Question

In: Accounting

The following information relates to Burgundy for July 2020: Actual direct labour costs $50,000 Actual direct...

The following information relates to Burgundy for July 2020: Actual direct labour costs $50,000 Actual direct labour rate per hour $10 Factory overhead rate per direct labour hour $15 Factory overhead incurred $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required a) Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the end of the period, which would be the adjustment to the cost of goods sold account? Aquamarine plans to manufacture two lines of chairs in the coming year – lounge and patio. The company is considering introducing an activity-based costing system. Given below are each activity, its cost and its related activity driver. Activity Cost Activity Driver Material setups $200,000 Number of setups Material handling $150,000 Number of parts Cutting $600,000 Number of parts Assembly $300,000 Direct labour hours Finishing $600,000 Number of units The level of activity for the year is: Lounge Patio Units to be produced 10,000 5,000 Number of setups 60 60 Number of parts per unit 10 5 Direct labour hours per unit 4 2 Required a) Under an activity-based costing system, what is the activity cost per unit of activity driver for assembly? b) Under an activity-based costing system, what is the total cost of lounge chairs for the year?

Solutions

Expert Solution

Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Burgundy
Workings for answer a Amount $ Note
Direct labor cost 50,000.00 A
Direct labor wage rate           10.00 B
Direct labor hours     5,000.00 C=A*B
Answer a Amount $ Note
Direct labor hours      5,000.00 D
Predetermined overhead rate           15.00 E
Overhead applied 75,000.00 F=D*E
Actual Overhead 80,000.00 See F
Under applied overhead     5,000.00 N=F-L
Answer b
Adjustment Entry
Account Debit $ Credit $
Cost of goods sold      5,000.00
Factory overhead            5,000.00
Aquamarine
Activity cost pool Cost Driver Cost Lounge Patio Total ABC rates
Material setups Number of setups       200,000.00             60.00                 60.00          120.00 1,666.67
Material handling Number of parts       150,000.00 100,000.00         25,000.00 125,000.00           1.20
Cutting Number of parts       600,000.00 100,000.00         25,000.00 125,000.00           4.80
Assembly Direct labor hours       300,000.00     40,000.00         10,000.00     50,000.00           6.00
Finishing Number of units       600,000.00     10,000.00            5,000.00     15,000.00         40.00
Total Cost assigned 1,850,000.00
Answer a
Activity cost per unit of activity driver for assembly is $ 6 per direct labor hour.
Answer b Lounge
Activity cost pool Cost Driver ABC Rates Activity used Cost assigned
Material setups Number of setups            1,666.67             60.00       100,000.00
Material handling Number of parts                   1.20 100,000.00       120,000.00
Cutting Number of parts                   4.80 100,000.00       480,000.00
Assembly Direct labor hours                   6.00     40,000.00       240,000.00
Finishing Number of units                 40.00     10,000.00       400,000.00
Total Cost assigned 1,340,000.00

Related Solutions

The following information relates to Burgundy for July 2020: Actual direct labour costs                            
The following information relates to Burgundy for July 2020: Actual direct labour costs                                              $50,000 Actual direct labour rate per hour                                  $10 Factory overhead rate per direct labour hour                 $15 Factory overhead incurred                                            $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the...
The following information relates to Burgundy for July 2020: Actual direct labour costs                            
The following information relates to Burgundy for July 2020: Actual direct labour costs                                              $50,000 Actual direct labour rate per hour                                  $10 Factory overhead rate per direct labour hour                 $15 Factory overhead incurred                                            $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the end of the period, which...
Below is the cost information for June and July, 2020. Physical Units Direct Materials Conversions Costs...
Below is the cost information for June and July, 2020. Physical Units Direct Materials Conversions Costs Total Beg. Work in Progress (July 1, 2020) 250 $78,750 $77,813 $156,813 Transferred to Finished Goods 725 Ending Work in Progress  (July 31, 2020) 200 Costs added July 2020 $271,875 $295,800 $567,675 The production manager informs you that the Beginning Work in Progress  (July 1) was 90% complete as to direct materials and 75% complete as to conversion costs. He also estimates that the Ending Work...
During the month of July, direct labour cost totalled $24,000 and direct labour cost was 30%...
During the month of July, direct labour cost totalled $24,000 and direct labour cost was 30% of prime cost. If total manufacturing costs during June were $105,000, the manufacturing overhead was:
Data on Gantry Company's direct labor costs are given below: Standard direct-labor hours 50,000 Actual direct-labor...
Data on Gantry Company's direct labor costs are given below: Standard direct-labor hours 50,000 Actual direct-labor hours 49,000 Direct-labor efficiency variance-favorable $ 5,200 Direct-labor rate variance-favorable $ 9,800 Total direct labor payroll $ 245,000 What was Gantry's actual direct labor rate?
Actual Direct labor costs and Actual Direct material costs are written [entered, or put] on A...
Actual Direct labor costs and Actual Direct material costs are written [entered, or put] on A job-order sheet. Estimated, not actual, manufacturing overhead costs are entered on a Job-order Sheet. A. Explain why estimated costs are used. B. Explain how the amount of manufacturing Overhead costs entered on a particular job-order cost sheet is determined.
The following information relates to Osceola Corporation for the past accounting period.     Direct costs Service...
The following information relates to Osceola Corporation for the past accounting period.     Direct costs Service Dept A $80,000 Service Dept B 60,000 Producing Dept C 15,000 Producing Dept D 20,000 Proportion of service by A to: Proportion of service by B to: B 10% A 30% C 60% C 20% D 30% D 50% Using the reciprocal method, Department B's cost allocated to Department C is: $29,021 $14,021 $13,192 $7,794
Q 22 The following data relates to actual output, actual costs and variances for the four-weekly...
Q 22 The following data relates to actual output, actual costs and variances for the four-weekly accounting period number 4 of a company from Bole which makes only one product. The value of work in progress at the end of period 4 was the same as the value of work -in - progress at the beginning of the month Actual production of product XY 18,000 units Actual costs incurred GHS'000 Direct materials purchased and used (150,000 kg) 210 Direct labour...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.64 Actual Costs Direct materials 2,700 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is a.$458 favorable b.$458 unfavorable c.$1,188 unfavorable d.$1,188 favorable
Indicate whether each of the following costs would be classified as direct materials, direct labour, manufacturing...
Indicate whether each of the following costs would be classified as direct materials, direct labour, manufacturing overhead or period cost. (1 Mark each) Cost of grapes purchased by a winery Depreciation on pizza ovens of a pizza restaurant Salary of a plant manager in a computer production facility Depreciation of computers used in a sales department Wages of drill-press operators in a manufacturing plant Part B Prime Pizza is famous for making Margherita pizzas and delivers pizzas to the suburb...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT