Question

In: Accounting

On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...

On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase of the land and construction of the building, $1,500,000 was borrowed on March 1, 2019 on a 9%, 3-year note payable. Other than the construction note, the only debt outstanding during 2019 was a $1,000,000, 12%, 6-year note payable dated January 1, 2019. The interest cost to be capitalized during 2019 is

Select one: a. $ 195,000 b. $ 183,000 c. $ 159,000 d. $ 135,000

Solutions

Expert Solution

Answer:

Option d is the correct answer. i.e. $135,000

Explanation:

Payment date Expenditures Capitlization
period
Weight Weighted
expenditures
Mar.1 $   1,200,000 7 months 0.58 $          700,000
May.1 $   1,680,000 5 months 0.42 $          700,000
Aug.1 $   3,000,000 2 months 0.17 $          500,000
Sep.30 $   4,800,000 0 months 0.00 $                     -  
Weighted-Average Accumulated Expenditures $      1,900,000
Funding Amount Rate Avoidable Interest
Specific Loan (9% note) $   1,500,000 9.00% $                 135,000
General Loan (12% notes) $      400,000 12.00% $                   48,000
$                 135,000
Loan Amount Rate Actual Interest
Construction loan $   1,500,000 9% $                   78,750
12% 6-year note payable $   1,000,000 12% $                 120,000
Actual Interest cost $                 198,750

Interest cost to be capitalized is lower of actual interest or avoidable interest.

Hence, capitalized interest cost during 2019 = $135,000


Related Solutions

On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher’s accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5 Construction costs incurred during the year, $180,000; estimated costs to complete, $630,000; progress billings during the year, $153,000; and collections, $140,000. 20X6...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available: 2019 2020 Cost Incurred $1,458,000 $1,620,000 Estimated costs to complete 1,560,000 - Billed 1,700,000 1,900,000 Collections during the year 1,440,000 2,160,000 Miller uses the percentage-of-completion method. Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019 and 2020? b) Prepare all journal entries for 2019...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available:                                                                                           2019               2020        Costs incurred...................................................... $1,458,000          $1,620,000        Estimated costs to complete.................................. 1,560,000                         —        Billed ……………………………………………….    1,700,000           1,900,000        Collections during the year.................................... 1,440,000            2,160,000 Miller uses the percentage-of-completion method. Instructions Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700 2,117,000 –0– Billings...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract Costs Incurred during the year $2,208,000 $2,230,000 $2,190,000 Estimated Costs to Complete the Contract at 12/31 $3,520,000 $2,190,000 -0- Billings...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,410,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,916,400 $2,079,200 $2,244,400 Estimated costs to complete the contract at 12/31 3,423,600 2,244,400 –0– Billings...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT