Question

In: Civil Engineering

produce a (250 words min) report that describes thedifferent stages o the signaling design process...

produce a (250 words min) report that describes the different stages o the signaling design process an how the information provided by signalling design is used by installation maintaince and/or testing

Solutions

Expert Solution

Traffic control signals are signaling devices that are positioned in a way to control or direct the flow of traffic. Some examples of traffic control devices are 3 section signal heads, advanced warning flashers, school flashers, overhead beacon flashers, and pedestrian hybrid beacons. It should be noted that all traffic control devices require a permit.


Different Stages of Signal Design Process :-

The following list is provided as a general representation of the stages that should be taken when designing traffic signals. This list is only provided as a guide and not as an all-encompassing checklist.

 Obtain Project Background & Design Data

 Prepare Survey/Base/Existing Plan
 Initial Site visit (where applicable)
 Identify Signal Requirements / Verify with TE reports where applicable
o Left turn phasing
o Pedestrian phases
o Overlaps
o Preempts
o Turn restrictions

 Review Geometric Design
 Establish crosswalks, stop lines and review ramp locations
 Identify overhead structure support (span wire/mast arm)
 Locate Signal heads (vehicles/pedestrian) and push buttons
 Locate Signal Poles
 Identify detection method and locate vehicle detectors
 Locate cabinet and power source
 Locate Pull boxes and conduits
 Locate and determine sign requirements
 Locate and design signal interconnect if applicable

Maintenance :-

Maintenance practices should include the following:

Response time - Response time depends on two factors - time to obtain an indication of failure and time to respond after receiving an indication of failure. The following requirements apply:

• Time to obtain indication of failure – Since closed loop systems and other centrally monitored systems provide an indication of controller failure, rapid failure identification can be accomplished using such techniques if these systems are supervised. Criteria for the percentage of failures that are initially detected within the traffic agency (as compared to reports from police, other agencies or citizens) are:

o For systems in excess of 400 intersections 70% of failures should be detected by the operating agency. In a dense network of coordinated signals, critical failure detection by the agency should approach 100%.

o For systems with 400 intersections or fewer, 50% of failures should be detected by the operating agency. Detection should be considerably higher for a dense network

• Time to respond after receiving an indication of controller or signal failure. o Within one hour during business hours. o Within two hours during non-business hours.

The Traffic Signal Report Cards indicate that a significant number of agencies conform to this requirement.
A procedure to identify the level of criticality for the intersection with respect to safety and congestion should be developed. Response priorities should be developed in accordance with this procedure.

Rates of critical failures (e.g. controller failures, deficient cabinet or signal wiring, short circuits, lightning strikes, etc.) should not exceed F failures per year per for each intersection. Where this rate is exceeded for a period of one year, an investigation to determine the root cause should be conducted. To establish the value of F, intersection failure rates should be reviewed and the value of F set at the highest 20% of intersection failure rates.

​​​​​​​Spares for the current equipment in the field should always be available.


Related Solutions

Assessment 9.0: Hand back process Produce a report (min 250 words) to detail the hand back...
Assessment 9.0: Hand back process Produce a report (min 250 words) to detail the hand back process as defined by the Infrastructure Controller, and detail the factors that should be considered as part of the hand back process including the potential areas for special consideration which should be confirmed. Detail the requirements for maintenance records which form part of the hand back process. Write it in text if you know the answer as I don't understand the handwriting
Produce a report detailing the planning process for an OLE construction activity (min 600 words), using...
Produce a report detailing the planning process for an OLE construction activity (min 600 words), using a recent work as the basis for the report. The report should detail the following: • Strategic planning process for engineering possessions • Planning of engineer’s trains and on track plant • Ordering and supply of materials • Manpower requirements • Road rail machines requirements • Possession arrangements • On track plant detailed plans • Interface with other engineering functions • Isolation of Traction...
Assessment 5.0: Hand back process Produce a report (min 300 words) to detail the hand back...
Assessment 5.0: Hand back process Produce a report (min 300 words) to detail the hand back process as defined by the infrastructure controller and detail the factors that should be considered as part of the hand back process including the potential areas for special consideration which should be confirmed. Detail the requirements for construction records which form part of the hand back process. The assets will be handed-back to the procuring authority at contract expiration. It is good practice to...
produce a report (300 words min) which identifies the requirements for drainage within the railway infrastructure...
produce a report (300 words min) which identifies the requirements for drainage within the railway infrastructure and the methods of achieving adequate drainage. use a section of track as an example and illustrate your report with photographs and drawings as appropriate. explain the common failure modes associated with track drainage.
Assessment 4.0: Management of Quality Produce a report (min 300 words) detailing construction methodology and the...
Assessment 4.0: Management of Quality Produce a report (min 300 words) detailing construction methodology and the process for the management of quality of installation and progress reporting for either of the following: Plain line track renewals S&C Installation Include in the report an outline the management of quality of high output techniques for the following: Plain line track renewals Ballast cleaning S&C Modular Installation methods Also include the management of quality of track renewals process for special circumstances including: Tunnels...
Assessment 11.0: Welding processes Produce a short report with diagrams (min 300 words) on the jointing...
Assessment 11.0: Welding processes Produce a short report with diagrams (min 300 words) on the jointing of rail using welding techniques including: • Alumino-thermic • Flash butt welding if you know the answer could you write it in text as I don't understand the handwriting
Assessment 8.0: Wheel/rail interface Produce a report (500 words min) to describe the wheel/rail in relation...
Assessment 8.0: Wheel/rail interface Produce a report (500 words min) to describe the wheel/rail in relation to the following: • Gauge corner cracking • Rolling contact fatigue
What is the information to be furnished during the planning and design stages of report on...
What is the information to be furnished during the planning and design stages of report on the work- activities in an engineering project?
Answer each of the following in 250 words: 1. Describe the stages of the product life...
Answer each of the following in 250 words: 1. Describe the stages of the product life cycle 2. Describe the characteristics of services
Consider the seven stages of the Design Process. How far back in the process do you...
Consider the seven stages of the Design Process. How far back in the process do you think you would you have to begin, in order to solve this minimizing nurse fatigue and why?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT