In: Accounting
Activity Rates and Product Costs using Activity-Based Costing
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows:
Activity Budgeted
Activity Cost
Activity Base
Casting $241,280 Machine
hours
Assembly 158,700 Direct labor
hours
Inspecting 32,160 Number of
inspections
Setup 44,950 Number of
setups
Materials handling 46,500
Number of loads
Corporate records were obtained to estimate the amount of activity
to be used by the two products. The estimated activity-base usage
quantities and units produced follow:
Activity Base Entry Dining
Total
Machine hours 4,920
4,360 9,280
Direct labor hours 4,230
6,350 10,580
Number of inspections 2,040
640 2,680
Number of setups 230
60 290
Number of loads 730
200 930
Units produced 9,800
4,900 14,700
a. Determine the activity rate for each activity. If required,
round the rate to the nearest dollar.
Activity Activity Rate
Casting $
per machine hour
Assembly $
per direct labor hour
Inspecting $
per inspection
Setup $
per setup
Materials handling $
per load
b. Use the activity rates in (a) to determine the total and
per-unit activity costs associated with each product. Round the per
unit amounts to the nearest cent.
Product Total Activity Cost Activity
Cost Per Unit
Entry Lighting Fixtures $
$
Dining Room Lighting Fixtures $
$
Answer-a)-
ACTIVITY RATE | |
Activity costs pool | Activity rate |
Casting | $26 per machine hour |
Assembly | $15 per labor hour |
Inspecting | $12 per inspection |
Setup | $155 per setup |
Materials handling | $50 per load |
Explanation-
Calculation of actvity rate | ||||
Activity cost pool | Activity Measure | Estimated overhead cost (a) | Expected activity (b) | Activity rate (c=a/b) |
$ | $ | |||
Casting | Number of machine hours | 241280 | 9280 | $26 per machine hour |
Assembly | Number of direct labor hours | 158700 | 10580 | $15 per labor hour |
Inspecting | Number of inspections | 32160 | 2680 | $12 per inspection |
Setup | Number of setups | 44950 | 290 | $155 per setup |
Materials handling | Number of loads | 46500 | 930 | $50 per load |
Total | 523590 |
b)-
LONSDALE INC. | |||
Calculation of total & per unit activity cost of each product | |||
Particluars | Entry Lighting Fixtures | Dinning Room Lighting Fixtures | Total |
$ | $ | $ | |
Casting costs | 4920 machine hours*$26 per machine hour= $127920 | 4360 machine hours*$26 per machine hour= $113360 | 241280 |
Assembly costs | 4230 Direct Labor Hours*$15 per Direct Labor Hour= $63450 | 6350 Direct Labor Hours*$15 per Direct Labor Hour= $95250 | 158700 |
Inspecting costs | 2040 inspections*$12 per inspection=$24480 | 640 inspections*$12 per inspection=$7680 | 32160 |
Set up costs | 230 setups*$155 per set up= $35650 | 60 setups*$155 per set up= $9300 | 44950 |
Material handling costs | 730 loads*$50 per load= $36500 | 200 loads*$50 per load= $10000 | 46500 |
Total activity costs (a) | 288000 | 235590 | 523590 |
Number of units (b) | 9800 | 4900 | 14700 |
Activity cost per unit (c=a/b) | 29.39 | 48.08 | 35.62 |