In: Finance
Use the following for Questions 1 - 4:
You are considering two mutually exclusive projects, A and B.
Project A costs $70,000 and generates cash flows of $12,000 for 10 years.
Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years.
Report rates in percentage form to two decimal places i.e. 10.03% not 10%
Question 1
At what discount rate would make you indifferent between choosing one project or another?
Question 2
Which project would you ACCEPT if your discount rate was 10%?
A) Project A
B) Project B
C) Both Project A and B
D) Neither Project A or B
Question 3
Which project would you ACCEPT if your discount rate was 5%?
A) Project A
B) Project B
C) Both Project A and B
D) Neither Project A or B
Question 4
What is the highest discount rate in which you can still produce a non-negative NPV?
Answer 1 | ||||||||||||
Calculation of discount rate that would make you indifferent between choosing one project or another | ||||||||||||
To find out this rate , we have to take difference of cash flows between two projects and then apply IRR formula to this difference. | ||||||||||||
Year | Cash flows | |||||||||||
Project A | Project B | Difference | ||||||||||
0 | -70000 | -60000 | -10000 | |||||||||
1 | 12000 | 2000 | 10000 | |||||||||
2 | 12000 | 2000 | 10000 | |||||||||
3 | 12000 | 2000 | 10000 | |||||||||
4 | 12000 | 2000 | 10000 | |||||||||
5 | 12000 | 2000 | 10000 | |||||||||
6 | 12000 | 2000 | 10000 | |||||||||
7 | 12000 | 29000 | -17000 | |||||||||
8 | 12000 | 29000 | -17000 | |||||||||
9 | 12000 | 29000 | -17000 | |||||||||
10 | 12000 | 29000 | -17000 | |||||||||
IRR of cash flow difference = | 7.47% | |||||||||||
Discount rate that would make you indifferent between choosing one project or another = 7.47% | ||||||||||||
Answer 2 | ||||||||||||
We decide about the projects based on NPV.The project with higher NPV will be selected. | ||||||||||||
Year | Discount factor @ 10% | Project A | Project B | |||||||||
Cash flow | Present Value | Cash flow | Present Value | |||||||||
0 | 1 | -$70,000.00 | -$70,000.00 | -$60,000.00 | -$60,000.00 | |||||||
1 | 0.909091 | $12,000.00 | $10,909.09 | $2,000.00 | $1,818.18 | |||||||
2 | 0.826446 | $12,000.00 | $9,917.36 | $2,000.00 | $1,652.89 | |||||||
3 | 0.751315 | $12,000.00 | $9,015.78 | $2,000.00 | $1,502.63 | |||||||
4 | 0.683013 | $12,000.00 | $8,196.16 | $2,000.00 | $1,366.03 | |||||||
5 | 0.620921 | $12,000.00 | $7,451.06 | $2,000.00 | $1,241.84 | |||||||
6 | 0.564474 | $12,000.00 | $6,773.69 | $2,000.00 | $1,128.95 | |||||||
7 | 0.513158 | $12,000.00 | $6,157.90 | $29,000.00 | $14,881.59 | |||||||
8 | 0.466507 | $12,000.00 | $5,598.09 | $29,000.00 | $13,528.71 | |||||||
9 | 0.424098 | $12,000.00 | $5,089.17 | $29,000.00 | $12,298.83 | |||||||
10 | 0.385543 | $12,000.00 | $4,626.52 | $29,000.00 | $11,180.76 | |||||||
NPV | $3,734.81 | $600.41 | ||||||||||
NPV of Project A | $3,734.81 | |||||||||||
NPV of Project B | $600.41 | |||||||||||
As NPV of project A is higher , it will be selected. | ||||||||||||
The answer is Option A. | ||||||||||||
Answer 3 | ||||||||||||
We decide about the projects based on NPV.The project with higher NPV will be selected. | ||||||||||||
Year | Discount factor @ 5% | Project A | Project B | |||||||||
Cash flow | Present Value | Cash flow | Present Value | |||||||||
0 | 1 | -$70,000.00 | -$70,000.00 | -$60,000.00 | -$60,000.00 | |||||||
1 | 0.952381 | $12,000.00 | $11,428.57 | $2,000.00 | $1,904.76 | |||||||
2 | 0.907029 | $12,000.00 | $10,884.35 | $2,000.00 | $1,814.06 | |||||||
3 | 0.863838 | $12,000.00 | $10,366.05 | $2,000.00 | $1,727.68 | |||||||
4 | 0.822702 | $12,000.00 | $9,872.43 | $2,000.00 | $1,645.40 | |||||||
5 | 0.783526 | $12,000.00 | $9,402.31 | $2,000.00 | $1,567.05 | |||||||
6 | 0.746215 | $12,000.00 | $8,954.58 | $2,000.00 | $1,492.43 | |||||||
7 | 0.710681 | $12,000.00 | $8,528.18 | $29,000.00 | $20,609.76 | |||||||
8 | 0.676839 | $12,000.00 | $8,122.07 | $29,000.00 | $19,628.34 | |||||||
9 | 0.644609 | $12,000.00 | $7,735.31 | $29,000.00 | $18,693.66 | |||||||
10 | 0.613913 | $12,000.00 | $7,366.96 | $29,000.00 | $17,803.48 | |||||||
NPV | $22,660.82 | $26,886.63 | ||||||||||
NPV of Project A | $22,660.82 | |||||||||||
NPV of Project B | $26,886.63 | |||||||||||
As NPV of project B is higher , it will be selected. | ||||||||||||
The answer is Option B. | ||||||||||||
Answer 4 | ||||||||||||
Calculation of highest discount rate in which you can still produce a non-negative NPV | ||||||||||||
To find out this rate , we have to find out IRR for both projects. | ||||||||||||
Year | Cash flows | |||||||||||
Project A | Project B | |||||||||||
0 | -70000 | -60000 | ||||||||||
1 | 12000 | 2000 | ||||||||||
2 | 12000 | 2000 | ||||||||||
3 | 12000 | 2000 | ||||||||||
4 | 12000 | 2000 | ||||||||||
5 | 12000 | 2000 | ||||||||||
6 | 12000 | 2000 | ||||||||||
7 | 12000 | 29000 | ||||||||||
8 | 12000 | 29000 | ||||||||||
9 | 12000 | 29000 | ||||||||||
10 | 12000 | 29000 | ||||||||||
IRR = | 11.23% | 10.14% | ||||||||||
Highest discount rate for project A | 11.23% | |||||||||||
Highest discount rate for project B | 10.14% | |||||||||||