In: Finance
Use the following for Questions 1 - 4:
You are considering two mutually exclusive projects, A and B.
Project A costs $70,000 and generates cash flows of $12,000 for 10 years.
Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years.
Report rates in percentage form to two decimal places i.e. 10.03% not 10%
Question 1
At what discount rate would make you indifferent between choosing one project or another?
Question 2
Which project would you ACCEPT if your discount rate was 10%?
A) Project A
B) Project B
C) Both Project A and B
D) Neither Project A or B
Question 3
Which project would you ACCEPT if your discount rate was 5%?
A) Project A
B) Project B
C) Both Project A and B
D) Neither Project A or B
Question 4
What is the highest discount rate in which you can still produce a non-negative NPV?
1- |
Year |
Project B |
Project A |
incremental cash flow = cash flow A- cash flow B |
2- |
Year |
Project B |
Project A |
0 |
-60000 |
-70000 |
-10000 |
0 |
-60000 |
-70000 |
||
1 |
2000 |
12000 |
10000 |
1 |
2000 |
12000 |
||
2 |
2000 |
12000 |
10000 |
2 |
2000 |
12000 |
||
3 |
2000 |
12000 |
10000 |
3 |
2000 |
12000 |
||
4 |
2000 |
12000 |
10000 |
4 |
2000 |
12000 |
||
5 |
2000 |
12000 |
10000 |
5 |
2000 |
12000 |
||
6 |
2000 |
12000 |
10000 |
6 |
2000 |
12000 |
||
7 |
29000 |
12000 |
-17000 |
7 |
29000 |
12000 |
||
8 |
29000 |
12000 |
-17000 |
8 |
29000 |
12000 |
||
9 |
29000 |
12000 |
-17000 |
9 |
29000 |
12000 |
||
10 |
29000 |
12000 |
-17000 |
10 |
29000 |
12000 |
||
Cross over rate |
Using IRR function in MS excel |
7.47% |
IRR = Using IRR function in MS excel |
10.14% |
11.23% |
|||
Both project A & B would be selected on the basis of IRR if discount rate is 10% but as projects are mutually exclusive then project with higher IRR would be selected and project A would be selected |
||||||||
3- |
Both project A & B would be selected on the basis of IRR if discount rate is 5% but as projects are mutually exclusive then project with higher IRR would be selected and project A would be selected |
4- |
IRR is the discount at which NPV would be non negative |