Question

In: Economics

Example: Consider two projects. The first project pays benefits of $90 today and nothing else. The...

Example:

Consider two projects. The first project pays benefits of $90 today and nothing else. The second project pays nothing today, nothing one year from now, but $100 two years from now. Which project would be preferred if the discount rate were 2%? What if the rate increased to 10%?

- For a discount rate of 2%, the present value calculations would be $90 for project one and $96.12 for project two; therefore, project two is preferred. At a rate of 10%, the PV of project one is still $90. For project two, the PV is now 100/1.1^2= 82.6; therefore, project one is preferred.

---------------------------------------------------------------------------------------------------------------------------------------------------------

How can I solve this questions below???????????????????????????????????

Consider two projects. The first project pays benefits of $90 today and nothing else. The second project pays nothing today, nothing one year from now, but $100 two years from now. Which project would be preferred if the discount rate were 2%? What if the rate increased to 8%?

Solutions

Expert Solution

CASE 1

Discount rate = 2% or 0.02

The first project pays benefit of $90 today.

The present value of benefit received today is amount itself.

Thus,

The present value of benefits from first project is $90.

The second project pays $100 two years from now.

Calculate the present value -

PV = $100/(1+0.02)2 = $100/(1.02)2 = $100/1.0404 = $96.12

The present value of bebefits from Project 2 is $96.12

The present value of benefits from Project 2 is higher.

So, at discount rate of 2%, Project 2 would be preferred.

CASE 2

Discount rate = 8% or 0.08

The first project pays benefit of $90 today.

The present value of benefit received today is amount itself.

Thus,

The present value of benefits from first project is $90.

The second project pays $100 two years from now.

Calculate the present value -

PV = $100/(1+0.08)2 = $100/(1.08)2 = $100/1.1664 = $85.73

The present value of bebefits from Project 2 is $85.73

The present value of benefits from Project 1 is higher.

So, at discount rate of 8%, Project 1 would be preferred.


Related Solutions

There are two projects that the company is considering: Project A costs 10,000 to implement today,...
There are two projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,900 at the end of year 1; 2,000 at the end of year 2; 5,000 at the end of year 3. Project B's initial cost is 7,500, and subsequent cash flows are 5,000 per year for 3 years. WACC is 8% for both projects. Calculate NPV and IRR for each project, and decide which to recommend.
There are two projects that the company is considering: Project A costs 10,000 to implement today,...
There are two projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1; 4,000 at the end of year 2; 6,000 at the end of year 3. Project B's initial cost is 12,000, and subsequent cash flows are 6,000 per year for 3 years. WACC is 8% for both projects. a. Calculate NPV and IRR for each project, and decide which one to...
Consider a project that requires an initial investment of $502, pays $106 one year from today...
Consider a project that requires an initial investment of $502, pays $106 one year from today (at t = 1), pays $202 two years from today (at t = 2), and pays $353 three years from today (at t = 3). Rounded an accurate to three decimal places, what is the payback period for this project? (Example: if we had a much longer-term project of nine years, and you found the payback period was 7.2345 years...your answer would be entered...
First, think of an example of “nothing” that is quite present in your life. It can...
First, think of an example of “nothing” that is quite present in your life. It can be an object, a place, or an activity. Now, look for a “something” version of it. How easy or difficult was it to find it? Comparing the two versions, which one are you more satisfied with, and why? What does that say about the place of McDonaldization in your life?
Consider the following two projects. The cost of capital for both projects is 15%. Project Year...
Consider the following two projects. The cost of capital for both projects is 15%. Project Year 0 1 2 3 4 5 Alpha -55,000 15,000 14,000 22,000 30,000 35,000 Gamma -80,000 40,000 30,000 25,000 25,000 20,000 Calculate the IRR for each project and determine which one is better. Calculate the NPV for each project and determine which one is better. Based on profitability index method, which project is better? Overall, which project should be accepted assuming they are mutually exclusive?...
Projects A and B are mutually exclusive projects. Project A requires an initial investment today of...
Projects A and B are mutually exclusive projects. Project A requires an initial investment today of $300 and generates expected cash flows of $100 at the end of each of the next 5 years. Project B requires an initial investment today of $130 and generates expected cash flows of $55 at the end of each of the next 5 years. a. If you plotted the NPV profiles, what would be the "crossover rate" in the graph? (Note you are not...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260 C1 110 138 C2 110 138 C3 110 138 C4 110 a. If the opportunity cost of capital is 10%, which of these two projects would you accept (A, B, or both)? b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 10%. c. Which one would you choose if the cost of...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT?    a. The crossover rate must be greater than 10%. b. If the cost of capital...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280 C1 120 148 C2 120 148 C3 120 148 C4 120 a.What are the internal rates of return on the two projects? b. If the opportunity cost of capital is 11%, what is the profitability index for each project?
"Consider two mutually exclusive projects that will be conducted for a total of 6 years. Project...
"Consider two mutually exclusive projects that will be conducted for a total of 6 years. Project A lasts 3 years (so it will need to be repeated 1 time) and has the following cash flow: Year 0 -$15,000; Year 1 $16,000; Year 2 $17,000; Year 3 $15,000. Project B lasts 2 years (so it will need to be repeated 2 times) and has the following cash flow: Year 0 -$23,000; Year 1 $19,000; Year 2 $17,000. Assume both projects can...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT