In: Accounting
The Welding Department of Healthy Company has the following production and manufacturing cost data for February 2017. All materials are added at the beginning of the process. Manufacturing Costs Production Data Beginning work in process Beginning work in process 15,200 units, 1/10 complete Materials $18,100 Units transferred out 54,700 Conversion costs 14,760 $32,860 Units started 51,000 Materials 220,220 Ending work in process 11,500 units, 1/5 complete Labor 67,500 Overhead 89,880 Prepare a production cost report for the Welding Department for the month of February. (Round unit costs to 2 decimal places, e.g. 2.25 and all other answers to 0 decimal places, e.g. 1,225.) HEALTHY MANUFACTURING COMPANY Welding Department Production Cost Report For the Month Ended February 28, 2017 Equivalent Units Quantities Physical Units Materials Conversion Costs Units to be accounted for Work in process, February 1 Started into production Total units Units accounted for Transferred out Work in process, February 28 Total units Costs Materials Conversion Costs Total Unit costs Total Costs $ $ $ Equivalent units Unit costs $ $ $ Costs to be accounted for Work in process, February 1 $ Started into production Total costs $ Cost Reconciliation Schedule Costs accounted for Transferred out $ Work in process, February 28 Materials $ Conversion costs Total costs $ Click if you would like to Show Work for this question: Open Show Work
THORPE
MANUFACTURING COMPANY Welding Department Production Cost Report For the Month Ended February 28, 2017 |
|||
Equivalent Units | |||
Quantities | Physical units | Material | Conversion Cost |
Units to be accounted for | |||
Work in process, February 1 | 15200 | ||
Started into production | 51000 | ||
Total Units | 66200 | ||
Units accounted for | |||
Transferred out | 54700 | 54700 | 54700 |
Work in progress Feb 28 | 11500 | 11500 | 2300 |
Total Units | 66200 | 66200 | 57000 |
Costs | Material | Conversion Cost | Total |
Unit Costs | |||
Total Costs | 238320 | 172140 | 410460 |
Equivqlent Units | 66200 | 57000 | |
Unit Costs | 3.6 | 3.02 | 6.62 |
(18100+220220) = 238320 | |||
(14760+67500+89880)=172140 | |||
Costs to be accounted for | |
Work in process, February 1 | 32860 |
Started into production | 377600 |
Total Cost | 410460 |
220220+67500+89880 |
Cost Reconciliation Schedule | |||
Costs accounted for | |||
Transferred out | 362114 | (54700*6.62) | |
Work in process, February 28 | (11500*3.6) | ||
Materials | 41400 | (2300*3.02) | |
Conversion Cost | 6946 | 48346 | |
Total Costs | 410460 |