In: Accounting
n 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 2,450,000 | $ | 2,695,000 | |||
Estimated costs to complete as of year-end | 4,900,000 | 2,450,000 | 0 | ||||||
Billings during the year | 2,200,000 | 2,350,000 | 5,450,000 | ||||||
Cash collections during the year | 1,900,000 | 2,300,000 | 5,800,000 | ||||||
Westgate recognizes revenue over time according to the percentage
of completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
The cost incurred during the year | $ | 2,100,000 | $ | 3,900,000 | $ | 3,300,000 | |||
Estimated costs to complete as of year-end | 4,900,000 | 3,200,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 3,900,000 | $ | 4,200,000 | |||
Estimated costs to complete as of year-end | 4,900,000 | 4,300,000 | 0 | ||||||
(All Amounts are in $ 000's)
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years
Actual Cost to Date | Actual Cost | Estimated Cost | Total Estimated Cost |
2018 | 2100 | 4900 | 7000 |
2019 | 4550 (2100+2450) | 2450 | 7000 |
2020 | 7245 (4550+2695) | 0 | 7245 |
Percentage of Completion
2018 (2100/7000) * 100 = 30 %
2019 (4550/7000) * 100 = 65 %
2020 ( 7245/7245) * 100 = 100%
Revenue Recognition | Less Actual cost | Gross Profit | |
2018 | 3000 (10000 * 30%) | 2100 | 900 |
2019 | 3500 (10000 * 65 %) - 3000 | 2450 | 1050 |
2020 | 3500 (10000-6500) | 2695 | 805 |
Q2-a
In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
1. To Record Cost of Construction
Construction In Progress A/c Dr. 2100
To Various Accounts 2100
(Being cost of construction is recorded for 2018)
2. To Record Progress Billings
Account Receivable A/c Dr. 2200
To Billing on Construction Contract 2200
3. To Record Collection of Cash
Cash A/c Dr. 1900
To Accounts Receivable 1900
4. To Record Gross Profits
Construction in Progress (Gross Profit) A/c Dr. 900
Cost of Construction A/c Dr. 2100
To Revenue from Long Term Contract A/c 3000
2-b
1. To Record Cost of Construction
Construction In Progress A/c Dr. 2450
To Various Accounts 2450
(Being cost of construction is recorded for 2019)
2. To Record Progress Billings
Account Receivable A/c Dr. 2350
To Billing on Construction Contract 2350
3. To Record Collection of Cash
Cash A/c Dr. 2300
To Accounts Receivable 2300
4. To Record Gross Profits
Construction in Progress (Gross Profit) A/c Dr. 1050
Cost of Construction A/c Dr. 2450
To Revenue from Long Term Contract A/c 3500
2-c
1. To Record Cost of Construction
Construction In Progress A/c Dr. 2695
To Various Accounts 2695
(Being cost of construction is recorded for 2019)
2. To Record Progress Billings
Account Receivable A/c Dr. 5450
To Billing on Construction Contract 5450
3. To Record Collection of Cash
Cash A/c Dr. 5800
To Accounts Receivable 5800
4. To Record Gross Profits
Construction in Progress (Gross Profit) A/c Dr. 805
Cost of Construction A/c Dr. 2695
To Revenue from Long Term Contract A/c 3500
3.Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
Balance Sheet (Partial) | 2018 (Amt) | 2018 (Amt) | 2019 (Amt) | 2019 (Amt) |
Current Assets | ||||
Account Receivable | 300 | 350 | ||
Construction in Progress | 2100 | 4550 | ||
Less :Billings | (2200) | (100) | (4550) | 0 |
Explanation:
Accounts Receivalbe (2018): 2200 - 1900 = 300
Accounts Receivalbe (2019): 2200 - 1900 + 2350 - 2300 = 350
4
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
Actual Cost to Date | Actual Cost | Estimated Cost | Total Estimated Cost |
2018 | 2100 | 4900 | 7000 |
2019 | 6000 (2100+3900) | 3200 | 9200 |
2020 | 9300 (6000+3300) | 0 | 9300 |
Percentage of Completion
2018 (2100/7000) * 100 = 30 %
2019 (6000/9200) * 100 = 65.22 %
2020 ( 9300/9300) * 100 = 100%
Revenue Recognition | Less Actual cost | Gross Profit | |
2018 | 3000 (10000 * 30%) | 2100 | 900 |
2019 | 3522 (10000 * 65.22 %) - 3000 | 3900 | (378) |
2020 | 3478 (10000-6522) | 3300 | 178 |
5 Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
Actual Cost to Date | Actual Cost | Estimated Cost | Total Estimated Cost |
2018 | 2100 | 4900 | 7000 |
2019 | 6000(2100+3900) | 4300 | 10300 |
2020 | 10200 (6000+4200) | 0 | 10200 |
Percentage of Completion
2018 (2100/7000) * 100 = 30 %
2019 (6000/10300) * 100 = 58.25%
2020 ( 10200/10200) * 100 = 100%
Revenue Recognition | Less Actual cost | Gross Profit | |
2018 | 3000 (10000 * 30%) | 2100 | 900 |
2019 | 2825 (10000 * 58.25 %) - 3000 | 3900 | (1075) |
2020 | 4175 (10000-5825) | 4200 | (25) |