Question

In: Physics

Consider a chiller plant that has to provide a cooling capacity of 800 TR. Water-cooled chiller...

Consider a chiller plant that has to provide a cooling capacity of 800 TR. Water-cooled chiller with a cooling tower is adopted. However due to the availability of waste heat, two different chillers are studied: R-123 centrifugal chiller and LiBr absorption chiller. Some of the design parameters are already fixed: - Evaporating temperature at 5 ºC - Condensing temperature at 42 ºC - Chilled water temperature at 7 ºC and 12 ºC respectively - Condensing water temperature at 32 ºC and 38 ºC respectively for the centrifugal chiller - Outdoor design condition at 33.5 ºC DB and 28 ºC WB Assume that the waste heat for the absorption chiller can heat up the generator to 95 ºC, and that the absorber temperature is maintained at 35 ºC respectively

For these two chillers, determine
i) The refrigeration effect and the mass flow rate of the refrigerant
ii) The energy input at the compressor / the generator
iii) The coefficient of performance (COP)
For the centrifugal chiller, determine
iv) The condenser water flowrate
v) The water cooling tower coefficient (make your own assumption of the cooling air flowrate)

For the absorption chiller, determine
vi) The concentration and mass flow rate of the weak and strong solution respectively
vii) The mass flow rate of the condensing water if the same condensing temperature is to be maintained at 32ºC and 38 ºC. Determine the inlet and outlet temperature of the water through the absorber and the condenser if the water first passes through the absorber then the condenser.
Attach with your answer the charts and/or diagrams that you have used in the calculation. State any engineering assumptions taken.

Solutions

Expert Solution

We need P-H chart for Two chiller to solve the problems. I have defined some terms which will be helpful to calculate the necessary requirements.

One TR is the amount of cooling obtained by one ton of ice melting in one day i.e. 12,000 Btu/hr, 3024 kcal/hr or 3.516 thermal kW.

Net refrigerating capacity • A quantity defined as the mass flow rate of the evaporator water multiplied by the difference in enthalpy of water entering and leaving the cooler, expressed in kW, Btu/hr, kcal/hr, or tons of refrigeration.

kW/ton rating • Commonly referred to as efficiency, but actually power input to compressor motor divided by tons of cooling produced, or kilowatts per ton (kW/ton) • Lower kW/ton indicates higher efficiency • kW/TR as a reference energy performance indicator •

Coefficient of performance (COP) • Chiller efficiency measured in cooling output divided by electric power input.

• Energy efficiency ratio (EER) • Performance of smaller chillers and rooftop units is frequently measured in EER rather than kW/ton • EER is calculated by dividing a chiller's cooling capacity by its power input at full-load conditions • The higher the EER, the more efficient the unit. P-H chart of centrifugal chiller below....

Efficiency = Useful energy output/ Energy input = Useful power output/ Power input


Related Solutions

Consider a 400-MW, 32 percent efficient coal-fired power plant that uses cooling water withdrawn from a...
Consider a 400-MW, 32 percent efficient coal-fired power plant that uses cooling water withdrawn from a nearby river (with an upstream flow of 10-m3/s and temperature 20 °C) to take care of waste heat. The heat content of the coal is 8,000 Btu/lb, the carbon content is 60% by mass, and the sulfur content is 2% by mass. How much electricity (in kWh/yr) would the plant produce each year? How many pounds per hour of coal would need to be...
1. Consider a 400-MW, 32 percent efficient coal-fired power plant that uses cooling water withdrawn from...
1. Consider a 400-MW, 32 percent efficient coal-fired power plant that uses cooling water withdrawn from a nearby river (with an upstream flow of 10-m3/s and temperature 20 °C) to take care of waste heat. The heat content of the coal is 8,000 Btu/lb, the carbon content is 60% by mass, and the sulfur content is 2% by mass. v. If the cooling water is only allowed to rise in temperature by 10 °C, what flow rate (in m3/s) from...
The mean water temperature downstream from a power plant cooling tower discharge pipe should be no...
The mean water temperature downstream from a power plant cooling tower discharge pipe should be no more than 97oF. Past experience has indicated that the standard deviation of temperature is 2oF. The water temperature is measured on 4 randomly chosen days, and the average temperature is found to be 94oF. Conduct a hypothesis testing using the 7 steps at a 5% significance level.
The mean water temperature downstream from a discharge pipe at a power plant cooling tower should...
The mean water temperature downstream from a discharge pipe at a power plant cooling tower should be no more than 100°F. Past studies has shown that the standard deviation of temperature is 2°F. The water temperature was measured on 10 randomly chosen days, and the results are shown below: 96.15 97.81 97.09 95.08 99.46 100.03 99.74 98.85 95.08 98.71 a. State the null hypothesis and alternative hypothesis for the above problem. b. Is there evidence that the water temperature is...
mean water temperature downstream from a discharge pipe at a power plant cooling tower should be...
mean water temperature downstream from a discharge pipe at a power plant cooling tower should be no more than 100°F. Past studies has shown that the standard deviation of temperature is 2°F. The water temperature was measured on 10 randomly chosen days, and the results are shown below: 96.15 , 97.81 , 97.09 , 95.0P , 99.46 , 100.03 , 99.74 , 98.85 , 95.08 , 98.71 a. State the null hypothesis and alternative hypothesis for the above problem. b....
6. A 600-MW steam power plant, which is cooled by a nearby river, has a thermal...
6. A 600-MW steam power plant, which is cooled by a nearby river, has a thermal efficiency of 35 percent. Determine the rate of heat transfer to the river water.
A 400-MW steam power plant, which is cooled by a nearby river, has a thermal efficiency...
A 400-MW steam power plant, which is cooled by a nearby river, has a thermal efficiency of 33 percent. (i) Sketch an appropriate illustration for this heat engine clearly showing the heat source and sink. (ii) Determine the rate of heat transfer to the river water. (iii) Will the actual heat transfer rate be higher or lower than this value? Why?
Zephram Corporation has a plant capacity of 200,000 units per month. Unit costs at capacity are:...
Zephram Corporation has a plant capacity of 200,000 units per month. Unit costs at capacity are: Direct materials $6.00 Direct labor 5.00 Variable overhead 4.00 Fixed overhead 2.00 Marketing—fixed 6.00 Marketing/distribution—variable 4.60 Current monthly sales are 190,000 units at $30.00 each. Q, Inc., has contacted Zephram Corporation about purchasing 2,500 units at $24.00 each. Current sales would not be affected by the one-time-only special order. What is Zephram's change in operating profits if the one-time-only special order is accepted?
Consider a plant that pollutes lead into the drinking water of a small town. The town...
Consider a plant that pollutes lead into the drinking water of a small town. The town is con- sidering a couple of interventions (i.e. taxation versus regulation) to address this problem. However, they are uncertain about the firm’s cost of reduction. Provide a solution to this problem. How does the policy instrument affect efficiency when cost are unknown. If Eliza is currently willing to trade 4 loaves of bread for 1 gallon of milk, then she must like loaves of...
Quencher Limited is planning to produce mineral water. It is contemplating to purchase a plant with a capacity of 100,000 bottles a month.
Quencher Limited is planning to produce mineral water. It is contemplating to purchase a plant with a capacity of 100,000 bottles a month. For the first year of operation the company expects to sell between 60,000 to 80,000 bottles. The budgeted costs at each of the two levels are as follows: GHS Particular 60,000 bottles 80,000 bottles Material 360,000 480,000 Labour 200,000 260,000 Factory overheads 120,000 150,000 Administration expenses 100,000 110,000 The production would be sold through retailers who will...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT