Question

In: Accounting

Parker Company developed the following standard cost for one of their products: Materials (9 pounds ×...

Parker Company developed the following standard cost for one of their products:

Materials (9 pounds × $4 per pound)

       $36.00

Direct labor (2 hours × $16 per hour)

         32.00

The following information is available regarding the company's operations for the period:

Units produced

12,000

Materials purchased

150,000 pounds @ $3.50 per pound

Materials used

120,000 pounds

Direct labor

20,000 hours @ $17.00 per hour

Required:

  1. Calculate the price and efficiency variances for direct material  
  2. Calculate the rate and efficiency variances for direct labor

Solutions

Expert Solution

Direct Material Price variance

= Actual quantity * (Actual price - Standard price)

Actual Quantity purchased = 150000 pounds

Actual price = 3.50 per pound

Standard price = 4 per pound

= 150000 * (3.50 - 4)

= (75000)

Since the Actual rate is less than standard rate it is favourable

Direct Material efficiency variance

= Actual units usage - Standard units usage *

( Standard rate)

Actual units usage = 120000 pounds

Standard usage for 1 unit = 9 pounds

Standard usage for 12000 units = 12000*9 = 108000 pounds

Standard rate = 4 per pound

Efficiency Variance = (120000 - 108000) *4

= 48000

Actual usage is higher than standard usage. Hence unfavourable

Direct labour Rate variance

=( Standard rate - Actual rate ) * Actual Hours worked

Standard rate = 16 per hour

Actual rate = 17 per hour

Actual Hours worked = 20000 Hours

Direct labour Rate Variance = (16-17)*20000

= (20000)

Since actual rate is higher than anticipated rate unfavourable

Direct labour efficiency Variance

= ( Actual hours - Standard hours) * Standard rate

Actual Hours = 20000

Standard Hours = 2 hours * 12000 unit = 24000

Standard cost = 16 per hour

Efficiency variance = (20000-24000)*16

=( 64000)

Actual hours worked is less than standard hours anticipated. Hence favourable


Related Solutions

Barbaro Production Company has developed the following standards for one of its products: STANDARD VARIABLE COST...
Barbaro Production Company has developed the following standards for one of its products: STANDARD VARIABLE COST CARD One Unit of Product Materials: 30 square feet × $5 per square foot $150.00 Direct labor: 16 hours × $7 per hour 112.00 Variable manufacturing overhead: 16 direct labor hours × $5 per hour 80.00 Total standard variable cost per unit $342.00 The company records materials price variances at the time of purchase. The following activity occurred during the month of April: Materials...
Simpson Manufacturing has the following standard cost sheet for one of its products: TotalDirect materials5 pounds...
Simpson Manufacturing has the following standard cost sheet for one of its products: TotalDirect materials5 pounds at $2 per pound$10 Direct labor2 hours at $25 per hour 50 Variable factory overhead2 hours at $5 per hour 10 Fixed factory overhead2 hours at $20 per hour 40 Cost per unit $110 The company uses a standard cost system and applies factory overhead cost based on direct labor hours and determines the factory overhead rate based on a practical capacity of 400...
standard cost sheet for one unit of the product. Direct materials (6 pounds at $1.60 per...
standard cost sheet for one unit of the product. Direct materials (6 pounds at $1.60 per pound) $9.60 Direct labor (6 hours at $10.00 per hour) $60.00 During the month of April, the company manufactures 310 units and incurs the following actual costs. Direct materials purchased and used (2,400 pounds) $4,080 Direct labor (1,880 hours) $18,612 What is the total, price, and quantity variances for materials and labor.
Direct Materials Variances Bellingham Company produces a product that requires 9 standard pounds per unit. The...
Direct Materials Variances Bellingham Company produces a product that requires 9 standard pounds per unit. The standard price is $8 per pound. If 3,600 units required 31,400 pounds, which were purchased at $8.32 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct materials price variance $ Favorable...
Company Inc. has the following direct materials standard to manufacture one unit: 1.5 pounds per unit...
Company Inc. has the following direct materials standard to manufacture one unit: 1.5 pounds per unit at $4.00 per pound Last week, 1,700 pounds of materials were purchased and used to make 1,000 units. The materials cost a total of $6,630. Determine the Price and Quantity Variances. Show work
Materials: Standard Qty. Standard Cost     Oats 525 pounds $1.25 per pound     Wheat 450 pounds $1.15 per...
Materials: Standard Qty. Standard Cost     Oats 525 pounds $1.25 per pound     Wheat 450 pounds $1.15 per pound     Barley   85 pounds $1.45 per pound     Malt   65 pounds $2.15 per pound     Honey 25 quarts $1.20 per quart       Water 25 gallons $0.45 per gallon   Time:     Miller 4 1/2 hours $22.75 per hour       Loader 1 1/2 hours $11.50 per hour   Overhead is applied at $5.75 per pound completed. The recipe produced 1,025 pounds of cereal mix. If required, round your answers to the nearest...
Welch Company budgeted the following cost standards for the current year: Direct materials = 1.40 pounds...
Welch Company budgeted the following cost standards for the current year: Direct materials = 1.40 pounds per unit @ $1.50 per pound Direct labor = 0.75 hours per unit @ $6 per hour Actual production and costs were as follows: Units produced = 2,800 Direct materials used = 4,500 lbs. Direct materials purchased = 5,000 lbs. @ a cost of $5,850 Direct labor incurred = 2,000 hours at a cost of $13,000The labor efficiency variance was Question 8 options: $600...
Wagner Company developed the following standard costs for its product for 2011: Direct Materials - 4...
Wagner Company developed the following standard costs for its product for 2011: Direct Materials - 4 pounds at $4.50 per pound Direct Labor - 2 hours at $10.50 per hour Based on their flexible budget, budgeted Manufacturing Overhead costs are $80,000 of fixed costs plus variable costs of $4 per direct labor hour. Normal capacity is set at 20,000 units of product OR 40,000 DIRECT LABOR HOURS. (20,000 units x 2 labor hours per unit) Actual costs for 2011 were...
Wagner Company developed the following standard costs for its product for 2011: Direct Materials - 4...
Wagner Company developed the following standard costs for its product for 2011: Direct Materials - 4 pounds at $4.50 per pound Direct Labor - 2 hours at $10.50 per hour Based on their flexible budget, budgeted Manufacturing Overhead costs are $80,000 of fixed costs plus variable costs of $4 per direct labor hour. Normal capacity is set at 20,000 units of product OR 40,000 DIRECT LABOR HOURS. (20,000 units x 2 labor hours per unit). Actual costs for 2011 were...
Abica Coffee Company produces Columbian coffee in batches of 5,900 pounds. The standard quantity of materials...
Abica Coffee Company produces Columbian coffee in batches of 5,900 pounds. The standard quantity of materials required in the process is 5,900 pounds, which cost $4.00 per pound. Columbian coffee can be sold without further processing for $8.40 per pound. Columbian coffee can also be processed further to yield Decaf Columbian, which can be sold for $11.00 per pound. The processing into Decaf Columbian requires additional processing costs of $12,450 per batch. The additional processing will also cause a 4%...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT