Question

In: Economics

Part 1: Suppose a project under consideration has the following stream of benefits and costs. Year...

Part 1: Suppose a project under consideration has the following stream of benefits and costs.

Year

0

1

2

3

4

5

Costs

$10,000

$6,000

$2,000

Benefits

$2,000

$4,000

$6,000

$8,000

$10,000

(a)Find the net present value of the project assuming a discount rate of 5%. Is the project worthwhile?

(b)Redo (a) assuming the discount rate is 10%. Would you recommend the project go forward?

(c)Suppose you have discovered that the benefits of the project have been overestimated and a more accurate assessment suggests that the benefit in each year is half of the original estimate. Assuming a discount rate of 5%, would you recommend the project go forward in this case? Briefly explain your answer.

Part 2: The government is contemplating a project that protects a wilderness area. The project is expected to produce annual net benefits of $100,000 into perpetuity. Assuming a discount rate of 8%, what is the net present value associated with this project?

Solutions

Expert Solution

Net present value (NPV) is the difference of present value of net benefits and the initial (year 0) cost.

Net benefit (NB) = Benefit – Cost

A project could be accepted, if it has positive NPV.

a.

NPV at 5% discount rate

Year

NB

5% discount factor = 1/(1 + 0.05)^n

NB × factor

0

0 – 10,000 = -10,000

1

-10,000

1

2,000

0.9524

1,904.80

2

4,000

0.9070

3,628.00

3

6,000 – 6,000 = 0

0.8638

0

4

8,000

0.8227

6,581.60

5

10,000 – 2,000 = 8,000

0.7835

6,268.00

NPV

8,382.40

Answer: NPV is $8,382.40.

Answer: The project is worthwhile, since it has positive NPV.

b.

NPV at 10% discount rate

Year

NB

5% discount factor = 1/(1 + 0.05)^n

NB × factor

0

0 – 10,000 = -10,000

1

-10,000

1

2,000

0.9091

1,818.20

2

4,000

0.8264

3,305.60

3

6,000 – 6,000 = 0

0.7513

0

4

8,000

0.6830

5,464.00

5

10,000 – 2,000 = 8,000

0.6209

4,967.20

NPV

5,555

Answer: NPV is $5,555.

Answer: The project is recommended, since it has positive NPV.

c.

If the benefit becomes ½, net benefits in each year would be as below:

Year

Benefits, B

Costs, C

Net benefits [B – C]

0

0

10,000

-10,000

1

1,000

0

1,000

2

2,000

0

2,000

3

3,000

6,000

-3,000

4

4,000

0

4,000

5

5,000

2,000

3,000

NPV at 5% discount rate

Year

NB

5% discount factor = 1/(1 + 0.05)^n

NB × factor

0

-10,000

1

-10,000

1

1,000

0.9524

952.40

2

2,000

0.9070

1,814.00

3

-3,000

0.8638

-2,591.40

4

4,000

0.8227

3,290.80

5

3,000

0.7835

2,350.50

NPV

-4,183.70

Answer: NPV is -$4,183.70.

Answer: The project is not recommended, since it has negative NPV.

Explanation: Once benefits in each year go down, NB becomes low. This is the reason why NPV becomes negative.

Part 2: NPV at perpetuity would be as below:

NPV = Net benefits / Discount rate

         = $100,000 / 0.08

         = $1,250,000 (Answer)


Related Solutions

*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0...
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000 2 1,000 3 1,000 4 2,000 5 2,000 Assuming an interest rate of 10%, the project's simple payback period is most nearly _________. A. 2 years B. 4 years C. 6 years D. 5 years E. 7 years Using the information from the problem above and linear interpolation, the project's discounted payback period is most nearly ___________. A. 3.62 years B....
A project under consideration costs $600,000, has a five-year life and has no salvage value. Depreciation...
A project under consideration costs $600,000, has a five-year life and has no salvage value. Depreciation is straight-line to zero. The firm has made the following projections related to this project: Base Case Lower Bound Upper Bound Unit Sales 3,000 2,850 3,150 Price Per Unit $300 $285 $315 Variable Cost Per Unit $170 $160 $180 Fixed Costs $150,000 $135,000 $165,000 The required return is 16 percent and the tax rate is 40 percent. No additional investment in net working capital...
A project under consideration costs $600,000, has a five-year life and has no salvage value. Depreciation...
A project under consideration costs $600,000, has a five-year life and has no salvage value. Depreciation is straight-line to zero. The firm has made the following projections related to this project: Base Case Lower Bound Upper Bound Unit Sales 3,000 2,850 3,150 Price Per Unit $300 $285 $315 Variable Cost Per Unit $170 $160 $180 Fixed Costs $150,000 $135,000 $165,000 The required return is 16 percent and the tax rate is 40 percent. No additional investment in net working capital...
1.       A project has the following cash flow. Year Costs Benefits 0 $10,000 0 1 0...
1.       A project has the following cash flow. Year Costs Benefits 0 $10,000 0 1 0 $5,000 2 $1,000 $5,000 3 0 $3,000 Assuming a discount rate of 10%, estimate the following: a)      Net Present Value (NPV) b)     Discounted Benefit-Cost Ratio c)      Net discounted Benefit-Cost Ratio d)     Is the project feasible? Explain your answer
Kermit Kite Co. has 2 Projects under consideration- PROJECT C and PROJECT D with the following...
Kermit Kite Co. has 2 Projects under consideration- PROJECT C and PROJECT D with the following cashflows. PROJECT C PROJECT D Year 0 (800,000) Year 0 (360,000) Year 1 450,000    Year 1 200,000 Year 2 350,000    Year 2 265,000 Year 3 215,000 The firm's cost of capital is 12%. Calculate the EAA for each project. Which is the preferred project under EAA and why?
A project under consideration has an internal rate of return of 13% and a beta of...
A project under consideration has an internal rate of return of 13% and a beta of 0.8. The risk-free rate is 3%, and the expected rate of return on the market portfolio is 13%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? c. What is the required rate of return on the project if its beta is 1.80? (Do...
A project under consideration has an internal rate of return of 13% and a beta of...
A project under consideration has an internal rate of return of 13% and a beta of 0.5. The risk-free rate is 3%, and the expected rate of return on the market portfolio is 13%. a-1. Calculate the required return.   Required return %   a-2. Should the project be accepted? Yes No b-1. Calculate the required return if its beta is 1.5.   Required return %   b-2. Should the project be accepted? Yes No
A project under consideration has an internal rate of return of 13% and a beta of...
A project under consideration has an internal rate of return of 13% and a beta of 0.4. The risk-free rate is 3%, and the expected rate of return on the market portfolio is 13%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? Yes No c. What is the required rate of return on the project if its beta is...
Your firm has an average-risk project under consideration. You choose to fund the project in the...
Your firm has an average-risk project under consideration. You choose to fund the project in the same manner as the firm’s existing capital structure. If the cost of debt is 9.50%, the cost of preferred stock is 10.00%, the cost of common stock is 12.00%, and the WACC adjusted for taxes is 11.50%, what is the project’s NPV given the expected cash flows listed here? Category T0 T1 T2 T3 Investment −$800,000 Net working capital −$ 50,000 $ 50,000 Operating...
Eclipse, Inc., has a new project under consideration that will require an investment of $6.9 million...
Eclipse, Inc., has a new project under consideration that will require an investment of $6.9 million today. If the project is successful, the cash flows will be $2.6 million for 12 years. If the project is unsuccessful, the cash flows will be $285,000 per year. Additionally, the company could sell the project’s fixed assets in one year and realize an aftertax salvage value of $4.7 million. The required return is 16 percent. What is the minimum probability of success that...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT