In: Accounting
Correct Answer –the total Activity for the activity cost pool.
Explanation
Activity rate for each activity depends on multiple cost drivers such as labor hour, machine hours , setup hours, inspections etc. all the driver’s total quantity is used to calculate activity rate for each activity and not just one activity driver.
Given below is schedule of activity rates for better understanding.
Calculation of Activity rates |
|||||
Activity Cost Pool |
Activity Measure |
Estimated Overhead Cost (A) |
Expected Activity (B) |
Activity rate (A/B) |
|
Machining |
Machine-hours |
$ 568,484.00 |
10,000 |
$ 56.85 |
Per MHs |
Machine setups |
Number of setups |
$ 15,442,154.00 |
290 |
$ 53,248.81 |
Per setups |
Production design |
Number of products |
$ 55,485.00 |
2 |
$ 27,742.50 |
Per products |
General factory |
Direct labor-hours |
$ 21,245.00 |
12,000 |
$ 1.77 |
Per DLHs |
Total |
$ 16,087,368.00 |