Question

In: Accounting

Q 22 The following data relates to actual output, actual costs and variances for the four-weekly...

Q 22

The following data relates to actual output, actual costs and variances for the four-weekly accounting period number 4 of a company from Bole which makes only one product.

The value of work in progress at the end of period 4 was the same as the value of work -in - progress at the beginning of the month

Actual production of product XY 18,000 units

Actual costs incurred GHS'000

Direct materials purchased and used (150,000 kg) 210

Direct labour cost (32,000 hours) 136

Variable production overhead 38

Variances GHS'000

Direct materials price 15 Favourable

Direct materials usage 9 Adverse

Direct labour rate 8 adverse

Direct labour efficiency 16 Favourable

Variable production overhead expenditure 6 Adverse

Variable production overhead efficiency 4 Favourable

Variable production overhead varies with labour hours worked

A standard marginal costing system is operated.

Required

Present a standard product cost sheet for one unit of product XY, showing how the standard marginal production cost the product is made up.

Solutions

Expert Solution

Standard Cost Sheet
Direct Material (8 x 1.5)         12.00
Direct Labor (2 x 4)           8.00
Overhead ( 2 x 1)           2.00
Total Cost         22.00

Working Note

Direct materials price variance = (AP - SP) Actual quantity

-15,000 = 210,000 - 150,000SP

150,000SP = 225,000

SP = 225,000/150,000

=1.5

Direct Materials quantity Variance = (AQ - SQ)SP

9,000 = (150,000 - SQ)1.5

9,000 = 225,000 - 1.5 SQ

SQ = 216,000/1.5

SQ = 144,000

Standard quantity per unit = 144,000/18,000 = 8 Kg

Direct labour rate variance = (AR - SR)Actual Hours

8,000 = 136,000 - 32,000SR

SR = 128,000/32,000

SR = 4

Direct labour efficiency variance = (Actual Hours - Standard Hours)SR

-16,000 =(32,000 - SH)4

-16,000 = 128,000 - 4SH

SH = 144,000/4

=36,000 Hours

Standard Hours per unit = 36,000/18,000 = 2

Variable production overhead expenditure variance = Actual expenditure - Budgeted Expenditure

Budgeted Expenditure = 38,000 - 6,000 = 32,000

Variable production overhead efficiency variance = 4,000

Standard Expenditure = 32,000 + 4,000 = 36,000

Standard VOH per unit = 36,000/18,000 = 2


Related Solutions

QUESTION 4 The underlisted data relate to actual output, costs and variances for the monthly accounting...
QUESTION 4 The underlisted data relate to actual output, costs and variances for the monthly accounting period of a company that makes only one product. Opening and closing work in progress were the same. Variances: GH₵ Direct materials price 30000 F Direct materials usage 18000 A Direct labour rate 16000 A Direct labour efficiency 32000 F Variable production overhead expenditure 12000 A Variable production overhead efficiency 8000 F Variable production overhead varies with labour hours worked. A standard marginal costing...
The following information relates to Burgundy for July 2020: Actual direct labour costs $50,000 Actual direct...
The following information relates to Burgundy for July 2020: Actual direct labour costs $50,000 Actual direct labour rate per hour $10 Factory overhead rate per direct labour hour $15 Factory overhead incurred $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required a) Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the...
The following information relates to Burgundy for July 2020: Actual direct labour costs                            
The following information relates to Burgundy for July 2020: Actual direct labour costs                                              $50,000 Actual direct labour rate per hour                                  $10 Factory overhead rate per direct labour hour                 $15 Factory overhead incurred                                            $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the...
The following information relates to Burgundy for July 2020: Actual direct labour costs                            
The following information relates to Burgundy for July 2020: Actual direct labour costs                                              $50,000 Actual direct labour rate per hour                                  $10 Factory overhead rate per direct labour hour                 $15 Factory overhead incurred                                            $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the end of the period, which...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A × $2.00 per unit 1 unit of material B × $3.00 per unit Direct labor 3 hours × $8.00 per hour Activity for September Materials purchased Material A 2,600 units × $2.05 per unit Material B 700 units × $3.10 per unit Materials used Material A 2,250 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 3 units of material A x $8.00 per unit 2 units of material B x $4.00 per unit Direct labor 2 hours x $15.00 per hour Activity for September Materials purchased Material A 7,000 units x $7.80 per unit Material B 4,800 units x $4.50 per unit Materials used Material A 6,430 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit Direct labor 3 hours x $ 18.00 per hour Activity for September Materials purchased Material A 6,750 units x $ 6.20 per unit Material B 1,650 units x $ 8.50 per unit Materials...
You have collected the following data on output and total variable costs: Q TVC 1 533...
You have collected the following data on output and total variable costs: Q TVC 1 533 2 1024 3 1491 4 1952 5 2425 6 2928 7 3479 8 4096 9 4797 10 5600 Over what range of output does this firm exhibit increasing returns (increasing MPMP), and diminishing returns (decreasing MPMP)? Select one: a. Increasing returns for output levels at 2 and higher, and decreasing returns for output levels at 3 and lower. b. Increasing returns for output levels...
Material and Labor Variances The following actual and standard cost data for direct material and direct...
Material and Labor Variances The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 4,200 lbs. @ $4.90 4,000 lbs. @ $5.20 Direct labor 5,700 hrs. @ $9.30 6,000 hrs. @ $9.50 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable. Materials...
Overhead Variances and Their Disposal Warner Company has the following data for the past year: Actual...
Overhead Variances and Their Disposal Warner Company has the following data for the past year: Actual overhead $240,500 Applied overhead:       Work-in-process inventory $56,000       Finished goods inventory 112,000       Cost of goods sold 112,000       Total $280,000 Warner uses the overhead control account to accumulate both actual and applied overhead. Required: 1. Calculate the overhead variance for the year. $ Provide the appropriate adjusting journal entry to close the overhead variance to Cost of Goods Sold. Assume the variance calculated is material. After...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT