In: Finance
Merton Clinic managers are analyzing a new project. The project’s most likely NPV is $120,000. The project cost of capital (discount rate) is 10 percent.
Probability NPV
0.05 ($800,000)
0.25 200,000
0.50 400,000
0.20 600,000
What is the project’s standard deviation?
a. -$300,000
b. $300,485
c. *$291,719
d. $281,593
e. $300,000
Solution :
The project's Standard Deviation is = $ 291,719.0429
= $ 291,719 ( when rounded off to the nearest whole number )
The solution is Option c. $ 291,719
Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.