In: Accounting
Ace Company manufactures two products, X and Y. The following information is given for X only:
X
Annual production units 2,000 units
Direct material cost per unit of product $15
Direct labor cost per unit of product 25
The company uses activity-based costing. And its overhead costs are traced to two activity cost pools. The following data are given:
Activity cost pool |
Activity measure |
Activity rate |
Total activity needed (for all 2,000 units of X together) |
||||||||||||||||||||||||||||||
Design |
Number of parts |
$3 per part |
3,000 parts |
||||||||||||||||||||||||||||||
Processing |
Direct labor hours |
$8 per direct labor hour |
1,000 direct labor hours |
||||||||||||||||||||||||||||||
What is the total overhead cost assigned to X (for all 2,000 units together)?
What is the unit product cost (cost per unit)?
|
Answer: |
Total overhead cost assigned to
X = ( Design Activity rate x Total activity needed ) + ( Processing Activity rate x Total activity needed ) = ( $3 x 3,000 ) + ($8 x 1,000) = $9,000 + $8,000 = $17,000 |
Total overhead cost assigned to X = $ 17,000 |
Option (D) is Correct - $17,000 |
Unit product cost = Direct material cost per unit + Direct labor cost per unit + overhead cost per unit = $15 + $25 + $ 17,000 / 2,000 units = $40 + $8.5 = $48.50 |
Unit product cost = $48.50 |
Option (B) is Correct - $ 48.50 |