Question

In: Finance

You need to consider two projects which have the following cash flows: Project A requires an...

You need to consider two projects which have the following cash flows:

Project A requires an initial investment of $10,000 and will generate net cash flows of $5,000 at the end of year 1, $6,000 at the end of year 2, $7,000 at the end of year 3, and $8,000 at the end of year 4. At the end of year 2, maintenance costs of $8,000 will have to be disbursed.

Project B requires an initial investment of $15,500 and will generate starting at the end of each year, net cash flows of $6,000 per year for 6 years (first cash flow in year 1). It will incur maintenance costs of $8,000 at the end of year 3.

Assume that the required return is 12% per annum for both projects.

i. Draw timeline showing the cash flows of projects A and B?

ii. Find the NPV of projects A and B?

iii. Which project should be chosen if Projects A and B are mutually exclusive? Explain.

iv. Which project should be chosen if the Projects A and B are completely independent? Explain.

v. Based on the cash flows of project A, explain why IRR is not an appropriate evaluation technique for this project?

Solutions

Expert Solution

i.

ii.

Project A

Year

Cash Flow(C)

PV Factor calculation

PV Factor(F) @ 12%

PV( C x F)

0

$        (10,000)

1/(1+0.12)^0

1

$           (10,000.00)

1

$            5,000

1/(1+0.12)^1

0.892857143

$                4,464.29

2

$          (2,000)

1/(1+0.12)^2

0.797193878

$              (1,594.39)

3

$            7,000

1/(1+0.12)^3

0.711780248

$                4,982.46

4

$            8,000

1/(1+0.12)^4

0.635518078

$                5,084.14

NPV

$                2,936.50

Project B

Year

Cash Flow(C)

PV Factor calculation

PV Factor(F) @ 12%

PV( C x F)

0

$       (15,500)

1/(1+0.12)^0

1

$           (15,500.00)

1

$          6,000

1/(1+0.12)^1

0.892857143

$                5,357.14

2

$           6,000

1/(1+0.12)^2

0.797193878

$                4,783.16

3

$          (2,000)

1/(1+0.12)^3

0.711780248

$              (1,423.56)

4

$            6,000

1/(1+0.12)^4

0.635518078

$                3,813.11

5

$            6,000

1/(1+0.12)^5

0.567426856

$                3,404.56

6

$            6,000

1/(1+0.12)^6

0.506631121

$                3,039.79

NPV

$                3,474.20

iii.

Based on NPV, Project B should be chosen if both projects are mutually exclusive as NPV of Project B is higher than Project A.

iv.

Based on NPV, both projects should be chosen if projects are independent as both the projects having positive NPV.

v.

Project A has two negative cash flow i.e. initial investment and year two maintenance cost which results in to two IRR values. For the reason of multiple IRR values of both the projects, IRR is not an appropriate evaluation technology for the projects.


Related Solutions

You need to consider two projects which have the following cash flows: Project A requires an...
You need to consider two projects which have the following cash flows: Project A requires an initial investment of $10,000 and will generate net cash flows of $5,000 at the end of year 1, $6,000 at the end of year 2, $7,000 at the end of year 3, and $8,000 at the end of year 4. At the end of year 2, maintenance costs of $8,000 will have to be disbursed. Project B requires an initial investment of $15,500 and...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260 C1 110 138 C2 110 138 C3 110 138 C4 110 a. If the opportunity cost of capital is 10%, which of these two projects would you accept (A, B, or both)? b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 10%. c. Which one would you choose if the cost of...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280 C1 120 148 C2 120 148 C3 120 148 C4 120 a.What are the internal rates of return on the two projects? b. If the opportunity cost of capital is 11%, what is the profitability index for each project?
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Consider the two projects with following cash flows denoted by (An, n). Project X: (-12000, 0),...
Consider the two projects with following cash flows denoted by (An, n). Project X: (-12000, 0), (6000, 1), (6000, 2), (6000, 3). Project Y: (-14000, 0), (7100, 1), (7100, 2), (7100, 3). If MARR is 20%, then which one of the following statements is correct: (using two decimal places) a) Project X is more costly one (i.e. high investment cost) b) IRR of project Y is less than 20% c) Incremental IRR of (Y-X) is 29.92% d) Project X is...
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT