,086 128,086 128,086 128,086 COGS 60,876 60,876 60,876 60,876 60,876 S&A 30,000 30,000 30,000 30,000 30,000 Depreciation 22,696.80 22,696.80 22,696.80 22,696.80 22,696.80 Investment in NWC 1,126.00 598 598 598 598 598 Investment in Gross PPE 113,484.00 The firm has a capital structure of 36.00% debt and 64.00% equity. The cost of debt is 10.00%, while the cost of equity is...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 123,751.00 123,751.00 123,751.00 123,751.00 123,751.00 Cost of Goods 69,125.00 69,125.00 69,125.00 69,125.00 69,125.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 20,811.80 20,811.80 20,811.80 20,811.80 20,811.80 Investment in NWC 1,108.00 576.00 576.00 576.00 576.00 576.00 Investment in Gross PPE 104,059.00 The firm has a capital structure of 43.00% debt and 57.00% equity. The cost of debt is 10.00%, while the cost of...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 124,757.00 124,757.00 124,757.00 124,757.00 124,757.00 Cost of Goods 65,261.00 65,261.00 65,261.00 65,261.00 65,261.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 20,786.40 20,786.40 20,786.40 20,786.40 20,786.40 Investment in NWC 1,197.00 559.00 559.00 559.00 559.00 559.00 Investment in Gross PPE 103,932.00 The firm has a capital structure of 34.00% debt and 66.00% equity. The cost of debt is 10.00%, while the cost of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT