Question

In: Accounting

Project: replace existing equipment There are three possible scenarios for the cost savings the company could...

Project: replace existing equipment

There are three possible scenarios for the cost savings the company could capture with the new equipment:

Scenario 1: the company captures cost savings of $40,000/year (30% likelihood of occurring),

Scenario 2: cost savings of $35,000/year (10% likelihood), and

Scenario 3: cost savings of $30,000/year (60% likelihood).

Initial investment: ($200,000) for replacement equipment, plus a positive revenue of $20,000 selling the replaced equipment in the used equipment market (NOTE: treat as scrap value at beginning of project)

Project cost of capital: WACC of 7% + a project risk premium of +1%

Life of project: 10 years

1A. Calculate the project cash flows: NOTE: Use a weighted average of the three scenarios’ savings as the annuity cash flow for the project:

Cash flow for project = (CF scenario 1 x weight) + (CF scenario 2 x weight) + (CF scenario 3 x weight)

1B. Calculate NPV: Using the information provided and your cash flow estimate from #1 above, calculate the company’s NPV for the project. Show your steps!

1C. Calculate IRR: Given the information above, what is the IRR of the project? (show your steps)

NOTE: Remember that the IRR is the NPV for the project, where NPV = zero. You use the NPV equation, with NPV = zero, and solve for the PVIFA multiplier. Last, look up the PVIFA in the table for the project # of years.

Solutions

Expert Solution

1) Project cash flows in this question will be equal to weighted average of three scenario's savings.

CF scenario 1 = $40,000, Weight = 30% or 0.30

CF scenario 2 = $35,000, Weight = 10% or 0.10

CF scenario 3 = $30,000, Weight = 60% or 0.60

Annual Cash Flows =  (CF scenario 1 x weight) + (CF scenario 2 x weight) + (CF scenario 3 x weight)

= ($40,000*0.30)+($35,000*0.10)+($30,000*0.60)

= $12,000+$3,500+$18,000 = $33,500

2) Net Present value (NPV) = PV of annual cash flows - PV of cash outflows

Project cost of capital = 7%+1% = 8%

PV of cash Inflows = Annual cash flows*PVAF(8%,10 yrs)

= $33,500*6.7101 = $224,788

PV of cash outflows = Replacement cost - Sale of replaced equipment

= $200,000 - $20,000 = $180,000

NPV = $224,788 - $180,000 = $44,788

3) As IRR is the NPV for the project, where NPV = zero. The present value of cash outflow will be equal to present value of cash inflow at IRR. The IRR is calculated as follows:-

PV of cash Inflows = PV of cash Outflows

Annual Cash Flows*PVAF(10 yrs,IRR) = $180,000

$33,500*PVAF(10 yrs,IRR) = $180,000

PVAF(10 yrs,IRR) = $180,000/$33,500

PVAF(10 yrs,IRR) = 5.3731

From the annuity table the value of 5.3731 is between 13% and 14%. Therefore the IRR will be 13.25%(approx.)


Related Solutions

A company is considering whether to replace one of its construction equipment. • The existing equipment...
A company is considering whether to replace one of its construction equipment. • The existing equipment has a current cost of $15,000, which declines by 20% each year for three years. The operating cost for this equipment is $20,000 for year 1, $8,000 for year 2, and $12,000 for year 3. • The proposed equipment will cost $50,000, last five years, and has a market value that declines by 20% each year. The operating cost for the proposed equipment is...
An investor has three possible scenarios for a project as follows: Pessimistic – NOI will be...
An investor has three possible scenarios for a project as follows: Pessimistic – NOI will be $220,000 for the first year, and then decrease by 3 percent per year over a five-year holding period. The property will sell for $1.7 million after five years. Most likely – NOI will be level at $220,000 per year for the next five years and the property will sell for $2.5 million Optimistic – NOI will be $220,000 the first year and increase 3...
Monty Industries is considering the purchase of new equipment costing $1,300,000 to replace existing equipment that...
Monty Industries is considering the purchase of new equipment costing $1,300,000 to replace existing equipment that will be sold for $194,000. The new equipment is expected to have a $223,000 salvage value at the end of its 4-year life. During the period of its use, the equipment will allow the company to produce and sell an additional 32,600 units annually at a sales price of $27 per unit. Those units will have a variable cost of $15 per unit. The...
Company A plans to replace with one of their current equipment with one of the three...
Company A plans to replace with one of their current equipment with one of the three options shown in the table. Option A B C Initial Cost 200 350 475 Annual Operation Cost 450 275 300 Salvage Value 75 60 80 Estimated Life in Year 20 20 20 Perform AW analysis to figure out which option should company A choose. The rate of return is 8% per year compounded Monthly. Please see correct answer below how do you get this?...
PLEASE ANSWER IN EXCEL WITH WORK. An investor has projected three possible scenarios for a project...
PLEASE ANSWER IN EXCEL WITH WORK. An investor has projected three possible scenarios for a project as follows: Pessimistic- NOI will be $200,000 the first year, and then decrease 2 percent per year over a five year holding period. The property will sell for 1.8 million after five year. Most Likely- NOI will be level at $200,000 per year for the next five years(level NOI) and the property will sell for 2 million. Optimistic- NOI will be 200,000 the first...
Blue Spruce Industries is considering the purchase of new equipment costing $1,207,000 to replace existing equipment...
Blue Spruce Industries is considering the purchase of new equipment costing $1,207,000 to replace existing equipment that will be sold for $188,800. The new equipment is expected to have a $203,000 salvage value at the end of its 5-year life. During the period of its use, the equipment will allow the company to produce and sell an additional 38,800 units annually at a sales price of $21 per unit. Those units will have a variable cost of $14 per unit....
Blue Spruce Industries is considering the purchase of new equipment costing $1,248,000 to replace existing equipment...
Blue Spruce Industries is considering the purchase of new equipment costing $1,248,000 to replace existing equipment that will be sold for $181,600. The new equipment is expected to have a $210,000 salvage value at the end of its 5-year life. During the period of its use, the equipment will allow the company to produce and sell an additional 38,400 units annually at a sales price of $29 per unit. Those units will have a variable cost of $14 per unit....
The company is considering a new assembly line to replace the existing assembly line. The existing...
The company is considering a new assembly line to replace the existing assembly line. The existing assembly line was installed 3 years ago at a cost of $90,000; it was being depreciated under the straight-line method. The existing assembly line is expected to have a usable life of 6 more years. The new assembly line costs $120,000; requires $9,000 in installation costs and $5,000 in training fees; it has a 6-year usable life and would be depreciated under the straight-line...
Macon Company is considering a new assembly line to replace the existing assembly line. The existing...
Macon Company is considering a new assembly line to replace the existing assembly line. The existing assembly line was installed 3 years ago at a cost of $90,000; it was being depreciated under the straight-line method. The existing assembly line is expected to have a usable life of 6 more years. The new assembly line costs $120,000; requires $9,000 in installation costs and $5,000 in training fees; it has a 6-year usable life and would be depreciated under the straight-line...
Macon Company is considering a new assembly line to replace the existing assembly line. The existing...
Macon Company is considering a new assembly line to replace the existing assembly line. The existing assembly line was installed 3 years ago at a cost of $90,000; it was being depreciated under the straight-line method. The existing assembly line is expected to have a usable life of 6 more years. The new assembly line costs $120,000; requires $9,000 in installation costs and $5,000 in training fees; it has a 6-year usable life and would be depreciated under the straight-line...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT