In: Accounting
Activity Rates and Product Costs using Activity-Based Costing
Lonsdale Inc. manufactures entry and dining room lighting
fixtures. Five activities are used in manufacturing the fixtures.
These activities and their associated budgeted activity costs and
activity bases are as follows:
Activity |
Budgeted Activity Cost |
Activity Base |
|
Casting | $570,000 | Machine hours | |
Assembly | 80,000 | Direct labor hours | |
Inspecting | 42,000 | Number of inspections | |
Setup | 38,000 | Number of setups | |
Materials handling | 23,750 | Number of loads |
Corporate records were obtained to estimate the amount of
activity to be used by the two products. The estimated
activity-base usage quantities and units produced follow:
Activity Base | Entry | Dining | Total | |||
Machine hours | 6,000 | 13,000 | 19,000 | |||
Direct labor hours | 3,000 | 2,000 | 5,000 | |||
Number of inspections | 600 | 400 | 1,000 | |||
Number of setups | 300 | 200 | 500 | |||
Number of loads | 450 | 500 | 950 | |||
Units produced | 6,000 | 3,000 | 9,000 |
a. Determine the activity rate for each activity.
Activity | Activity Rate | |
Casting | $ | per machine hour |
Assembly | $ | per direct labor hour |
Inspecting | $ | per inspection |
Setup | $ | per setup |
Materials handling | $ | per load |
b. Use the activity rates in (a) to determine the total and per-unit activity costs associated with each product. Round the per unit amounts to the nearest cent.
Product | Total Activity Cost | Activity Cost Per Unit |
Entry Lighting Fixtures | $ | $ |
Dining Room Lighting Fixtures | $ | $ |
Answer-a)-
ACTIVITY RATE | |
Activity costs pool | Activity rate |
Casting | $30 per machine hour |
Assembly | $16 per labor hour |
Inspecting | $42 per inspection |
Setup | $76 per setup |
Materials handling | $25 per load |
Explanation-
Calculation of actvity rate | ||||
Activity cost pool | Activity Measure | Estimated overhead cost (a) | Expected activity (b) | Activity rate (c=a/b) |
$ | $ | |||
Casting | Number of machine hours | 570000 | 19000 | $30 per machine hour |
Assembly | Number of direct labor hours | 80000 | 5000 | $16 per labor hour |
Inspecting | Number of inspections | 42000 | 1000 | $42 per inspection |
Setup | Number of setups | 38000 | 500 | $76 per setup |
Materials handling | Number of loads | 23750 | 950 | $25 per load |
Total | 753750 |
b)-
LONSDALE INC. | |||
Calculation of total & per unit activity cost of each product | |||
Particluars | Entry Lighting Fixtures | Dinning Room Lighting Fixtures | Total |
$ | $ | $ | |
Casting costs | 6000 machine hours*$30 per machine hour= $180000 | 13000 machine hours*$30 per machine hour= $390000 | 570000 |
Assembly costs | 3000 Direct Labor Hours*$16 per Direct Labor Hour= $48000 | 2000 Direct Labor Hours*$16 per Direct Labor Hour= $32000 | 80000 |
Inspecting costs | 600 inspections*$42 per inspection=$25200 | 400 inspections*$42 per inspection=$16800 | 42000 |
Set up costs | 300 setups*$76 per set up= $22800 | 200 setups*$76 per set up= $15200 | 38000 |
Material handling costs | 450 loads*$25 per load= $11250 | 500 loads*$25 per load= $12500 | 23750 |
Total activity costs (a) | 287250 | 466500 | 753750 |
Number of units (b) | 6000 | 3000 | 9000 |
Activity cost per unit (c=a/b) | 47.88 | 155.50 | 83.75 |