Question

In: Accounting

n 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

n 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000
Estimated costs to complete as of year-end 4,900,000 2,450,000 0
Billings during the year 2,200,000 2,350,000 5,450,000
Cash collections during the year 1,900,000 2,300,000 5,800,000


Westgate recognizes revenue over time according to the percentage of completion.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018 2019 2020
The cost incurred during the year $ 2,100,000 $ 3,900,000 $ 3,300,000
Estimated costs to complete as of year-end 4,900,000 3,200,000 0


5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018 2019 2020
Cost incurred during the year $ 2,100,000 $ 3,900,000 $ 4,200,000
Estimated costs to complete as of year-end 4,900,000 4,300,000 0

Solutions

Expert Solution

(All Amounts are in $ 000's)

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years

Actual Cost to Date Actual Cost Estimated Cost Total Estimated Cost
2018 2100 4900 7000
2019 4550 (2100+2450) 2450 7000
2020 7245 (4550+2695) 0 7245

Percentage of Completion

2018 (2100/7000) * 100 = 30 %

2019 (4550/7000) * 100 = 65 %

2020 ( 7245/7245) * 100 = 100%

Revenue Recognition Less Actual cost Gross Profit
2018 3000 (10000 * 30%) 2100 900
2019 3500 (10000 * 65 %) - 3000 2450 1050
2020 3500 (10000-6500) 2695 805

Q2-a

In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).

1. To Record Cost of Construction

Construction In Progress A/c Dr. 2100

To Various Accounts 2100

(Being cost of construction is recorded for 2018)

2. To Record Progress Billings

Account Receivable A/c Dr. 2200

To Billing on Construction Contract 2200

3. To Record Collection of Cash

Cash A/c Dr. 1900

To Accounts Receivable 1900

4. To Record Gross Profits

Construction in Progress (Gross Profit) A/c Dr. 900

Cost of Construction A/c Dr. 2100

To Revenue from Long Term Contract A/c 3000

2-b

1. To Record Cost of Construction

Construction In Progress A/c Dr. 2450

To Various Accounts 2450

(Being cost of construction is recorded for 2019)

2. To Record Progress Billings

Account Receivable A/c Dr. 2350

To Billing on Construction Contract 2350

3. To Record Collection of Cash

Cash A/c Dr. 2300

To Accounts Receivable 2300

4. To Record Gross Profits

Construction in Progress (Gross Profit) A/c Dr. 1050

Cost of Construction A/c Dr. 2450

To Revenue from Long Term Contract A/c 3500

2-c

1. To Record Cost of Construction

Construction In Progress A/c Dr. 2695

To Various Accounts 2695

(Being cost of construction is recorded for 2019)

2. To Record Progress Billings

Account Receivable A/c Dr. 5450

To Billing on Construction Contract 5450

3. To Record Collection of Cash

Cash A/c Dr. 5800

To Accounts Receivable 5800

4. To Record Gross Profits

Construction in Progress (Gross Profit) A/c Dr. 805

Cost of Construction A/c Dr. 2695

To Revenue from Long Term Contract A/c 3500

3.Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.

Balance Sheet (Partial) 2018 (Amt) 2018 (Amt) 2019 (Amt) 2019 (Amt)
Current Assets
Account Receivable 300 350
Construction in Progress 2100 4550
Less :Billings (2200) (100) (4550) 0

Explanation:

Accounts Receivalbe (2018): 2200 - 1900 = 300

Accounts Receivalbe (2019):  2200 - 1900 + 2350 - 2300 = 350

4

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

Actual Cost to Date Actual Cost Estimated Cost Total Estimated Cost
2018 2100 4900 7000
2019 6000 (2100+3900) 3200 9200
2020 9300 (6000+3300) 0 9300

Percentage of Completion

2018 (2100/7000) * 100 = 30 %

2019 (6000/9200) * 100 = 65.22 %

2020 ( 9300/9300) * 100 = 100%

Revenue Recognition Less Actual cost Gross Profit
2018 3000 (10000 * 30%) 2100 900
2019 3522 (10000 * 65.22 %) - 3000 3900 (378)
2020 3478 (10000-6522) 3300 178

5 Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

Actual Cost to Date Actual Cost Estimated Cost Total Estimated Cost
2018 2100 4900 7000
2019 6000(2100+3900) 4300 10300
2020 10200 (6000+4200) 0 10200

Percentage of Completion

2018 (2100/7000) * 100 = 30 %

2019 (6000/10300) * 100 = 58.25%

2020 ( 10200/10200) * 100 = 100%

Revenue Recognition Less Actual cost Gross Profit
2018 3000 (10000 * 30%) 2100 900
2019 2825 (10000 * 58.25 %) - 3000 3900 (1075)
2020 4175 (10000-5825) 4200 (25)

Related Solutions

n 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
n 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020 Cost incurred during the year $2,624,000  $3,690,000  $2,074,600 Estimated costs to complete as of year-end 5,576,000   1,886,000 0 Billings during the year 2,200,000   4,114,000   3,686,000 Cash collections during the year 2,000,000   3,800,000   4,200,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT