Question

In: Finance

The following table shows the cost information for a product at the 15,000-units level. Use the...

The following table shows the cost information for a product at the 15,000-units level. Use the table to answer these questions: What are the incremental and marginal costs for producing 5,000 additional units? Suppose that, at a new production level of 30,000, the fixed cost increases to $3 million, what are the incremental and marginal costs for the additional 10,000 units? All cost figures are in dollars. Calculate [USING EXCEL]

Quantity Fixed Cost Variable Cost Total Cost Incremental Coast Marginal Cost
15,000 1,500,000 6,400,000 ?
20,000 ? ? ? ? ?
30,000 ? ? ? ? ?

Solutions

Expert Solution

Marginal Cost is the increase/decrease in the cost resulted from producing an additional quantity of output.

Incremental Cost is the increase/decrease in the Overall Total cost for additional output. This is much wider than the definition of Marginal cost.

Based on the given data in two scenarios (Case 1 and Case 2):

The numbers represent Positive means increase in cost and negative means decrease in cost;

Incremental cost = Difference in the Total Cost;

Marginal Cost = Difference in the Total Cost per unit;


Related Solutions

Question 1 The table below shows the cost and revenue information of a firm. Output (units)...
Question 1 The table below shows the cost and revenue information of a firm. Output (units) Price (RM) Total Cost (RM) Total revenue (RM) Marginal Cost (RM) Marginal Revenue (RM) 0 14 10 1 14 14 2 14 22 3 14 34 4 14 48 5 14 64 6 14 82 (a) Complete the table above. [9 marks] (b) Determine the price and output at equilibrium. [6 marks] (c) Calculate the profit or loss at equilibrium. [4 marks] (d) Is...
Required information Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product...
Required information Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labour-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Measure Estimated Overhead Cost Expected Activity   Machining Machine-hours $ 227,700   11,000 MHs   Machine...
Using the information in the following table and assuming that the cost of transferring units between...
Using the information in the following table and assuming that the cost of transferring units between 2 adjacent departments is $5/unit and between 2 non-adjacent departments is $8/unit, Calculate the cost for the existing layout.      Design a layout that will have a lower cost and calculate the cost. Load Summary Chart                To From A B C D E F A 15 50 125 B 20 25 75 C 50 120 120 D 60 25 E 50 100 F...
The table below shows the average cost of a firm depending on the level of production....
The table below shows the average cost of a firm depending on the level of production. Q 0 1 2 3 4 5 6 AC -- 32 24 20 24 25 26 Assuming that the company is operating in the long run what are fixed costs?
Webster Company produces 40,000 units of product A, 30,000 units of product B, and 15,000 units...
Webster Company produces 40,000 units of product A, 30,000 units of product B, and 15,000 units of product C from the same manufacturing process at a cost of $390,000. A and B are joint products, and C is regarded as a by-product. The unit selling prices of the products are $40 for A, $30 for B, and $1 for C. None of the products requires separable processing. Of the units produced, Webster Company sells 33,000 units of A, 29,000 units...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 216,700 11,000...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Using the ABC system, what percentage of the Machine Setups is assigned to Product Y and...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Using the ABC system, what percentage of the General Factory cost is assigned to Product Y...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 213,400 11,000...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 213,400 11,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT