Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent,...

  1. Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below.

    Frequently Ordering
    Customers
    Less Frequently
    Ordering Customers
    Sales orders 43,000 4,300
    Order size 15 150
    Average unit manufacturing cost $45 $45
    Order-processing activity costs:
        Processing sales orders $2,878,500

    Order-filling capacity is purchased in steps (order-processing clerks) of 1,000, each step costing $46,000; variable order-filling activity costs are $35 per order. The activity capacity is 45,000 orders; thus, the total order-filling cost is $3,725,500 [(45 steps × $46,000) + ($35 × 47,300)]. Current practice allocates ordering cost in proportion to the units purchased.

    Deeds recently lost a bid for 100 units. (The per-unit bid price was $2 per unit more than the winning bid.) The manager of Deeds was worried that this was a recurring trend for the larger orders. (Other large orders had been lost with similar margins of loss.) No such problem was taking place for the smaller orders; the company rarely lost bids on smaller orders.

    Required:

    1. Calculate the unit bid price offered to Deeds’s customers assuming that order-filling cost is allocated to each customer category in proportion to units sold. Note: Do not round interim calculations. Round your final answer to the nearest cent.
    $

    2. Assume that a newly implemented ABC system concludes that the number of orders placed is the best cost driver for the order-filling activity. Assign order-filling costs using this driver to each customer type and then calculate the new unit bid price for each customer type. Note: Do not round interim calculations. Round the final order cost allocation to the nearest whole dollar. Round final bid prices to the nearest cent.

    Order Cost Allocation
    round to whole dollar
    Bid Price
    round to two decimals
    Frequently ordering $ $
    Less frequently ordering $ $

    Using this new price, would Deeds have won the bid for the units recently lost?

    • Yes
    • No

    3. What if Deeds offers a discount for orders of 35 units or more to the frequently ordering customers? Assume that all the frequently ordering customers can and do take advantage of this offer at the minimum level possible. Compute the new order cost allocation and bid price.

    Note: Round the number of steps UP to the nearest whole number, using that result in future calculations. For the Order Cost Allocation and Bid Price, do not round interim calculations. Then round the final order cost allocation to the nearest whole dollar and final Bid Price the nearest cent.

    Order Cost Allocation
    round to whole dollar
    Bid Price
    round to two decimals
    Frequently ordering $ $

    Can Deeds offer the original price from Requirement 1 to the frequently ordering customers and not decrease its profitability?

    • Yes
    • No

Solutions

Expert Solution

Answer :-

1.

Order-filling cost is allocated to each customer category in proportion to units sold
Total units sold=
(43,000*15)+(4,300*150)=
1,290,000
i.e.,645,000 + 645,000 each category
So,order cost allocation for either customer category=
645,000/1,290,000*3,725,500=
18,62,750
So,Bid price for either category=
(Mfg.Order Processing cost)*(1=Mark-up%)
(45+(18,62,750/645,000))*1.40=
67.04

2.

No. of orders placed is the best cost driver for the order-filling activity
Order cost allocation:
Frequently ordering customers
43000/47,300 * 3,725,500=
3,386,818
Less Frequently ordering customer:
4,300/47,300 * 3,725,500=
338,689
Now calculating the Bid-price for each category as in 1 above,
For Frequently ordering customers
(45+(3386818/645,000))*1.40=
70.35
for Less Frequently ordering customer:
(45+(338689/645,000))*1.40=
63.73
Yes. As per the ABC costing, Deed could have won the bid, as it is almost $ 4 (67.04-63.73) less than the original bid in 1.

3.

Given----Assume that all the frequently ordering customers can and do take advantage of this offer
No.of Orders for 35 units at a time = (43000*15)/35 = 18,429 (frequent order customers)
So, now the total orders will be = 18,429 + 4,300 = 22,729
No.of steps=22,729/1,000 = 22.7 ie. 23 steps
Order-filling cost= (23* $ 46000)+(35*22729)= $ 18,53,515
Order-filling cost allocated to the frequent category=(18,429/22,729)* $18,53,515 = $15,02,857
So, Bid Price for frequent category customers=(45+(15,02,857/645,000))*1.40= $ 66.26
Yes.
As both the bid prices are almost the same, Deeds can offer the old price & quantity discounts without much decrease in profits.

Related Solutions

Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent,...
Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 39,000 3,900 Order size 15 150 Average unit manufacturing cost $45 $45 Order-processing activity...
Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent,...
Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 37,000 3,700 Order size 15 150 Average unit manufacturing cost $40 $40 Order-processing activity...
Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent,...
Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 39,000 3,900 Order size 15 150 Average unit manufacturing cost $50 $50 Order-processing activity...
Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost...
Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 37,000 3,700 Order size 15 150 Average unit manufacturing cost $45...
Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost...
Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 37,000 3,700 Order size 15 150 Average unit manufacturing cost $45...
Cornerstone Exercise 11.3 (Algorithmic) Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment...
Cornerstone Exercise 11.3 (Algorithmic) Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 39,000 3,900 Order size 15 150 Average...
External Linkages, Customer Costing, Customer Profitability Emery Company sells small machine parts to heavy equipment manufacturers...
External Linkages, Customer Costing, Customer Profitability Emery Company sells small machine parts to heavy equipment manufacturers for an average price of $2.80 per part. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Each time an order is placed and processed, a setup is required. Scheduling is also needed to coordinate the many different orders that come in and place demands on the plant’s manufacturing resources. Emery also inspects...
External Linkages, Customer Costing, Customer Profitability Emery Company sells small machine parts to heavy equipment manufacturers...
External Linkages, Customer Costing, Customer Profitability Emery Company sells small machine parts to heavy equipment manufacturers for an average price of $1.70 per part. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Each time an order is placed and processed, a setup is required. Scheduling is also needed to coordinate the many different orders that come in and place demands on the plant’s manufacturing resources. Emery also inspects...
Machine Parts Co. produces custom-made machine parts. Machine Parts Co. recently implemented an activity-based management (ABM)...
Machine Parts Co. produces custom-made machine parts. Machine Parts Co. recently implemented an activity-based management (ABM) system with the objective of reducing costs. Machine Parts Co. has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred fixed setup costs of $560,000 (salaries of 10...
Kaizen Costing Gordon Company produces custom-made machine parts. A setup activity is required for the batches...
Kaizen Costing Gordon Company produces custom-made machine parts. A setup activity is required for the batches of parts that it produces. Activity output is measured using setup hours. The value-added standard (SQ) for this activity is zero. On July 1, at the beginning of the fiscal year, 18 setup hours were allowed and used per batch. The standard wage rate for setup labor is $17 per setup hour. During the first quarter of the new fiscal year, the company is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT