Question

In: Finance

Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0...

Hodgkiss Enterprises has gathered projected cash flows for two projects.

Year Project I Project J
0 –$ 256,000 –$ 256,000
1 114,400 88,600
2 104,200 99,600
3 88,200 101,600
4 77,200 108,600

At what interest rate would the company be indifferent between the two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
  

Interest rate             %

Which project is better if the required return is above this interest rate?
  

Solutions

Expert Solution

Indifference rate is rate at which NPV of both project is same

Project I
Discount rate 16.474%
Year 0 1 2 3 4
Cash flow stream -256000.000 114400.000 104200.000 88200.000 77200.000
Discounting factor 1.000 1.165 1.357 1.580 1.840
Discounted cash flows project -256000.000 98219.135 76808.252 55818.586 41946.683
NPV = Sum of discounted cash flows
NPV Project I = 16792.66
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project J
Discount rate 16.474%
Year 0 1 2 3 4
Cash flow stream -256000.000 88600.000 99600.000 101600.000 108600.000
Discounting factor 1.000 1.165 1.357 1.580 1.840
Discounted cash flows project -256000.000 76068.316 73417.484 64298.960 59007.898
NPV = Sum of discounted cash flows
NPV Project J = 16792.66
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

So interest rate for indifference = 16.474%

At a rate higher than this Project I has higher NPV hence it should be selected

For eg at 17%

Project I
Discount rate 17.000%
Year 0 1 2 3 4
Cash flow stream -256000.000 114400.000 104200.000 88200.000 77200.000
Discounting factor 1.000 1.170 1.369 1.602 1.874
Discounted cash flows project -256000.000 97777.778 76119.512 55069.483 41197.784
NPV = Sum of discounted cash flows
NPV Project I = 14164.56
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project J
Discount rate 17.000%
Year 0 1 2 3 4
Cash flow stream -256000.000 88600.000 99600.000 101600.000 108600.000
Discounting factor 1.000 1.170 1.369 1.602 1.874
Discounted cash flows project -256000.000 75726.496 72759.150 63436.049 57954.395
NPV = Sum of discounted cash flows
NPV Project J = 13876.09
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

Related Solutions

Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 –$ 259,000 –$ 259,000 1 114,100 90,400 2 104,800 99,900 3 88,800 101,900 4 77,800 108,900 At what interest rate would the company be indifferent between the two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)    Interest rate             % Which project is better if the required return is above this interest...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 -269,000 -269,000 1 113,100 96,400 2 106,800 100,900 3 90,800 102,900 4 79,800 109,900 At what interest rate would the company be indifferent between the two projects? Which project is better if the required return is above this interest rate?
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 220 ?$ 220 1 100 120 2 100 120 3 100 120 4 100 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (260 ) $ (260 ) 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project A...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A - $ 100 $26 $28 $42 $52 B -$ 100    $52 $42 $28    $18 a. What is the IRR of each? project? b. What is the NPV of each project at your cost of? capital? c. At what cost of capital are you indifferent between the two? projects? d. What should you? do?
22) Textiles Unlimited has gathered projected cash flows for two projects. At what interest rate would...
22) Textiles Unlimited has gathered projected cash flows for two projects. At what interest rate would the company be indifferent between the two projects? Year /Cash Flow A /Cash Flow B 0 /-$10,000.00 /-$5,000.00 1/ $142,200.00/ $52,600.00 2/ $34,600.00/ $139,400.00 3/ $38,700.00/ $35,500.00 A) 22.41 percent B) 19.16 percent C) 29.11 percent D) -15.14 percent E) -19.49percent
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT