Question

In: Finance

If you were told that each project’s cost of capital was 12%, which project should be selected using the NPV criteria? What is each project’s IRR?

Corporate Finance

1. ABC Pvt. Ltd. is considering two mutually exclusive capital investments. The project’s expected net cash flows are as follows:

Expected Cash Flows

Year

Project A

Project B

0

-375

-575

1

-300

190

2

-200

190

3

-100

190

4

600

190

5

600

190

6

926

190

7

-200

0

If you were told that each project’s cost of capital was 12%, which project should be selected using the NPV criteria? What is each project’s IRR? What is the regular payback period for these two projects? What is the profitability index for each project if the cost of capital is 12%? The answer should be a min of 800 words in Computerized word format

Solutions

Expert Solution

Net present value of project (A)

Years Cash flows $ PVIF@12% PV ($)
0 - 375 1.0000 -375.00
1 -300 0.8929 -267.87
2 -200 0.7972 -159.44
3 -100 0.7118 -71.18
4 600 0.6355 381.30
5 600 0.5674 340.44
6 926 0.5066 469.11
7 -200 0.4523 -90 46
NPV (Sum up) $226.90

Net present value of project (B)

NPV = - initial cost + ACF(PVIF12%,6)

NPV = -575 + 190(PVIF12%,6)

NPV = - 575 + 190*4.1114

NPV = $206.17

Based on NPV Creterian Project (A) should be selected , because of its higher NPV

Calculation of IRR of both the projects , using Excel function of IRR would be as follows

Regular payback periods

Project A = 4 years + 375/600 = 4.625 years

Project B = 575/190 = 3.03 years

Profitability index (PI)

PI = PV cash inflow/initial costs

PI (A) = 601.90/375 = 1.6051

PI (B) = 781.17/575 = 1.3586


Related Solutions

What is the payback period, NPV, IRR of A. Using this information, should we accept Project...
What is the payback period, NPV, IRR of A. Using this information, should we accept Project A. Why or why not. Given the following information answer the question above. The discount rate is 10 percent.      PROJECT A       t           Cash Flow       0          (150,000)        1          40,000           2          40,000              3          40,000          4           40,000           5            40,000               ROUND TO NEAREST DOLLAR OR TEN %
What does it mean when a capital budgeting project has an NPV of zero? The project’s...
What does it mean when a capital budgeting project has an NPV of zero? The project’s IRR will be less than the required hurdle rate for the project The firm’s stockholders will earn a positive return, but it will be less than their required return, given the risk of the investment The firm’s security holders will earn their required rate of return, given the risk of the investment The firm’s stockholders will earn a negative return none of the above
When a capital budgeting project has an NPV of zero, what does this mean? The project’s...
When a capital budgeting project has an NPV of zero, what does this mean? The project’s IRR will be less than the required hurdle rate for the project The firm’s stockholders will earn a positive return, but it will be less than their required return, given the risk of the investment The firm’s stockholders will earn a negative return The firm’s security holders will earn their required rate of return, given the risk of the investment none of the above
why is the NPV a better method than using the IRR for project rankings? which would...
why is the NPV a better method than using the IRR for project rankings? which would you rather use? how can you apply the capital budgeting techniques to your purchase of a rental property?
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Inital Outlay (105,000.000) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% Your company is considering three independent projects. Given the following cash flow information,...
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Initial Outlay (105,000.00) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% NPV = $75,228.32 $77,364.07 -$2,531.00 $69,006.08 Answer: Project B How to show work...
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what...
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what have you accomplished for your shareholders? 1A. A semiannual bond pays a 4.5 % coupon for the next 27 years. If investors want a 7.3% return, what are they willing to pay for the bond?
Please explain what is Internal rate of return (IRR), Cost of Capital, NPV, and the Discount...
Please explain what is Internal rate of return (IRR), Cost of Capital, NPV, and the Discount Rate. How are they associated when deciding on an investment opportunity?
What is the NPV for a project if its cost of capital is 0 percent and...
What is the NPV for a project if its cost of capital is 0 percent and its initial after-tax cost is $5,000,000 and it is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4? Select one: a. $6,700,000 b. $137,053 c. $1,700,000 d. $371,764 Which of the following is TRUE? Select one: a. The Gordon model assumes that the value of a share of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT