Question

In: Statistics and Probability

Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team...

Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team that is developing the process for implementing a new database management system at corporate headquarters. The corporate planning group in Waltham, Massachusetts has contacted him and has asked how confident the design group is about completing the project in 60 days. He has developed these estimated time durations in days for the project:

Activity

Immediate Predecessor

Activities

Optimistic

Time (to)

Most Likely Time (tm)

Pessimistic

Time (tp)

A

--

10

12

15

B

A

6

10

14

C

A

8

16

18

D

A

6

12

20

E

B

5

6

8

F

C,E

10

12

13

G

B

12

14

16

H

D

18

21

24

I

D

10

15

20

J

F.G.H

8

10

14

  1. Compute the expected time and variance for each activity.
  2. Determine the critical path and the expected duration of the project.
  3. What is the probability that the project will take longer than 58 days to complete?
  4. Which path in the project network offers the greatest risk of overrunning a new deadline of 56 days?

Solutions

Expert Solution

Solution:-

Given that

Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team that is developing the process for implementing a new database management system at corporate headquarters.

The design group is about completing the project in 60 days.

1) Compute the expected time and variance for each activity.

Mean Std dev Variance Activity
12.16667 0.833333 0.694444 A
10 1.333333 1.777778 B
15 1.666667 2.777778

C

12.33333 2.333333 5.444444 D
6.166667 0.5 0.25 E
11.83333 0.5 0.25 F
14 0.666667 0.444444 G
21 1 1 H
15 1.666667 2.777778 I
10.33333 1 1 J

2) Determine the critical path and the expected duration of the project.

The critical path is:

A-D-H-J

Expected duration = 55.83
3) What is the probability that the project will take longer than 58 days to complete?

= 0.76

The probability is 0.2238.

4) Which path in the project network offers the greatest risk of overrunning a new deadline of 56 days?

A-D-H-I-J

The calculations are:

Data  

Results:-

Activity Early Start Early Finish Late Start Late Finish Slack
A 0 12.16667 0 12.16667 0
B 12.16667 22.16667 17.5 27.5 5.333333
C 12.16667 27.16667 18.66667 33.66667 6.5
D 12.16667 24.5 12.16667 24.5 0
E 22.16667 28.333333 27.5 33.66667 5.333333
F 28.33333 40.16667 33.66667 45.5 5.333333
G 22.16667 36.16667 31.5 45.5 9.333333
H 24.5 45.5 24.5 45.5 0
I 24.5 39.5 40.83333 55.83333 16.33333
J 45.5 55.83333 45.5 55.83333 0
Project 55.83333

Thanks for supporting...

Please give me a thumbs up if this helps you out. Thanks you!


Related Solutions

Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team...
Jim Sweet, a project manager at Clover Health in San Francisco, is assigned to the team that is developing the process for implementing a new database management system at corporate headquarters. The corporate planning group in Waltham, Massachusetts has contacted him and has asked how confident the design group is about completing the project in 60 days. He has developed these estimated time durations in days for the project: Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm)...
Ike Nate works as a manager in the San Francisco office of an international public accounting...
Ike Nate works as a manager in the San Francisco office of an international public accounting firm. His father has just taken a position as a purchasing agent for one of the public accounting firm’s San Francisco clients. Has Ike’s independence been impaired with respect to this audit client? Has the public accounting firm’s independence been impaired if Ike does not work on the audit?
Jim Wilson is the office manager for a large manufacturing firm. His team is studying the...
Jim Wilson is the office manager for a large manufacturing firm. His team is studying the usage of the company’s copy machines. A random sample of ten copy machines revealed the following number of copies from each machine (reported in 1,000s): 1026 920 1193 968 986 973 1073 1229 965 1185 Jim believes that the actual mean usage of all the copy machines is well over a million copies. Develop a 95% confidence interval for the mean number of copies...
You have been assigned to work as a project manager on a very important project that...
You have been assigned to work as a project manager on a very important project that requires significant funding. There are several options to consider. Being new to the organisation, you have very limited knowledge of the organisational dynamics, industry and funding preferences. As a project manager, what do you think your duties are on this project? Name a few essential steps and activities you will need to do to effectively perform your job.
Barbara just received the good news: She was assigned as the project manager for a project...
Barbara just received the good news: She was assigned as the project manager for a project that her company won as part of competitive bidding. Whenever a request for proposal (RFP) comes into Barbara’s company, a committee composed mainly of senior managers reviews the RFP. If the decision is made to bid on the job, the RFP is turned over to the Proposal Department. Part of the Proposal Department is an estimating group that is responsible for estimating all work....
You are a member in a project team and the project manager asked you to purchase...
You are a member in a project team and the project manager asked you to purchase 4 laptops with certain specifications (Lenovo ThinkPad T series, Core i7, 2 Tera Storage, 32 GB Ram, 15.6" size, NVIDIA® graphics). How do you set your procurement management to do that?
you are a member in a project team and the project manager asked you to purchase...
you are a member in a project team and the project manager asked you to purchase 4 laptops with certain specifications (lenovo thinkpad T series,core i7,2 tera storage ,32 GB Ram ,15.6 size , NVIDIA graphics ) how do you set your procurement management to do that?
You are a project team manager, and your team members report each day to you to...
You are a project team manager, and your team members report each day to you to receive their primary assignments.   Not every team member is as efficient as another with particular kinds of tasks.    Time required (hours) to complete tasks Task Task complexity Team member 1 - Jones Team member 2 - Nguyen Team member 3 - Walpita Team member 4 - Manderas Task A Very high 3 5 4 3 Task A High 2 1 3 2 Task...
Assume you are a project manager at JCDecaux and have been assigned to work with the...
Assume you are a project manager at JCDecaux and have been assigned to work with the city of Lyon to implement this physical, organizational, and social change. What are the practical and philosophical implications of this work?
You have be assigned to lead a project team. You have been given a lot of...
You have be assigned to lead a project team. You have been given a lot of latitude in how you will lead this team.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT