In: Accounting
Required information
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labour-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Measure |
Estimated Overhead Cost |
Expected Activity |
|||
Machining |
Machine-hours |
$ |
227,700 |
11,000 |
MHs |
Machine setups |
Number of setups |
$ |
153,900 |
270 |
setups |
Production design |
Number of products |
$ |
91,000 |
2 |
products |
General factory |
Direct labour-hours |
$ |
257,000 |
13,200 |
DLHs |
Activity Measure |
Product Y |
Product Z |
Machine-hours |
7,700 |
3,300 |
Number of setups |
60 |
210 |
Number of products |
1 |
1 |
Direct labour-hours |
8,700 |
4,500 |
Required:
What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)
|
Required:
What is the activity rate for the Machine Setups activity cost pool?
|
Required:
What is the activity rate for the Product Design activity cost pool?
|
Required:
What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)
|
Required:
Which of the four activities is a batch-level activity?
Required:
Which of the four activities is a product-level activity?
Required:
Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Do not round intermediate calculations and round your final answer to the nearest dollar amount.)
|
Required:
Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Do not round intermediate calculations and round your final answer to the nearest dollar amount.)
|
Question 1 and 2 | |||||
Activity | Question 2 | Measure | Estimated OH cost | Expected Activity | Question 1 |
Machining | Machine Hours | $ 2,27,700.00 | 11,000.00 | $ 20.70 | |
Machine Setups | Batch Level | Number of setups | $ 1,53,900.00 | 270.00 | $ 570.00 |
Production design | Product Level | Number of products | $ 91,000.00 | 2.00 | $ 45,500.00 |
General Factory | Direct Labour hours | $ 2,57,000.00 | 13,200.00 | $ 19.47 |
Question 3 | |||||
Activity | Activity Rate | Expected Activity Y | Expected OH cost Y | Expected Activity Z | Expected OH cost Z |
Machining | $ 20.70 | 7,700.00 | $ 1,59,390.00 | 3,300.00 | $ 68,310.00 |
Machine Setups | $ 570.00 | 60.00 | $ 34,200.00 | 210.00 | $ 1,19,700.00 |
Production design | $ 45,500.00 | 1.00 | $ 45,500.00 | 1.00 | $ 45,500.00 |
General Factory | $ 19.47 | 8,700.00 | $ 1,69,386.36 | 4,500.00 | $ 87,613.64 |