In: Accounting
Value-Stream Costing Objective
During the week of June 12, Harrison Manufacturing produced and shipped 15,400 units of its aluminum wheels: 3,000 units of Model A and 12,400 units of Model B. The following costs were incurred:
| Materials | Salaries/ Wages |
Machining | Other | Total Cost | |||||
| Order processing | $19,000 | $19,000 | |||||||
| Production planning | 243,000 | 243,000 | |||||||
| Purchasing | 22,500 | 22,500 | |||||||
| Stamping | $355,000 | 35,500 | $36,600 | $20,000 | 447,100 | ||||
| Welding | 160,000 | 42,000 | 42,000 | 12,000 | 256,000 | ||||
| Cladding | 265,000 | 265,000 | |||||||
| Testing | 10,500 | 10,500 | |||||||
| Packaging and shipping | 9,000 | 9,000 | |||||||
| Invoicing | 12,600 | 12,600 | |||||||
| Total | $780,000 | $394,100 | $78,600 | $32,000 | $1,284,700 |
Required:
1. Assume initially that the value-stream costs
and total units shipped apply only to one model (a single-product
value stream). Calculate the unit cost. Round your answer to the
nearest dollar amount.
$ per unit
2. Calculate the unit cost for Models A and B. Round your answers to the nearest dollar amount.
| Unit Cost | |
| Model A | $ |
| Model B | $ |
3. What if Model A is responsible for 40 percent of the materials cost? Calculate the unit materials cost for Models A and B. Round your answers to the nearest dollar amount.
| Unit Cost | |
| Model A | $ |
| Model B | $ |
Calculate the total unit cost for Models A and B. Round your interim calculations and final answers to the nearest dollar amount.
| Unit Cost | |
| Model A | $ |
| Model B | $ |