In: Finance
You are considering the following two mutually exclusive
projects. The crossover rate between these two projects is ___
percent and Project ___ should be accepted if the required return
is greater than the crossover rate.
| Year | Project A | Project B | ||||
| 0 | −$39,000 | −$39,000 | ||||
| 1 | 21,500 | 13,720 | ||||
| 2 | 13,500 | 11,500 | ||||
| 3 | 13,500 | 25,600 | ||||
12.85%; B
12.52%; A
12.52%; B
12.93%; A
12.93%; B
The crossover rate is the rate at which the NPV of the two projects is the same

Substituting the option values, the equation holds at 12.52% so the crossover rate is 12.52%
Below is the NPV schedules for both the projects at the crossover rates:
Project A:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $-39,000.00 | 1/(1+0.125176224326535)^0= | 1 | 1*-39000= | $ -39,000.00 |
| 1 | $ 21,500.00 | 1/(1+0.125176224326535)^1= | 0.888749672 | 0.888749671722349*21500= | $ 19,108.12 |
| 2 | $ 13,500.00 | 1/(1+0.125176224326535)^2= | 0.789875979 | 0.789875978986583*13500= | $ 10,663.33 |
| 3 | $ 13,500.00 | 1/(1+0.125176224326535)^3= | 0.702002017 | 0.702002017025695*13500= | $ 9,477.03 |
| NPV = Sum of all Discounted CF | $ 248.47 |
Project B:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $-39,000.00 | 1/(1+0.125176224326535)^0= | 1 | 1*-39000= | -39,000.00 |
| 1 | $ 13,720.00 | 1/(1+0.125176224326535)^1= | 0.888749672 | 0.888749671722349*13720= | 12,193.65 |
| 2 | $ 11,500.00 | 1/(1+0.125176224326535)^2= | 0.789875979 | 0.789875978986583*11500= | 9,083.57 |
| 3 | $ 25,600.00 | 1/(1+0.125176224326535)^3= | 0.702002017 | 0.702002017025695*25600= | 17,971.25 |
| NPV = Sum of all Discounted CF | $ 248.47 |
We need to create an NPV profile to see which project has higher NPV and should thus be selected:
| Cost of capital | A | B |
| 0.00% | $ 9,500.00 | $ 11,820.00 |
| 12.00% | $ 567.58 | $ 639.30 |
| 12.52% | $ 247.02 | $ 247.02 |
| 12.53% | $ 240.90 | $ 239.20 |
| 12.55% | $ 228.66 | $ 224.23 |
| 12.56% | $ 222.55 | $ 216.75 |
| 12.57% | $ 216.44 | $ 209.27 |
| 12.58% | $ 210.33 | $ 201.80 |
| 12.59% | $ 204.22 | $ 194.32 |
| 13.00% | $ -44.79 | $ -110.14 |
| 13.01% | $ -50.83 | $ -117.51 |
So we can see that the NPV is higher for Project A beyond 12.52% so it should be selected.