In: Accounting
Approximately Relevant ABC
Reducir, Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for the cylinders in the Cutting and Welding Department. Other parts and the subassembly are then assembled in the Assembly Department. The activities, expected costs, and drivers associated with these two manufacturing processes are given below.
Process | Activity | Cost | Activity Driver | Expected Quantity |
Cutting and Welding | Welding | $ 776,000 | Welding hours | 4,000 |
Machining | 450,000 | Machine hours | 10,000 | |
Inspecting | 448,250 | No. of inspections | 1,000 | |
Materials handling | 300,000 | No. of batches | 12,000 | |
Setups | 240,000 | No. of setups | 100 | |
$2,214,250 | ||||
Assembly | Changeover | $ 180,000 | Changeover hours | 1,000 |
Rework | 61,750 | Rework orders | 50 | |
Testing | 300,000 | No. of tests | 750 | |
Materials handling | 380,000 | No. of parts | 50,000 | |
Engineering support | 130,000 | Engineering hours | 2,000 | |
$1,051,750 |
Other overhead activities, their costs, and drivers are listed below.
Activity | Cost | Activity Driver | Quantity |
Purchasing | $ 135,000 | Purchase requisitions | 500 |
Receiving | 274,000 | Receiving orders | 2,000 |
Paying suppliers | 225,000 | No. of invoices | 1,000 |
Providing space and utilities | 100,000 | Machine hours | 10,000 |
Total | $ 734,000 |
Other production information concerning the two hydraulic cylinders is also provided:
Cylinder A | Cylinder B | ||||
Units produced | 1,500 | 3,000 | |||
Welding hours | 1,600 | 2,400 | |||
Machine hours | 3,000 | 7,000 | |||
Inspections | 500 | 500 | |||
Moves | 7,200 | 4,800 | |||
Batches | 45 | 55 | |||
Changeover hours | 540 | 460 | |||
Rework orders | 5 | 45 | |||
No. of tests | 500 | 250 | |||
Parts | 40,000 | 10,000 | |||
Engineering hours | 1,500 | 500 | |||
Requisitions | 425 | 75 | |||
Receiving orders | 1,800 | 200 | |||
Invoices | 650 | 350 |
Process | Activity | Cost |
Cutting and Welding | Welding | $ 2,000,000 |
Machining | 1,000,000 | |
Inspecting | 50,000 | |
Materials handling | 72,000 | |
Setups | 400,000 | |
$3,522,000 | ||
Assembly | Changeover | $ 28,000 |
Rework | 50,000 | |
Testing | 40,000 | |
Materials handling | 60,000 | |
Engineering support | 70,000 | |
$248,000 |
Other overhead activities:.
Activity | Cost |
Purchasing | $ 50,000 |
Receiving | 70,000 |
Paying suppliers | 80,000 |
Providing space and utilities | 30,000 |
$230,000 |
The per unit overhead cost using the 14 activity-based drivers is $1,108 and $779 for Cylinder A and Cylinder B, respectively.
Required:
1. Determine the percentage of total costs represented by the three most expensive activities.
%
2. If required, round your interim calculations
and final answers to the nearest dollar.
Allocate the costs of all other activities to the three activities
identified in Requirement 1 in proportion to their individual
activity costs.
Allocation | |
Welding | $ |
Machining | $ |
Setups | $ |
Calculate the total activity costs of all the three activities.
Cost pools | |
Welding | $ |
Machining | $ |
Setups | $ |
Activity Rates | ||
Welding | $ | per welding hour |
Machining | $ | per machine hour |
Setups | $ | per batch |
Now assign these total costs to the products using the drivers of the three chosen activities.
Cylinder A | Cylinder B | |||
Rate 1 (welding) | $ | $ | ||
Rate 2 (machining) | $ | $ | ||
Rate 3 (setups) | $ | $ | ||
Total overhead costs | $ | $ | ||
Unit overhead costs | $ | $ |
3. Using the costs assigned in Requirement 2, calculate the percentage error using the ABC costs as a benchmark. Round your answers to one decimal place. If an item is negative, use a minus (-) sign to indicate.
Percentage error | |
Cylinder A | % |
Cylinder B | % |
1. Activities highlighted in bold in last column are most expensive.
Activity | Cost | Expected Quantity | Cylinder A Units | Cylinder B Units | Cylinder A Cost | Cylinder B Cost | %age of total cost |
Welding | 2,000,000 | 4,000 | 1,600 | 2,400 | 800,000 | 1,200,000 | 50.00% |
Machining | 1,000,000 | 10,000 | 3,000 | 7,000 | 300,000 | 700,000 | 25.00% |
Inspecting | 50,000 | 1,000 | 500 | 500 | 25,000 | 25,000 | 1.25% |
Materials handling | 72,000 | 12,000 | 7,200 | 4,800 | 43,200 | 28,800 | 1.80% |
Setups | 400,000 | 100 | 45 | 55 | 180,000 | 220,000 | 10.00% |
3,522,000 | 1,348,200 | 2,173,800 | |||||
Changeover | 28,000 | 1,000 | 540 | 460 | 15,120 | 12,880 | 0.70% |
Rework | 50,000 | 50 | 5 | 45 | 5,000 | 45,000 | 1.25% |
Testing | 40,000 | 750 | 500 | 250 | 26,667 | 13,333 | 1.00% |
Materials handling | 60,000 | 50,000 | 40,000 | 10,000 | 48,000 | 12,000 | 1.50% |
Engineering support | 70,000 | 2,000 | 1,500 | 500 | 52,500 | 17,500 | 1.75% |
248,000 | 147,287 | 100,713 | |||||
Purchasing | 50,000 | 500 | 425 | 75 | 42,500 | 7,500 | 1.25% |
Receiving | 70,000 | 2,000 | 1,800 | 200 | 63,000 | 7,000 | 1.75% |
Paying suppliers | 80,000 | 1,000 | 650 | 350 | 52,000 | 28,000 | 2.00% |
Providing space and utilities | 30,000 | 10,000 | 3,000 | 7,000 | 9,000 | 21,000 | 0.75% |
230,000 | 166,500 | 63,500 | |||||
4,000,000 | 1,661,987 | 2,338,013 | 100.00% |
2. Allocation of other activity costs:
Cost of other 11 activities | 600,000 | |
Actual Cost | Allocation Cost | |
Welding | 2,000,000 | 352,941 |
Machining | 1,000,000 | 176,471 |
Setups | 400,000 | 70,588 |
Total | 3,400,000 | 600,000 |
Total Activity Costs:
Actual Cost | Allocation Cost | Total Costs | |
Welding | 2,000,000 | 352,941 | 2,352,941 |
Machining | 1,000,000 | 176,471 | 1,176,471 |
Setups | 400,000 | 70,588 | 470,588 |
Total | 3,400,000 | 600,000 | 4,000,000 |
Activity rates:
Total Costs | Expected Quantity | Activity Rates | |
Welding | 2,352,941 | 4,000 | 588 |
Machining | 1,176,471 | 10,000 | 118 |
Setups | 470,588 | 100 | 4,706 |
Total | 4,000,000 |
Total Costs to products:
Total Costs | Expected Quantity | Activity Rates | Cylinder A Units | Cylinder B Units | Cylinder A Cost | Cylinder B Cost | |
Welding | 2,352,941 | 4,000 | 588 | 1,600 | 2,400 | 941,176 | 1,411,765 |
Machining | 1,176,471 | 10,000 | 118 | 3,000 | 7,000 | 352,941 | 823,530 |
Setups | 470,588 | 100 | 4,706 | 45 | 55 | 211,765 | 258,823 |
Total | 4,000,000 | Total Overhead costs | 1,505,882 | 2,494,118 | |||
Units | 1,500 | 3,000 | |||||
Unit overhead costs | 1,004 | 831 |
3. Percentage error using ABC costs as benchmark:
To calculate %age error, we need to allocate expected costs of ABC into Cylinder A and B as we did in req 2:
Activity | Cost | Expected Quantity | Cylinder A Units | Cylinder B Units | Cylinder A Cost | Cylinder B Cost |
Welding | 776,000 | 4,000 | 1,600 | 2,400 | 310,400 | 465,600 |
Machining | 450,000 | 10,000 | 3,000 | 7,000 | 135,000 | 315,000 |
Inspecting | 448,250 | 1,000 | 500 | 500 | 224,125 | 224,125 |
Materials handling | 300,000 | 12,000 | 7,200 | 4,800 | 180,000 | 120,000 |
Setups | 240,000 | 100 | 45 | 55 | 108,000 | 132,000 |
2,214,250 | 957,525 | 1,256,725 | ||||
Changeover | 180,000 | 1,000 | 540 | 460 | 97,200 | 82,800 |
Rework | 61,750 | 50 | 5 | 45 | 6,175 | 55,575 |
Testing | 300,000 | 750 | 500 | 250 | 200,000 | 100,000 |
Materials handling | 380,000 | 50,000 | 40,000 | 10,000 | 304,000 | 76,000 |
Engineering support | 130,000 | 2,000 | 1,500 | 500 | 97,500 | 32,500 |
1,051,750 | 704,875 | 346,875 | ||||
Purchasing | 135,000 | 500 | 425 | 75 | 114,750 | 20,250 |
Receiving | 274,000 | 2,000 | 1,800 | 200 | 246,600 | 27,400 |
Paying suppliers | 225,000 | 1,000 | 650 | 350 | 146,250 | 78,750 |
Providing space and utilities | 100,000 | 10,000 | 3,000 | 7,000 | 30,000 | 70,000 |
734,000 | 537,600 | 196,400 | ||||
4,000,000 | Expected Costs | 2,200,000 | 1,800,000 |
Percent error:
Cylinder A | Cylinder B | |
Expected Costs | 2,200,000 | 1,800,000 |
Actual Costs | 1661987 | 2338013 |
Percent Error | -24.46% | 29.89% |