Question

In: Finance

v You are a financial analyst at Gen-Eric Corporation, and you are considering two mutually exclusive...

v

  1. You are a financial analyst at Gen-Eric Corporation, and you are considering two mutually exclusive projects. Unfortunately, the figures for project 1 are in nominal terms and the figures for project 2 are in real terms. The nominal discount rate for both projects is 8%, and the inflation rate is projected to be 4%. Which project should you choose?

(4 pts)

Project 1

Project 2

0

-$50,000

-$40,000

1

40,000

30,000

2

50,000

40,000

3

70,000

75,000

Solutions

Expert Solution

- Project 1 figures are in Nominal Terms and its the discount rate is also in nominal terms. Thus, using both to calculate the NPV of the Project.

Year Cash Flows of project 1 ($) PV Factor @8.00% Present Value of Project 1 ($)
0                    (50,000.00) 1.0000                         (50,000.00)
1                      40,000.00 0.9259                           37,037.04
2                      50,000.00 0.8573                           42,866.94
3                      70,000.00 0.7938                           55,568.26
NPV                           85,472.23

NPV of the Project 1 is $ 85,472.23

- Project 2 cash flows are in real terms which means that they are not inflation adjusted. Thus, first we will add inflation to the real terms cash flows to convert them into Nominal cash flow terms.

& then we will calculate the NPV of the project using nominal interest rate as discount rate to compute NPV of the Project:-

Year Real Term cash flows Inflation adjustment Nominal terms Cash flows PV Factor @8.00% Present Value of Project 1 ($)
0                    (40,000.00) - -40000 1.0000                  (40,000.00)
1                      30,000.00 30,000*(1+4%)^1 31200 0.9259                    28,888.89
2                      40,000.00 40,000*(1+4%)^2 43264 0.8573                    37,091.91
3                      75,000.00 75,000*(1+4%)^3 84364.8 0.7938                    66,971.50
NPV                    92,952.29

Note- Cashflow in 0 period is not adjusted to inflation as its value is already in today's terms which is infalation adjusted while the future cash flows are not adjusted with increase in per year inflation value of money.

NPV of the Project 2 is $92,952.29

Hence, project 2 should be chosen

If you need any clarification regarding this solution, then you can ask in comments

If you like my answer then please Up-vote as it will be motivating.


Related Solutions

You are considering the following two mutually exclusive projects that will not be repeated. The required...
You are considering the following two mutually exclusive projects that will not be repeated. The required rate of return is 11.25% for project A and 10.75% for project B. Which project should you accept and why? Year      Project A Project B 0 -48,000 -126,900 1 18,400 69,700 2 31,300 80,900 3 11,700 0 project A; because its NPV is about $335 more than the NPV of project B project A; because it has the higher required rate of return project...
You are considering two mutually exclusive (you can do one or the other – not both)...
You are considering two mutually exclusive (you can do one or the other – not both) projects with the following cash flows. Using NPV and IRR, which project should you accept if the discount rate is 5 percent? What if the discount rate is 10 percent? Year Project A Project B 0 -$200,000 -$200,000 1 100,000 0 2 100,000 0 3 100,000 300,000
Harris Corporation is considering the following two mutually exclusive projects with their projected cash flows:                        &nb
Harris Corporation is considering the following two mutually exclusive projects with their projected cash flows:                                     Year                 Project A          Project B                                     0                    ($10,000)         ($10,000)                                     1                         4,500                      0                                     2                         4,500                      0                                        3                         4,500              15,000 If the required return on these projects is 10 percent, which would be chosen and why? Group of answer choices Project A because of higher IRR Project B because of higher NPV Project B because of higher IRR Project...
( Time-disparity problem ) The State Spartan Corporation is considering two mutually exclusive projects. The free...
( Time-disparity problem ) The State Spartan Corporation is considering two mutually exclusive projects. The free cash flows associated with these projects are shown in the popup window: PROJECT A PROJECT B Initial outlay − $70,000 − $70,000 Inflow year 1 19,625 0 Inflow year 2 19,625 0 Inflow year 3 19,625 0 Inflow year 4 19,625 0 Inflow year 5 19,625 120,000 The required rate of return on these projects is 9 percent. A. What is each project's payback...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$26,000 −$26,000 1 9,500 17,590 2 9,500 7,500 3 17,500 9,610 rev: 05_02_2019_QC_CS-167236, 05_09_2019_QC_CS-168369, 09_24_2019_QC_CS-182411 Multiple Choice 18.39%; A 11.89%; B 16.97%; B 11.89%; A 16.97%; A
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greaterthan the crossover rate. Year Project A Project B 0 −$30,000 −$30,000 1 11,500 19,630 2 11,500 9,500 3 19,500 11,650
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$24,000 −$24,000 1 8,500 16,570 2 8,500 6,500 3 16,500 8,590 Multiple Choice 12.17%; B 12.17%; A 17.82%; A 16.49%; A 16.49%; B
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$39,000 −$39,000 1 21,500 13,720 2 13,500 11,500 3 13,500 25,600 12.85%; B 12.52%; A 12.52%; B 12.93%; A 12.93%; B
Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A...
Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% Question 1 At what discount rate would make you indifferent between choosing one project...
Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A...
Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% Question 1 At what discount rate would make you indifferent between choosing one project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT