Question

In: Finance

You are evaluating an investment project and learn the following: The project’s NPV at a discount...

You are evaluating an investment project and learn the following: The project’s NPV at a discount rate of 16% is +$35,879 The project’s NPV at a discount rate of 20% is +$12,356 The project’s NPV at a discount rate of 22% is -$1,923 Based on (i)-(iii) above you know the project’s IRR must be:

a.

Less than 16%

b.

Greater than 22%

c.

Between 16% and 20%

d.

Between 20% and 22%

e.

Exactly 20%

Solutions

Expert Solution

IRR Is rate at which NPV of the project is zero

The answer is between 20% and 22%


Related Solutions

Shopify, Inc. is considering a project that has the following cash flows. The project’s appropriate discount...
Shopify, Inc. is considering a project that has the following cash flows. The project’s appropriate discount rate is 6.7%. Year 0 1 2 3 4 Cash flows -$9200 $3300 $3400 $0 $4100 Calculate the project's NPV (round your answer to the nearest whole number). Answer:
What is the NPV of the following project if the discount rate is 10%? Round to...
What is the NPV of the following project if the discount rate is 10%? Round to the nearest cent. Investment today: $-150,000; Cash flow in year 1: $60,000; Cash flow in year 2: $75,000; Cash flow in year 3: $60,000
If the applicable discount rate is 15%, what is the NPV of the following investment? Round...
If the applicable discount rate is 15%, what is the NPV of the following investment? Round to the nearest cent. The project is expected to cost $81,000 immediately, and generate the following annual cash flows: Year 1: $29,000 Year 2: $35,000 Year 3: $64,000 Year 4: $21,000 You want to start an organic garlic farm. The farm costs $300,000, to be paid in full immediately. Year 1 cash flows will be $36,000, and grow at 6% a year into year...
If you were told that each project’s cost of capital was 12%, which project should be selected using the NPV criteria? What is each project’s IRR?
Corporate Finance1. ABC Pvt. Ltd. is considering two mutually exclusive capital investments. The project’s expected net cash flows are as follows:Expected Cash FlowsYearProject AProject B0-375-5751-3001902-2001903-1001904600190560019069261907-2000If you were told that each project’s cost of capital was 12%, which project should be selected using the NPV criteria? What is each project’s IRR? What is the regular payback period for these two projects? What is the profitability index for each project if the cost of capital is 12%? The answer should be a...
A). You are evaluating a project with the following cash flows: initial investment is $-12, and...
A). You are evaluating a project with the following cash flows: initial investment is $-12, and the expected cash flows for years 1 - 3 are $10, $11 and $17 (all cash flows are in millions of dollars). What is this projects NPV? The company's WACC is 10%. B). You are evaluating a project with an initial investment of $16.9 million dollars, and expected cash flows of $7 million dollars each for years 1-3. What is the project's simple payback?...
As the financial advisor to Beena you are evaluating the following new investment in a project....
As the financial advisor to Beena you are evaluating the following new investment in a project. • The project has a useful life of 12 years. • Land costs $6m and is estimated to have a resale value of $10m at the completion of the project. • Buildings cost $5m, with allowable depreciation of 10% pa reducing balance and a salvage value of $0.9m. • Equipment costs $4m, with allowable depreciation of 20% pa reducing balance and a salvage value...
What does it mean when a capital budgeting project has an NPV of zero? The project’s...
What does it mean when a capital budgeting project has an NPV of zero? The project’s IRR will be less than the required hurdle rate for the project The firm’s stockholders will earn a positive return, but it will be less than their required return, given the risk of the investment The firm’s security holders will earn their required rate of return, given the risk of the investment The firm’s stockholders will earn a negative return none of the above
When a capital budgeting project has an NPV of zero, what does this mean? The project’s...
When a capital budgeting project has an NPV of zero, what does this mean? The project’s IRR will be less than the required hurdle rate for the project The firm’s stockholders will earn a positive return, but it will be less than their required return, given the risk of the investment The firm’s stockholders will earn a negative return The firm’s security holders will earn their required rate of return, given the risk of the investment none of the above
Merton Clinic managers are analyzing a new project. The project’s most likely NPV is $120,000. The...
Merton Clinic managers are analyzing a new project. The project’s most likely NPV is $120,000. The project cost of capital (discount rate) is 10 percent. Probability   NPV 0.05   ($800,000) 0.25   200,000 0.50   400,000 0.20   600,000 What is the project’s standard deviation? a. -$300,000 b. $300,485 c. *$291,719 d. $281,593 e. $300,000
You are evaluating a project with the following cash flows: initial investment is $-23, and the  expected...
You are evaluating a project with the following cash flows: initial investment is $-23, and the  expected cash flows for years 1 - 3 are $12, $9 and $8 (all cash flows are in millions of dollars). What is this projects NPV? The company's WACC is 9%. Express your answer in millions of dollars, rounded to 2 decimals and without the dollar sign. So, if your answer is 23.5678, just enter 23.57.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT