Question

In: Civil Engineering

Assessment 9.0: Hand back process Produce a report (min 250 words) to detail the hand back...

Assessment 9.0: Hand back process

Produce a report (min 250 words) to detail the hand back process as defined by the Infrastructure Controller, and detail the factors that should be considered as part of the hand back process including the potential areas for special consideration which should be confirmed. Detail the requirements for maintenance records which form part of the hand back process.

Write it in text if you know the answer as I don't understand the handwriting

Solutions

Expert Solution

Ans.) Hand Back process - At the Contract expiration, The process of Handing back the assets to the Client. The requirements of Hand Back must always be clearly defined in the Contract so that the successful Awarded Bidder may project this into its financial model to meet the requirements. There should always be an acceptable condition of the Assets and useful durable life of asset at the expiration date which may be handed back to the Employer.

Factors & Potential Areas that should be accounted during Hand Back : The Works shall be taken over by the Employer when

  • (i) the Works have been completed in accordance with the Contract with Good Quality, with complete Hand back of Records maintained for Quality , Measurements records, Third Party test reports , Progress Repots, Registers as per duly approved formats with Signatures of representatives of Contractor, Engineer and the Employer including the matters regarding Time for Completion &
  • (ii) a Taking-Over Certificate for the Works has been issued, or is deemed to have been issued in accordance with this Sub-Clause
  • (iii) Returning the Bank Guarantees/Retention money to the Contractor with respect to Contract Terms.
  • (iv) Remaining Tests to be conducted on Completion which may be conducted by the Contractor within defect Liability period.

The Employer may reject the application, giving reasons and specifying the work required to be done by the Contractor to enable the Taking-Over Certificate to be issued.

Details of Maintenance Records & other factors : After the Engineer has issued a Taking-Over Certificate for a part of the Works, the Contractor shall be given the earliest opportunity to take such steps as may be necessary to carry out any outstanding Tests on Completion. The Contractor shall carry out these Tests on Completion as soon as practicable before the expiry date of the relevant Defects Notification Period.

In order that the Works and Contractor’s Documents, and each Section, shall be in the condition required by the Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as soon as practicable thereafter, the Contractor shall:

  1. complete any work which is outstanding on the date stated in a Taking-Over Certificate, within such reasonable time as is instructed by the Engineer, and
  2. execute all work required to remedy defects or damage, as may be notified by (or on behalf of) the Employer on or before the expiry date of the Defects Notification Period for the Works or Section (as the case may be).

If a defect appears or damage occurs, the Contractor shall be notified accordingly, by (or on behalf of) the Employer.

If a Taking-Over Certificate has been issued for a part of the Works if specified in contract, the delay damages thereafter for completion of the remainder of the Works shall be reduced. Similarly, the delay damages for the remainder of the Section (if any) in which this part is included shall also be reduced. For any period of delay after the date stated in this Taking-Over Certificate, the proportional reduction in these delay damages shall be calculated as the proportion which the value of the part so certified bears to the value of the Works or Section (as the case may be) as a whole


Related Solutions

Assessment 5.0: Hand back process Produce a report (min 300 words) to detail the hand back...
Assessment 5.0: Hand back process Produce a report (min 300 words) to detail the hand back process as defined by the infrastructure controller and detail the factors that should be considered as part of the hand back process including the potential areas for special consideration which should be confirmed. Detail the requirements for construction records which form part of the hand back process. The assets will be handed-back to the procuring authority at contract expiration. It is good practice to...
produce a (250 words min) report that describes thedifferent stages o the signaling design process...
produce a (250 words min) report that describes the different stages o the signaling design process an how the information provided by signalling design is used by installation maintaince and/or testing
Assessment 4.0: Management of Quality Produce a report (min 300 words) detailing construction methodology and the...
Assessment 4.0: Management of Quality Produce a report (min 300 words) detailing construction methodology and the process for the management of quality of installation and progress reporting for either of the following: Plain line track renewals S&C Installation Include in the report an outline the management of quality of high output techniques for the following: Plain line track renewals Ballast cleaning S&C Modular Installation methods Also include the management of quality of track renewals process for special circumstances including: Tunnels...
Assessment 11.0: Welding processes Produce a short report with diagrams (min 300 words) on the jointing...
Assessment 11.0: Welding processes Produce a short report with diagrams (min 300 words) on the jointing of rail using welding techniques including: • Alumino-thermic • Flash butt welding if you know the answer could you write it in text as I don't understand the handwriting
Produce a report detailing the planning process for an OLE construction activity (min 600 words), using...
Produce a report detailing the planning process for an OLE construction activity (min 600 words), using a recent work as the basis for the report. The report should detail the following: • Strategic planning process for engineering possessions • Planning of engineer’s trains and on track plant • Ordering and supply of materials • Manpower requirements • Road rail machines requirements • Possession arrangements • On track plant detailed plans • Interface with other engineering functions • Isolation of Traction...
Assessment 8.0: Wheel/rail interface Produce a report (500 words min) to describe the wheel/rail in relation...
Assessment 8.0: Wheel/rail interface Produce a report (500 words min) to describe the wheel/rail in relation to the following: • Gauge corner cracking • Rolling contact fatigue
Assessment 9.0: Soil Mechanics Produce a 300 word report which identifies the cause and effect of...
Assessment 9.0: Soil Mechanics Produce a 300 word report which identifies the cause and effect of slips in embankments and cuttings and the affect it might have on safety of the line. The report should include the theory behind soil mechanics – soil saturation, subsidence, inappropriate mineral extraction, overloading of embankment by neighbouring construction and subterranean fires. Include a range of potential solutions to embankment stability risks. Would prefer in Text as don't understand the handwriting on here.
produce a report (300 words min) which identifies the requirements for drainage within the railway infrastructure...
produce a report (300 words min) which identifies the requirements for drainage within the railway infrastructure and the methods of achieving adequate drainage. use a section of track as an example and illustrate your report with photographs and drawings as appropriate. explain the common failure modes associated with track drainage.
Assessment 5.0: Ensuring fitness for purpose of the signalling system 5.1 Produce a report (300 words...
Assessment 5.0: Ensuring fitness for purpose of the signalling system 5.1 Produce a report (300 words min) that explains how the sequential stages of installation, testing and commissioning of a new signalling system ensure it is fit for purpose. Your report should focus on the individual stages and the competence and equipment required and how the results of activities are recorded to be passed on to the next stages. 5.2 Produce a report (300 words min) that describes the need...
PLS EXPLAIN IN DETAIL THE SAND MOLD CASTING PROCESS. PLS WRITE IN MORE THAN 250 WORDS...
PLS EXPLAIN IN DETAIL THE SAND MOLD CASTING PROCESS. PLS WRITE IN MORE THAN 250 WORDS ILLUSTRATING EACH AND EVERY FINE DETAIL.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT