Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team that is developing the process for implementing a new database management system at corporate headquarters. The corporate planning group in Waltham, Massachusetts has contacted him and has asked how confident the design group is about completing the project in 60 days. He has developed these estimated time durations in days for the project:
Activity |
Immediate Predecessor Activities |
Optimistic Time (to) |
Most Likely Time (tm) |
Pessimistic Time (tp) |
A |
-- |
10 |
12 |
15 |
B |
A |
6 |
10 |
14 |
C |
A |
12 |
14 |
22 |
D |
A |
7 |
10 |
16 |
E |
B |
5 |
6 |
8 |
F |
C,E |
10 |
12 |
13 |
G |
B |
12 |
14 |
16 |
H |
D |
18 |
21 |
24 |
I |
D |
10 |
15 |
20 |
J |
F.G.H |
8 |
10 |
14 |