Question

In: Accounting

Exercise 6-2 a. Equivalent Units Material Labor & Overhead Units completed            9,500 Units, ending process: All...

Exercise 6-2
a. Equivalent Units
Material Labor & Overhead
Units completed            9,500
Units, ending process:
All material            1,500
25% labor and overhead
Equivalent units          11,000                  -   
b. Material Labor Overhead Total
Work in process, beg.
Current costs
Total costs
Equivalent units
Unit costs $              -    $              -    $              -    $              -   
c. Completed and transferred
d. Ending work in process:
Materials
Labor
Overhead
Total
e. Total costs accounted for $   
* rounding difference

FILL OUT GRAPH

E6-2 Page 349 Computing equivalent production, unit costs, and costs for completed units and ending inventory Precision Inc. manufactures wristwatches on an assembly line. The work in process inventory as of March 1 consisted of 1,000 watches that were complete as to materials and 75% complete as to labor and overhead. The March 1 work in process costs were as follows: Materials $5,000 Labor $5,000 Overhead $8,000 During the month, 10,000 units were started and 9,500 units were completed. The 1,500 units of ending inventory were complete as to materials and 25% complete as to labor and overhead. The costs for March were as follows: Materials $61,000 Labor $20,000 Overhead $48,000

Solutions

Expert Solution

Answer in your format

Calculation

Company Name
Department production Report
Weighted average Method
Month ended March 31
Summary of Physical units
Units in beginning WIP inventory 1,000
Units started during month 10,000
Total unit to be accounted for 11000
Units completed and transferred out 9,500
Units in ending WIP inventory 1,500
Total unit accounted for 11000
Equivalent Units of production
Particulars Physical units Direct material Direct labor overhead
% units % units % units
units in beginning WIP inventory 1000 100% 1000 100% 1000 100% 1000
Units in Started and completed (9500-1000) 8500 100% 8500 100% 8500 100% 8500
units in ending WIP inventory 1500 100% 1500 25% 375 25% 375
Equivalent Units of production 11000 9875 9875
Summary of cost to be accounted
Direct material Direct labor overhead Total
Cost in beginning WIP            5,000            5,000            8,000            18,000
Cost incurred during Month (Add)          61,000          20,000          48,000          129,000
total cost to be accounted for          66,000          25,000          56,000          147,000
cost per Equivalent Unit
total cost to be accounted for 66000 25000 56000
Equivalent Units of production 11000 9875 9875
Cost per Equivalent Unit $          6.00 $          2.53 $          5.67 $          14.20
Assign costs to units transferred out and units in ending WIP inventory
cost assigned to units transferred out
units completed and transferred out 9500 9500 9500
Cost per Equivalent Unit 6.00 2.53 5.67
cost assigned to units transferred out          57,000          24,035          53,865          134,900
cost assigned to units ending work in progress
equivalent units in ending WIP inventory 1500 375 375
Cost per Equivalent Unit 6.00 2.53 5.67
cost assigned to units ending work in progress            9,000                949            2,126            12,075
Total cost assigned

Related Solutions

Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Oak Ridge Steel Company are $0.80 and $0.45, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, July 1 0 4,900 Started and completed during July 61,000 61,000 Transferred out of Rolling (completed) 61,000 65,900 Inventory in process, July 31 4,000 2,400 Total units to...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $1.80 and $2.70, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct MaterialsConversion Inventory in process, October 10 2,900 Started and completed during October48,000 48,000 Transferred out of Rolling (completed)48,000 50,900 Inventory in process, October 316,000 3,600 Total units to be assigned costs54,000 54,500 The beginning...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Oak Ridge Steel Company are $2.15 and $1.60, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, July 1 0 1,800 Started and completed during July 46,000 46,000 Transferred out of Rolling (completed) 46,000 47,800 Inventory in process, July 31 4,000 2,000 Total units to...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $1.90 and $1.40, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 0 1,900 Started and completed during October 32,000 32,000 Transferred out of Rolling (completed) 32,000 33,900 Inventory in process, October 31 4,000 2,400 Total units to be...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Filling Department of Eve Cosmetics Company are $0.80 and $1.25, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, beginning of period 0 2,900 Started and completed during the period 41,000 41,000 Transferred out of Filling (completed) 41,000 43,900 Inventory in process, end of period 5,000 2,000 Total...
Equivalent Units, Unit Cost, Valuation of Goods Transferred Out and Ending Work in Process The blending...
Equivalent Units, Unit Cost, Valuation of Goods Transferred Out and Ending Work in Process The blending department had the following data for the month of March: Units in BWIP — Units completed 21,600 Units in EWIP (20% complete) 2,250 Total manufacturing costs $101,430 Required: 1. What is the output in equivalent units for March? equivalent units 2. What is the unit manufacturing cost for March? Note: Round your answer to the nearest cent. $ per unit 3. Compute the cost...
Department A had 5,000 units in work in process that were 62% completed as to labor...
Department A had 5,000 units in work in process that were 62% completed as to labor and overhead at the beginning of the period; 31,900 units of direct materials were added during the period; 34,500 units were completed during the period; and 2,400 units were 35% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of...
1. Describe equivalent units and what they are used for? 2. Describe what a predetermined overhead...
1. Describe equivalent units and what they are used for? 2. Describe what a predetermined overhead rate is, how it is calculated and what it is used for?
Department R had 4,000 units in work in process that were 69% completed as to labor...
Department R had 4,000 units in work in process that were 69% completed as to labor and overhead at the beginning of the period. During the period, 25,500 units of direct materials were added, 27,500 units were completed, and 2,000 units were 25% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of equivalent units of...
Department R had 5,000 units in work in process that were 77% completed as to labor...
Department R had 5,000 units in work in process that were 77% completed as to labor and overhead at the beginning of the period; 33,400 units of direct materials were added during the period; 35,700 units were completed during the period; and 2,700 units were 34% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT