In: Accounting
n 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,044,000 | $ | 2,628,000 | $ | 2,890,800 | |||
Estimated costs to complete as of year-end | 5,256,000 | 2,628,000 | 0 | ||||||
Billings during the year | 2,170,000 | 2,502,000 | 5,328,000 | ||||||
Cash collections during the year | 1,885,000 | 2,600,000 | 5,515,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,044,000 | $ | 3,885,000 | $ | 3,285,000 | |||
Estimated costs to complete as of year-end | 5,256,000 | 3,185,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,044,000 | $ | 3,885,000 | $ | 4,155,000 | |||
Estimated costs to complete as of year-end |
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
|
In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
1. Record construction costs. / 2. Record progress billings. / 3. Record cash collections. / 4. Record gross profit (loss)
In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
2018: 1. Record construction costs. / 2. Record progress billings. / 3. Record cash collections. / 4. Record gross profit (loss).
In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
1. Record construction costs. / 2. Record progress billings. / 3. Record cash collections. / 4. Record gross profit (loss).
Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. (Do not round intermediate calculations.)
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
|
Answer-
There are two methods of computation of contract revenue, expenses, loss/profit and the value of work in progress. One is complete contract method and another is the percentage of completion method.
Complete contract method as the name suggests calculates revenue,expesnses, loss/profit and work in progress once the contract is complete. Complete contract method is used where there is no assurance of receiving of contract revenue due to any factor like terms in contracts.
The percentage of completion contract calculates on the basis of
work complete every year. and percentage of contract method is used
where there is certainty of receiving contract revenue others
scenarios.
Methodology to calculate
Percentage of Completion Contract Method-
Formulas
Project Completion % = Accumulated Cost At The End/Estimated
Total Cost*100
Recognized Revenue=Total Revenue*Project completion %
Gross Profit=Recognized Revenue-Cost incurred during the year
Apart from it all work in progress will be considered as an asset
which will be expanse out in the year of completion of contract and
billing shall be considered in liabilities.
or it can be termed as "Net Advance Billing "if billing is more
than construction in progress (Liability side) or "Net Construction
in Progress " if construction in the progress is more than billing
(Asset side) on the balance sheet.
Construction in progress is also considered as work in progress.
1
% of Completion Method | |||||
Westgate Construction Company | |||||
S.No. | Detail | 2018 | 2019 | 2020 | 2021 |
1 | Cost incurred during the year | 2,044,000 | 2,628,000 | 2,890,800 | |
2 | Accumulated Cost At The End | 2,044,000 | 4,672,000 | 7,562,800 | |
3 | Estimated costs to complete as of year-end | 5,256,000 | 2,628,000 | - | |
4 | Estimated Total Cost (2+3) | 7,300,000 | 7,300,000 | 7,562,800 | |
5 | Completion %(2/4) | 28% | 64% | 100% | |
6 | Recognized Revenue till date | ||||
10000000*Completion% | 2,800,000 | 6,400,000 | 10,000,000 | ||
7 | Recognized Revenue in year | 2,800,000 | 3,600,000 | 3,600,000 | |
8 | Billings during the year | 2,170,000 | 2,502,000 | 5,328,000 | |
9 | Cash collections during the year | 1,885,000 | 2,600,000 | 5,515,000 | |
10 | Gross Profit(7-1) | $ 756,000 | $ 972,000 | $ 709,200 |
2.a,b,c
2018 | 2019 | 2020 | |||||
S.No. | Detail | Dr.($) | Cr.($) | Dr.($) | Cr.($) | Dr.($) | Cr.($) |
1 | To Record Cost of Construction | ||||||
Construction in Process | 2,044,000 | 2,628,000 | 2,890,800 | ||||
Various accounts | 2,044,000 | 2,628,000 | 2,890,800 | ||||
2 | To Record Progress Billings | ||||||
Accounts Receivables | 2,170,000 | 2,502,000 | 5,328,000 | ||||
Billings on Construction in Process | 2,170,000 | 2,502,000 | 5,328,000 | ||||
3 | To Record Collections | ||||||
Cash | 1,885,000 | 2,600,000 | 5,515,000 | ||||
Accounts Receivables | 1,885,000 | 2,600,000 | 5,515,000 | ||||
4 | To Recognized Revenue (Gross Profit) | ||||||
Construction in Process (Gross Profit) | 756,000 | 972,000 | 709,200 | ||||
Construction Expense | 2,044,000 | 2,628,000 | 2,890,800 | ||||
Contract Revenue | 2,800,000 | 3,600,000 | 3,600,000 | ||||
5 | To Record Completion of the Contract | ||||||
Billings on Construction in Process | 10,000,000 | ||||||
Construction in Process | 10,000,000 |