Question

In: Finance

A large company has the opportunity to select one of four projects: A, B, C, D,...

A large company has the opportunity to select one of four projects: A, B, C, D, or the null (Do nothing) alternative. Each project requires a single initial investment as shown in the table below. Information on each alternative was fed into a computer program that calculated the IRR for each project as well as the pertinent incremental IRR(s) as shown in the table below.

Project

Initial Investment

Project IRR

Incremental Rate of Return of “Row” – “Column”

Null

A

B

C

D

A

$12,000

14%

7.5%

8%

B

$15,000

12%

6%

10%

9%

C

$10,000

9%

2%

7%

D

$9,000

7%

For each value of MARR below indicate which project is preferred and the evaluations you made to arrive at this conclusion.

a. MARR = 15%

b. MARR = 6%

c. MARR = 8.5%

Please don't use excel functions, just show condensed formulas, ex: (P/F,i(%),n) , etc. Thank you!

Solutions

Expert Solution

Internal Rate of Return (IRR) is used in capital budgeting to estimate the profitability of potential investments.

Internal rate of return is a discount rate that makes the net present value (NPV) of all cash flows from a particular project equal to zero.

IRR calculations rely on the same formula as NPV does.
If a project's internal rate of return is higher, it is more desirable to undertake.

IRR can be used to rank multiple prospective projects a firm is considering on a relatively even basis.

Assuming the costs of investment are equal among the various projects, the project with the highest IRR would probably be considered the best and undertaken first.

The minimum acceptable rate of return, often abbreviated MARR, or hurdle rate is the minimum rate of return on a project a manager or company is willing to accept before starting a project, given its risk and the opportunity cost of forgoing other projects.

The hurdle rate is frequently used as synonym of cut off rate, benchmark and cost of capital.

It is used to conduct preliminary analysis of proposed projects and generally increases with increased risk.

(a) When MARR = 15%

Project B is preferred to project A.

The Initial investment for Project B is more and it generates more return.

Higher the risk, higher the return.

The incremental rate of return of Project B is higher as compared to A.

(b). MARR = 6%

(c). MARR = 8.5%

For both (b) and (c), we make an assumption that the initial investment is maximum $10,000.

In that case we have to analyse project C and D.

Project C is preferred to project D.

  • It has a higher IRR as compared to Project D
  • It has a higher return as compared to Project D.
  • Project C has a higher Incremental rate of return as compared to Project D.

Related Solutions

A department head has four managers, and three projects (A, B, C) to be executed. The...
A department head has four managers, and three projects (A, B, C) to be executed. The managers differ in efficiency, and the projects differ in their intrinsic complexity. The estimate of the times each manager would take to complete each project is given in the matrix below. Formulate a linear programming (LP) model for determining how the projects should be assigned, to a manager, so as to minimize the total project completion time. No manager should be assigned more than...
A project has four activities (A, B, C, and D) that must be performed sequentially. The...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.32 6 0.39 7 0.27 8 0.02 B 4 0.18 6 0.51 8 0.31 C 7 0.10 9 0.29 11 0.43 13 0.15 15 0.03 D 10 0.61 12 0.39 Provide the base-case, worst-case, and best-case calculations for the time to complete...
A rotating shaft has four masses A, B, C, and D attached to it. The planes...
A rotating shaft has four masses A, B, C, and D attached to it. The planes that these masses rotating at are spaced equally. The magnitude of the masses are 6.5, 11.8, 4.2, and 5.1 kg, respectively. Calculate the radii that the masses should be placed at from the center of the shaft such that the system be in a complete dynamic balance. The shaft angular speed varies between 1760 and 1875 r.p.m. Assume whatever dimension or quantity that you...
A company has three production departments A, B, and C and one service department D. Planned...
A company has three production departments A, B, and C and one service department D. Planned overhead costs for the quarter are as follows: Overheads £ Absorption basis Quality Control 3000 Direct Labour Hours Depreciation 3750 Machine value Insurance 1250 Machine value Rates and Rent 7500 Floor area Utility bills           625 Floor area The following information is available for each department: Absorption basis A B C D Machine Value (£) 5000 2500 3500 1500 Budgeted Direct Labour hours 1000 500...
Four People (A, B, C, D) are having a conversation. When one person finishes speaking, it...
Four People (A, B, C, D) are having a conversation. When one person finishes speaking, it is equally likely that any of the other three begins. Under this assumption, the transitions from one speaker to the next follow the rules of a Markov chain. Let T be the number of transitions it takes for conversation to return A. Find the mean of T.
Four People (A, B, C, D) are having a conversation. When one person finishes speaking, it...
Four People (A, B, C, D) are having a conversation. When one person finishes speaking, it is equally likely that any of the other three begins. Under this assumption, the transitions from one speaker to the next follow the rules of a Markov chain. Let T be the number of transitions it takes for conversation to return A. Find the mean of T.
The following graph contains four lines (A, B, C and D), each of which has a...
The following graph contains four lines (A, B, C and D), each of which has a slope that is either positive, negative, zero, or infinite.For each of the following scenarios, indicate whether the relationship between the two variables is positive or negative, as well as which line on the previous graph has a slope that reflects this type of relationship. Hint: The X-axis and Y-axis on the graph are not labeled intentionally. You need to substitute the variables from each scenario...
The following graph contains four lines (A, B, C and D), each of which has a...
The following graph contains four lines (A, B, C and D), each of which has a slope that is either positive, negative, zero, or infinite.For each of the following scenarios, indicate whether the relationship between the two variables is positive or negative, as well as which line on the previous graph has a slope that reflects this type of relationship. Hint: The X-axis and Y-axis on the graph are not labeled intentionally. You need to substitute the variables from each scenario...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3 levels and is a between-subjects variable; Factor B has 2 levels and is a within-subjects variable; Factor C has 2 levels and is a between-subjects variable; Factor D has 3 levels and is a within-subjects variable. 1. How many “cells” or “conditions” or “groups” are there in this experiment? 2. If you want to test 10 participants per cell, how many TOTAL participants will...
A process has four stages (A, B, C, and D). The stages have output rates of...
A process has four stages (A, B, C, and D). The stages have output rates of 5 units/hr, 12 units/hr, 10 units/hr, and 7 units/hr, respectively. What is the output rate of this process? a. 12 units/hr b. 10 units/hr c. 7 units/hr d. 5 units/hr
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT