Question

In: Finance

Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A...

Use the following for Questions 1 - 4:

You are considering two mutually exclusive projects, A and B.

Project A costs $70,000 and generates cash flows of $12,000 for 10 years.

Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years.

Report rates in percentage form to two decimal places i.e. 10.03% not 10%

Question 1

At what discount rate would make you indifferent between choosing one project or another?

Question 2

Which project would you ACCEPT if your discount rate was 10%?

A) Project A

B) Project B

C) Both Project A and B

D) Neither Project A or B

Question 3

Which project would you ACCEPT if your discount rate was 5%?

A) Project A

B) Project B

C) Both Project A and B

D) Neither Project A or B

Question 4

What is the highest discount rate in which you can still produce a non-negative NPV?

Solutions

Expert Solution

Answer 1
Calculation of discount rate that would make you indifferent between choosing one project or another
To find out this rate , we have to take difference of cash flows between two projects and then apply IRR formula to this difference.
Year Cash flows
Project A Project B Difference
0 -70000 -60000 -10000
1 12000 2000 10000
2 12000 2000 10000
3 12000 2000 10000
4 12000 2000 10000
5 12000 2000 10000
6 12000 2000 10000
7 12000 29000 -17000
8 12000 29000 -17000
9 12000 29000 -17000
10 12000 29000 -17000
IRR of cash flow difference = 7.47%
Discount rate that would make you indifferent between choosing one project or another = 7.47%
Answer 2
We decide about the projects based on NPV.The project with higher NPV will be selected.
Year Discount factor @ 10% Project A Project B
Cash flow Present Value Cash flow Present Value
0 1 -$70,000.00 -$70,000.00 -$60,000.00 -$60,000.00
1 0.909091 $12,000.00 $10,909.09 $2,000.00 $1,818.18
2 0.826446 $12,000.00 $9,917.36 $2,000.00 $1,652.89
3 0.751315 $12,000.00 $9,015.78 $2,000.00 $1,502.63
4 0.683013 $12,000.00 $8,196.16 $2,000.00 $1,366.03
5 0.620921 $12,000.00 $7,451.06 $2,000.00 $1,241.84
6 0.564474 $12,000.00 $6,773.69 $2,000.00 $1,128.95
7 0.513158 $12,000.00 $6,157.90 $29,000.00 $14,881.59
8 0.466507 $12,000.00 $5,598.09 $29,000.00 $13,528.71
9 0.424098 $12,000.00 $5,089.17 $29,000.00 $12,298.83
10 0.385543 $12,000.00 $4,626.52 $29,000.00 $11,180.76
NPV $3,734.81 $600.41
NPV of Project A $3,734.81
NPV of Project B $600.41
As NPV of project A is higher , it will be selected.
The answer is Option A.
Answer 3
We decide about the projects based on NPV.The project with higher NPV will be selected.
Year Discount factor @ 5% Project A Project B
Cash flow Present Value Cash flow Present Value
0 1 -$70,000.00 -$70,000.00 -$60,000.00 -$60,000.00
1 0.952381 $12,000.00 $11,428.57 $2,000.00 $1,904.76
2 0.907029 $12,000.00 $10,884.35 $2,000.00 $1,814.06
3 0.863838 $12,000.00 $10,366.05 $2,000.00 $1,727.68
4 0.822702 $12,000.00 $9,872.43 $2,000.00 $1,645.40
5 0.783526 $12,000.00 $9,402.31 $2,000.00 $1,567.05
6 0.746215 $12,000.00 $8,954.58 $2,000.00 $1,492.43
7 0.710681 $12,000.00 $8,528.18 $29,000.00 $20,609.76
8 0.676839 $12,000.00 $8,122.07 $29,000.00 $19,628.34
9 0.644609 $12,000.00 $7,735.31 $29,000.00 $18,693.66
10 0.613913 $12,000.00 $7,366.96 $29,000.00 $17,803.48
NPV $22,660.82 $26,886.63
NPV of Project A $22,660.82
NPV of Project B $26,886.63
As NPV of project B is higher , it will be selected.
The answer is Option B.
Answer 4
Calculation of highest discount rate in which you can still produce a non-negative NPV
To find out this rate , we have to find out IRR for both projects.
Year Cash flows
Project A Project B
0 -70000 -60000
1 12000 2000
2 12000 2000
3 12000 2000
4 12000 2000
5 12000 2000
6 12000 2000
7 12000 29000
8 12000 29000
9 12000 29000
10 12000 29000
IRR = 11.23% 10.14%
Highest discount rate for project A 11.23%
Highest discount rate for project B 10.14%

Related Solutions

Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A...
Use the following for Questions 1 - 4: You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% Question 1 At what discount rate would make you indifferent between choosing one project...
Use the following for Questions 1 - 5: You are considering two mutually exclusive projects, A...
Use the following for Questions 1 - 5: You are considering two mutually exclusive projects, A and B. Project A costs $60,000 and generates cash flows of $9,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for seven years and then cash flows of $27,000 for three years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% Question 1 (3 points) Calculate what discount rate would make you indifferent between choosing...
You are considering the following two mutually exclusive projects that will not be repeated. The required...
You are considering the following two mutually exclusive projects that will not be repeated. The required rate of return is 11.25% for project A and 10.75% for project B. Which project should you accept and why? Year      Project A Project B 0 -48,000 -126,900 1 18,400 69,700 2 31,300 80,900 3 11,700 0 project A; because its NPV is about $335 more than the NPV of project B project A; because it has the higher required rate of return project...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$26,000 −$26,000 1 9,500 17,590 2 9,500 7,500 3 17,500 9,610 rev: 05_02_2019_QC_CS-167236, 05_09_2019_QC_CS-168369, 09_24_2019_QC_CS-182411 Multiple Choice 18.39%; A 11.89%; B 16.97%; B 11.89%; A 16.97%; A
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greaterthan the crossover rate. Year Project A Project B 0 −$30,000 −$30,000 1 11,500 19,630 2 11,500 9,500 3 19,500 11,650
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$24,000 −$24,000 1 8,500 16,570 2 8,500 6,500 3 16,500 8,590 Multiple Choice 12.17%; B 12.17%; A 17.82%; A 16.49%; A 16.49%; B
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$39,000 −$39,000 1 21,500 13,720 2 13,500 11,500 3 13,500 25,600 12.85%; B 12.52%; A 12.52%; B 12.93%; A 12.93%; B
You are considering the following two mutually exclusive projects. The crossover point is _____ percent. YEAR...
You are considering the following two mutually exclusive projects. The crossover point is _____ percent. YEAR PROJECT A PROJECT B 0 -$16,000 -$16,000 1 11,000 5,000 2 8,000 7,000 3 3,000 12,000 PLEASE SHOW WORK WITHOUT USING EXCEL PLEASE THE ANSWER IS 14.42
You are considering the following two mutually exclusive projects. Both projects will be depreciated using straight-line...
You are considering the following two mutually exclusive projects. Both projects will be depreciated using straight-line depreciation to a zero book value over the life of the project. Neither project has any salvage value. Year Project(A) Project (B) 0 -$30,000 -$30,000 1 13,000 5,000 2 11,000 5,000 3 9,000 5,000 4 7,000 5,000 5 0 5,000 6 7 8 9 10 0 0 0 0 0 5,000 5,000 5,000 5,000 5,000 The required rate of return is 10%. (1). (4...
You are considering the following two mutually exclusive projects. Both projects will be depreciated using straight-line...
You are considering the following two mutually exclusive projects. Both projects will be depreciated using straight-line depreciation to a zero book value over the life of the project. Neither project has any salvage value. Year Project(A) Project (B) 0 -$30,000 -$30,000 1 13,000 5,000 2 11,000 5,000 3 9,000 5,000 4 7,000 5,000 5 0 5,000 6 7 8 9 10 0 0 0 0 0 5,000 5,000 5,000 5,000 5,000     The required rate of return is 10% a....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT