In: Statistics and Probability
Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team that is developing the process for implementing a new database management system at corporate headquarters. The corporate planning group in Waltham, Massachusetts has contacted him and has asked how confident the design group is about completing the project in 60 days. He has developed these estimated time durations in days for the project:
Activity |
Immediate Predecessor Activities |
Optimistic Time (to) |
Most Likely Time (tm) |
Pessimistic Time (tp) |
A |
-- |
10 |
12 |
15 |
B |
A |
6 |
10 |
14 |
C |
A |
8 |
16 |
18 |
D |
A |
6 |
12 |
20 |
E |
B |
5 |
6 |
8 |
F |
C,E |
10 |
12 |
13 |
G |
B |
12 |
14 |
16 |
H |
D |
18 |
21 |
24 |
I |
D |
10 |
15 |
20 |
J |
F.G.H |
8 |
10 |
14 |
Solution:-
Given that
Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team that is developing the process for implementing a new database management system at corporate headquarters.
The design group is about completing the project in 60 days.
1) Compute the expected time and variance for each activity.
Mean | Std dev | Variance | Activity |
12.16667 | 0.833333 | 0.694444 | A |
10 | 1.333333 | 1.777778 | B |
15 | 1.666667 | 2.777778 |
C |
12.33333 | 2.333333 | 5.444444 | D |
6.166667 | 0.5 | 0.25 | E |
11.83333 | 0.5 | 0.25 | F |
14 | 0.666667 | 0.444444 | G |
21 | 1 | 1 | H |
15 | 1.666667 | 2.777778 | I |
10.33333 | 1 | 1 | J |
2) Determine the critical path and the expected duration of the project.
The critical path is:
A-D-H-J
Expected duration = 55.83
3) What is the probability that the project will take
longer than 58 days to complete?
= 0.76
The probability is 0.2238.
4) Which path in the project network offers the greatest risk of overrunning a new deadline of 56 days?
A-D-H-I-J
The calculations are:
Data
Results:-
Activity | Early Start | Early Finish | Late Start | Late Finish | Slack |
A | 0 | 12.16667 | 0 | 12.16667 | 0 |
B | 12.16667 | 22.16667 | 17.5 | 27.5 | 5.333333 |
C | 12.16667 | 27.16667 | 18.66667 | 33.66667 | 6.5 |
D | 12.16667 | 24.5 | 12.16667 | 24.5 | 0 |
E | 22.16667 | 28.333333 | 27.5 | 33.66667 | 5.333333 |
F | 28.33333 | 40.16667 | 33.66667 | 45.5 | 5.333333 |
G | 22.16667 | 36.16667 | 31.5 | 45.5 | 9.333333 |
H | 24.5 | 45.5 | 24.5 | 45.5 | 0 |
I | 24.5 | 39.5 | 40.83333 | 55.83333 | 16.33333 |
J | 45.5 | 55.83333 | 45.5 | 55.83333 | 0 |
Project | 55.83333 |
Thanks for supporting...
Please give me a thumbs up if this helps you out. Thanks you!