In: Economics
PROJECT SUMMARY
A multiprime contract for the construction of a new high school for the New State Building Commission
KEY PLAYERS
Concrete Services Corp. (CSP)
Concrete Contractors
CSP did not have much experience working on public projects, but it did have vast experience as a concrete subcontractor.
Steel Contractor Inc. (SCI)
Steel contractor responsible for supplying the steel columns and erecting the steel frame of the building
Corporal Construction and Management Services, Inc. (CCMS)
Management service responsible for creating and managing the schedule for the project, including:
CCMS is the project’s construction manager under the standard CM Agreement and General Conditions issued by the New State Building Commission. They are a relatively new company and did not have much experience in a construction management role.
Paul Manager
Assigned by CCMS as the lead project manager on the construction project
CCMS needed to quickly fill the lead construction management role on the project or face termination, so they hired Paul Manager. Paul was recommended to CCMS by the owner of SCI.
THE CHALLENGE
Throughout the project, CSP complained to Paul that SCI was hindering its work progress because SCI was experiencing delays in erecting the steel and often did not get the steel columns delivered in time. On a regular basis, the CSP crew would show up for work and would be forced to wait around because SCI had not completed its erection of the steel due to delays in the delivery of SCI’s materials.
When CSP brought the situation to Paul Manager’s attention, Paul told CSP not to worry about it and that he was confident that SCI would come through and complete its scope of work in a timely manner. Paul Manager never conducted a job site meeting to address the situation and he never documented any of CSP’s concerns. On one occasion, CSP’s concrete pump was crushed by one of SCI’s cranes because Paul had arranged to have both crews on the job at the same time working in the same area.
The construction project’s completion date was delayed several months, in part due to an unusually rainy season, but also due in part to schedule delays experienced by several of the contractors on the project.
CSP filed a lawsuit in federal district court alleging that CCMS’s mismanagement of its oversight responsibilities caused CSP to experience a number of delays and to work inefficiently, resulting in extra costs. As evidence of CCMS’s mismanagement of the entire project, CSP alleged that:
Question
1. What management technique would you recommend to Paul to mitigate the risk of future disputes?
2. What documentation could either side provide to support their claim?
Introduction
1)Paul being the lead project manager for construction project , thus had the duty and obligation to ensure that the project is completed within the stipulated period with the coordination and cooperation of CSP and SCI which was must to carry out the work smoothly but as such it is witnesses that due to the delays of supplying steel by SCI , CSP has been encountering a lots of problems. Due to irregular deliveries by SCI , the progress of project was hindered which eventually lead to risks of raised costs, exceeding deadlines , etc
In order to mitigate the risk Paul , the lead manager should initiate Some of the most suitable strategies to mitigate the risks associated with the project which can be:
Avoiding the risk :
It might be the least option considered in case there is no other
profitable option left. If Paul feels that the continuation of this
projects will result in nothing but losses , then it will be better
for him to call off the project to prevent the future complexities,
financial problems or liquidity crunch etc.
Paul needs to mitigate the risk is to formulate such procedures and
policies that will enable the project completion within the time
limits and budget through applying techniques to forecast
uncertainities , predicting delays in advance through monitoring
and evalauting the work of steel errection periodically in order to
ensure these delays are proactively avoided by ivertime arrangement
or similar methods ,
To reduce collisions between SCI and CSP , and thus ensuring each
work interdependently through synchronizing their efforts and
promoting coordination.
These techniques will help to minimize or eradicate the risky
situation creating complexities
Accepting risk and handling it:
The another method to mitigate the risk is to accept that the risks
exist and identifying the root cause that result in a particular
outcome.
It involves designing out the the reasoning behind unwanted risk
that jas the maximum possibility to arise and thus initiating steps
to curb these risks efficiently
It will incorporate closely monitoring the field performance and
initiating early problem detection and warnings systems that will
enable to get the efforts and operations on line if are deviated or
derailed
controlling or reducing risks
It involves using the risk reduction techniques to keep ceratin
things at place that will enable to reduce risks. Although it will
involve certain amount of cost , but it will lead to prioritizing
the risks to combat them in advance so that the construction
project runs smoothly with mutual efforts and coordination.
It also involves reducing the occurrence of risks by avoiding such
situations that have been encountered in pasy or are more common in
the project so far
2) CSP can provide the claim that due to lack of due diligence,
efforts and hardwork SCP never makes deliveries on time which
eventually hampers the operations and affects the smooth flow of
activities .
The delays in supplying steel leads to not being able to work as
per the set schedule ,and meeting the standards set, may it be the
budget or the time frame .
Because due to SCP delays occur that increase the life cycle of
project due to which labour need to attend more to work than the
prescribed time resulting in cost hike creating complexities for
project completion and affecting efficiency.
To further support their claim they can also include the situation
of work collision between SCP And CPI which lead to Crushing of
concrete pump build by them
Morover CCMS has also been reported to abandon the critical path
schedule, forcing contractors to do work out of sequence
Access to the job site often prevented its crew from working at
all
Further due to these prevailing situation the process for
submitting and approving extra work orders took too long, and they
thus remained unresolved mostly.
On the other hand SCP can argue through claiming that It has always
tried to complete the scope of project in timely manner by being
enough digent towards the work but the construction project’s
completion date was delayed several months beacuse of an unusually
rainy season due to which it took time for them to come back to
routine as it made processes grow complex and undermined the speed
of work for employees resulting in inefficient outcome otherwise
their efforts and work schedule was taken into due
consideration
Further they can claim that because of having relatively less
experience in construction projects and such roles , created
certain discrepancies , thus nothing was done
deliberately
Hope i explained well in the time frame given
God bless and good luck :) sorry for typing mistakes
You can comment for any doubts