Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.60 | 29,000 | units |
Sprockets | 0.20 | 44,000 | units |
Additional information about the company follows:
Hubs require $27 in direct materials per unit, and Sprockets require $12.
The direct labor wage rate is $17 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 17,100 | 95 | 76 | 171 |
Special processing (machine-hours) | $ | 161,000 | 4,600 | 0 | 4,600 |
General factory (organization-sustaining) | $ | 158,200 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Complete this question by entering your answers in the tabs below.
Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
|
Just having some trouble figuring out the overhead cost per unit.
Hubs | Sprockets | |||
Answer | Working | Answer | Working | |
Direct materials | $ 27.00 | [given] | $ 12.00 | [given] |
Direct labor | $ 10.20 | 0.60 DLHs x $ 17 | $ 3.40 | 0.20 DLHs x $ 17 |
Overhead | $ 5.88 | [ (95 x$ 100) + (4600 x $35)]/29000 units] | $ 0.17 | [ (76 x $ 100) / 44000] |
Unit cost | $ 43.08 | $ 15.57 |
--Working
Activity Cost Pool | Overhead cost | Total Activity | Activity Rate | |
[A] | [B] | [C = A/B] | ||
Machine setups | $17,100 | 171 | $100.000 | per setup |
Special processing | $161,000 | 4600 | $35.00 | per MH |