In: Accounting
A company makes two products, the variable costs are as follows;
Product A Product B
£ £
Direct materials 1 3
Direct labour (£6 per hour) 6 3
Variable overhead 1 1
8 7
The sale price of A is £14 and B is £11. During the month of July the availability of Direct Labour is limited to 5000 hours due to staff taking holidays. Sales demand is expected to be 3000 units of A and 5000 units of B.
Monthly fixed costs are £20,000 and opening stocks are zero.
Required:
Answer a)
Calculation of deficiency in labor hours per month
Product A |
Product B |
Total |
|
Labor hours consumed per unit |
1.00 |
0.50 |
|
Expected sales demand per month |
3,000 Units |
5,000 Units |
|
Total Labor hours required per month (A) |
3,000 |
3,000 |
6,000 |
Total Labor hours available per month (B) |
5,000 |
||
Deficiency in Labor hours (A) - (B) |
1,000 |
Therefore 1,000 labor hours are deficient per month.
Answer b)
Calculation of priority ranking for production
Product A |
Product B |
|
Selling Price per unit (A) |
£ 14.00 |
£ 11.00 |
Less: Variable Costs |
||
Direct Materials |
£ 1.00 |
£ 3.00 |
Direct Labor |
£ 6.00 |
£ 3.00 |
Variable Overheads |
£ 1.00 |
£ 1.00 |
Total Variable Costs (B) |
£ 8.00 |
£ 7.00 |
Contribution margin per unit (A) - (B) |
£ 6.00 |
£ 4.00 |
Labor hours consumed per unit |
1.00 |
0.50 |
Contribution margin per labor hour |
£ 6.00 |
£ 8.00 |
Ranking |
II |
I |
Working Notes:
Calculation of Labor hours required per unit of each product.
Labor hour per unit = Total labor cost per unit of the product/ Direct Labor rate per hour
Product A:
Labor hour per unit = £ 6 per unit/ £ 6 per hour
= 1 labor hour per unit
Product B:
Labor hour per unit = £ 2 per unit/ £ 6 per hour
= 0.50 labor hour per unit
Answer c)
Calculation of maximum profit
Product A |
Product B |
Total |
|
Number of Units produced and sold (A) |
2,500 |
5,000 |
|
Contribution margin per unit (B) |
£ 6.00 |
£ 4.00 |
|
Total Contribution margin (A) x (B) |
£ 15,000 |
£ 20,000 |
£ 35,000 |
Less: Monthly fixed costs |
£ 20,000 |
||
Net profit |
£ 15,000 |
Therefore maximum net profit with the available 5,000 labor hours is £ 15,000.
Working Note:
Calculation of optimum Product mix with available 5,000 labor hours
Direct labor hours per unit |
Number of Units Produced and Sold |
Total Labor hours consumed |
|
Product B |
0.50 |
5,000 |
2,500 |
Product A |
1.00 |
2,500 |
2,500 |
Total |
5,000 |
Answer d)
Calculation of maximum profit
With the available maximum number of labor hours (i.e. 5,000 labor hours), the company is able to produce 5,000 units of product B and 2,500 units of Product A.
Maximum demand of product B is fulfilled.
Maximum demand of product A is 3,000 units. However, the company is able to produce and sell 2,500 units of Product A with the current available machine hours. Thus 500 units of product A could not be produced and sold. The loss of profit will be equal to the contribution margin that these products would have earned.
Loss Profit = Number of units of product A that could not be produced and sold X contribution margin per unit of Product A
= 500 units X £ 6.00 per unit
= £ 3,000
Therefore the loss of profit due to limiting factor is £ 3,000.
Calculation of maximum amount the company would be willing to pay for each additional labor hour
Since the maximum demand of product A could not fulfilled due to limiting factor (i.e. Labor hours), the maximum the company would be willing to pay for each additional labor hour will be equal to the contribution margin per labor hour for Product A, i.e. £ 6.00.