Question

In: Economics

A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...

A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.03 million, and the concrete option has an initial cost of $2.42 million. Every 25 years, the steel bridge must be painted at a cost of $420,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to last 75 years. Both are assumed to be identically replaced indefinitely. Based on the shortest acceptable analysis period for each option, determine the equivalent uniform annual cost (EUAC) for the best option using an interest rate of 8%. Express your answer in $ to the nearest $1,000.

Solutions

Expert Solution

We have the following information

Steel Girder Bridge

Concrete Bridge

Initial Cost

$2,030,000

$2,420,000

Painting Cost (every 25 years)

$420,000

0

Life

50 years

75 years

Interest Rate

8%

8%

Steel Girder Bridge

Equivalent annual worth = 2,030,000(A/P, i, n) + 420,000(A/P, i, n) + 420,000(A/P, i, n)

Equivalent annual worth = 2,030,000(A/P, 8%, 50) + 420,000(A/P, 8%, 25) + 420,000(A/P, 8%, 50)

Equivalent annual worth = 2,030,000[0.08(1 + 0.08)50/((1 + 0.08)50 – 1)] + 420,000[0.08(1 + 0.08)25/((1 + 0.08)25 – 1)] + 420,000[0.08(1 + 0.08)50/((1 + 0.08)50 – 1)]

Equivalent annual worth = (2,030,000 × 0.0817) + (420,000 × 0.0937) + (420,000 × 0.0817)

Equivalent annual worth of Steel Girder Bridge = $239,519

Concrete Bridge

Equivalent annual worth = 2,420,000(A/P, i, n)

Equivalent annual worth = 2,420,000(A/P, 8%, 75)

Equivalent annual worth = 2,420,000[0.08(1 + 0.08)75/((1 + 0.08)75 – 1)]

Equivalent annual worth = 2,420,000 × 0.0802

Equivalent annual worth of Concrete Bridge = $194,084

Since, the equivalent annual worth of Concrete Bridge is lower, so Concrete Bridge should be selected.


Related Solutions

A firm is considering two mutually exclusive projects, A and B. The projects are different in...
A firm is considering two mutually exclusive projects, A and B. The projects are different in that they have different returns depending on general economic conditions. The firm forecasts that return on the market, and the returns on each project, along with their associated probabilities will be given by the following table. You can assume a 5% risk free rate and a 6% market risk premium. Assume the CAPM holds. Compare the expected returns to the cost of capital for...
A firm is evaluating two mutually exclusive projects that have unequal lives. The firm must evaluate...
A firm is evaluating two mutually exclusive projects that have unequal lives. The firm must evaluate the projects using the annualized net present value approach and recommend which project they should select.-- Calculate and make decision base on the following. The firm's cost of capital has been determined to be 18 percent, and the projects have the following initial investments and cash flows: Project W Project Y Initial Investment 40,000 58,000 cash flow 1 20,000 30,000 2 20,000 35,000 3...
The Sloan Corporation is trying to choose between the following two mutually exclusive design projects:   ...
The Sloan Corporation is trying to choose between the following two mutually exclusive design projects:    Year Cash Flow (I) Cash Flow (II) 0 –$ 61,000 –$ 18,300 1 28,100 9,950 2 28,100 9,950 3 28,100 9,950     a-1 If the required return is 10 percent, what is the profitability index for both projects? (Do not round intermediate calculations. Round your answers to 3 decimal places, e.g., 32.161.)    Profitability Index   Project I      Project II       a-2 If...
eBook Haley’s Crockett Designs Inc. is considering two mutually exclusive projects. Both projects require an initial...
eBook Haley’s Crockett Designs Inc. is considering two mutually exclusive projects. Both projects require an initial investment of $12,000 and are typical average-risk projects for the firm. Project A has an expected life of 2 years with after-tax cash inflows of $7,000 and $8,000 at the end of Years 1 and 2, respectively. Project B has an expected life of 4 years with after-tax cash inflows of $8,000 at the end of each of the next 4 years. The firm’s...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,700 ​$12,700 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$880 ​$1,530 Most likely 1,680 1,680 Optimistic 2,470 1,710 a. Determine the range of annual...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​$12,400 ​$12,400 Outcome Annual cash inflows ​(CF ​) Pessimistic ​$840 ​$1,560 Most likely 1,650 1,650 Optimistic 2,450 1,740 a. Determine the range of annual cash inflows...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions...
Basic scenario analysis  -- Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​12,200 ​12,200 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$800 ​$1,560 Most likely 1,700 1,700 Optimistic 2,480 1,720 a. Determine the range of...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis    Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​ pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF0​) ​ $12,900    ​ $12,900    Outcome Annual cash inflows ​(CF ​) Pessimistic ​$870 ​$1,530 Most likely 1,690 1,690 Optimistic 2,500 1 720 a. Determine...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to...
Basic scenario analysis   Prime Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The​ firm's financial analysts have developed​pessimistic, most​ likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. Project A Project B Initial investment ​(CF 0CF0​) ​$12,800 ​$12,800 Outcome Annual cash inflows ​(CFCF ​) Pessimistic ​$860 ​$1,530 Most likely 1,680 1,680 Optimistic 2,500 1,780 a. Determine the range of annual cash...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT