Question

In: Finance

1. The following I/S is based on the information associated with a new project. if The...

1. The following I/S is based on the information associated with a new project. if The required return is 15%. Answer the questions.

Year

1

2

3

4

Sales

Variable Cost

Fixed Cost

Depreciation

EBIT

Taxes (40%)

Net income

6,000,000

3,000,000

1,500,000

300,000

1,200,000

480,000

720,000

6,000,000

3,000,000

1,500,000

300,000

   1,200,000

480,000

720,000

6,000,000

3,000,000

1,500,000

300,000

1,200,000

480,000

720,000

6,000,000

3,000,000

1,500,000

300,000

1,200,000

480,000

720,000

1. The following I/S is based on the information associated with a new project. if The required return is 15%. Answer the questions.

Projected Income Statements

Year

1

2

3

4

Sales

Variable Cost

Fixed Cost

Depreciation

EBIT

Taxes (40%)

Net income

6,000,000

3,000,000

1,500,000

300,000

1,200,000

480,000

720,000

6,000,000

3,000,000

1,500,000

300,000

   1,200,000

480,000

720,000

6,000,000

3,000,000

1,500,000

300,000

1,200,000

480,000

720,000

6,000,000

3,000,000

1,500,000

300,000

1,200,000

480,000

720,000

We have to invest $1,500,000 to get started. In four years, the new equipment will be worth about tenth of what we paid for it. However, its book value is 300,000. Tax rate is 40%. In addition, we need additional NWC capital of $250,000 at the beginning of the life of this project. Fill the blanks in the following projected cash flow table.

Projected Cash Flows

Year

0

1

2

3

4

OCF

Changes in NWC

Capital spending

( )

( )

( )

( )

( )

( )

( )

( )

Total Cash Flow

( )

( )

( )

( )

( )

Figure out the net present value of this project. Based on the NPV, is the profitability index greater or less than 1?

Figure out payback period, discounted payback period, IRR, and Modified IRR.

Solutions

Expert Solution

Projected income statement:

Particulars 1 2 3 4
Sales 6,000,000 6,000,000 6,000,000 6,000,000
- VC 3,000,000 3,000,000 3,000,000 3,000,000
Contribution 3,000,000 3,000,000 3,000,000 3,000,000
-FC 1,500,000 1,500,000 1,500,000 1,500,000
-Dep 300,000 300,000 300,000 300,000
EBIT 1,200,000 1,200,000 1,200,000 1,200,000
Tax@40% 480,000 480,000 480,000 480,000
Net income 720,000 720,000 720,000 720,000

Projected cash flows:

Particulars 0 1 2 3 4
OCF(depreciation added back) 1,020,000 1,020,000 1,020,000 1,020,000
Changes in NWC (250,000) 250,000
Capital spending (1,500,000) (90,000)
Total cash flows (1,750,000) 1,020,000 1,020,000 1,020,000 1,180,000

(The equipment is worth 150,000 but its book value is 300,000. Therefore it will get a tax benefit of 60,000 for the loss incurred)

NPV of the project (use NPV function in excel) = $1,090,051

PI is cash inflows/cash outflows = 1,859,051/1,750,000 = 1.06

IRR = 47% (using excel irr function)

MIRR requires reinvest rate which is not given. You can figure out the payback period with the calculations.


Related Solutions

1. Chronic Pain Clinic has estimated the following cash flows associated with a new project. The...
1. Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital (discount rate) is 8 percent. Year 0: ($700,000) Year 1: $400,000 Year 2: $400,000 Year 3: $400,000 2. What is the project’s net present value? A. $186,897 B. $197,619 C. $208,225 D. $324,538 E. $330,839 Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital (discount rate) is 9 percent. Year...
Apollo is considering a new expansion project, Project S. Project S is a new health-food product...
Apollo is considering a new expansion project, Project S. Project S is a new health-food product that Allied is thinking of introducing to the market. Along the way, Allied’s finance staff has received a lot of information, the highlights of which are summarized below:  Project S will require Apollo to purchase $900,000 of equipment in 2013 (t = 0).  Inventory will increase by $175,000 and accounts payable will rise by $75,000. All other working capital components will stay...
(Software Project Management) A project has following risks (R), associated likelihood (L) and impact (I), and...
(Software Project Management) A project has following risks (R), associated likelihood (L) and impact (I), and the risk reduction cost (C) and resulting reduced risk likelihood (L') of some planned risk reduction measures: (R) (L) (I) (C) (L') R1 20% $75,000 $5,000 5% R2 1% $1,000,000 $20,000 0.5% R3 8% $200,000 $8,000 6% a) Calculate the risk reduction leverage for each of the above risks. b) Based on your analysis in a) above, for which risk(s) would it be worth...
The following items (partial list) are associated with a functional-based cost accounting information system, an activity-based...
The following items (partial list) are associated with a functional-based cost accounting information system, an activity-based cost accounting information system, or both: ? a. materials purchasing cost incurrence b. assignment of purchasing cost to products using direct labor hours c. assignment of purchasing cost using number of purchase orders d. usage of direct materials e. direct materials cost assigned to products using direct tracing f. materials handling cost incurrence g. materials handling cost assigned using direct labor hours h. materials...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
23.   A firm is deciding on a new project. Use the following information for the project...
23.   A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of...
6. A firm is deciding on a new project. Use the following information for the project...
6. A firm is deciding on a new project. Use the following information for the project evaluation and analysis: - The initial costs are $450,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $30,000 at the end of the project. - The project also requires an additional $100,000 for net working capital to start the project....
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis: - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project. - The project also requires an additional $200,000 for net working capital. All of the net working...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT