Question

In: Economics

1.       A project has the following cash flow. Year Costs Benefits 0 $10,000 0 1 0...

1.       A project has the following cash flow.

Year

Costs

Benefits

0

$10,000

0

1

0

$5,000

2

$1,000

$5,000

3

0

$3,000

Assuming a discount rate of 10%, estimate the following:

a)      Net Present Value (NPV)

b)     Discounted Benefit-Cost Ratio

c)      Net discounted Benefit-Cost Ratio

d)     Is the project feasible? Explain your answer

Solutions

Expert Solution

(a) Annual net benefit = Annual benefit - Annual cost

NPV is sum of all annual net benefit discounted at 10%, computed as follows.

Year

Cost ($)

Benefit ($)

Net Benefit ($)

PV Factor @10%

Discounted Net Benefit ($)

(A)

(B)

(C)=(B)-(A)

(D)

(C)x(D)

0

10,000

0

-10,000

1.0000

-10,000

1

0

5,000

5,000

0.9091

4,545

2

1,000

5,000

4,000

0.8264

3,306

3

0

3,000

3,000

0.7513

2,254

NPV ($) =

105

(b)

Present Value (PV) of Costs and Benefits are computed as follows.

Year

Cost ($)

PV Factor @10%

Discounted Cost ($)

(A)

(B)

(A) x (B)

0

10,000

1.0000

10,000

1

0

0.9091

0

2

1,000

0.8264

826

3

0

0.7513

0

PV of Costs ($) =

10,826

Year

Benefit($)

PV Factor @10%

Discounted Benefit ($)

(A)

(B)

(A) x (B)

0

0

1.0000

0

1

5,000

0.9091

4,545

2

5,000

0.8264

4,132

3

3,000

0.7513

2,254

PV of Benefit ($) =

10,932

Discounted Benefit-Cost ratio (BCR) = PV of benefits / PV of costs

= $10,932 / $10,826

= 1.01

Note that Discounted BCR and Net Discounted BCR are the same terms.

(c) Since NPV is positive and (Net) Discounted Benefit-Cost ratio is higher than 1, the project is feasible.


Related Solutions

A project has the following cash flow. Years Costs Benefits 0 $10,000 0 1 $1,000 $5,000...
A project has the following cash flow. Years Costs Benefits 0 $10,000 0 1 $1,000 $5,000 2 $1,000 $5,000 3 $2,000 $6,000 4 $20,000 $3,000 a) Find net present value b) Discounted Benefit-Cost Ratio c)Net discounted Benefit-Cost Ratio discount ratio is 10%
A project has the following cash flows: Year Cash Flow 0 $ 40,000 1 – 19,000...
A project has the following cash flows: Year Cash Flow 0 $ 40,000 1 – 19,000 2 – 30,000 What is the IRR for this project? What is the NPV of this project, if the required return is 11 percent? What is the NPV of the project if the required return is 0 percent? What is the NPV of the project if the required return is 22 percent?
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000...
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000 2 – 37,000 What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project has the following cash flows: Year Cash Flow 0 $ 42,000 1 – 21,000...
A project has the following cash flows: Year Cash Flow 0 $ 42,000 1 – 21,000 2 – 32,000 What is the IRR for this project? (Round your answer to 2 decimal places. (e.g., 32.16)) IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) NPV $ What is...
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0...
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000 2 1,000 3 1,000 4 2,000 5 2,000 Assuming an interest rate of 10%, the project's simple payback period is most nearly _________. A. 2 years B. 4 years C. 6 years D. 5 years E. 7 years Using the information from the problem above and linear interpolation, the project's discounted payback period is most nearly ___________. A. 3.62 years B....
There is a project with the following cash flows : Year Cash Flow 0 −$21,800 1...
There is a project with the following cash flows : Year Cash Flow 0 −$21,800 1 6,300 2 7,350 3 6,750 4 4,400 What is the payback period? Multiple Choice a. 4.00 years b. 3.32 years c. 3.74 years d. 3.56 years e. 2.79 years
There is a project with the following cash flows : Year Cash Flow 0 −$23,700 1...
There is a project with the following cash flows : Year Cash Flow 0 −$23,700 1 7,000 2 7,700 3 7,100 4 5,100 What is the payback period? Multiple Choice 2.73 years 4.00 years 3.81 years 3.63 years 3.37 years
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT