Question

In: Accounting

Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,000 units...

Value-Stream Costing Objective

During the week of June 12, Harrison Manufacturing produced and shipped 16,000 units of its aluminum wheels: 3,400 units of Model A and 12,600 units of Model B. The following costs were incurred:

Materials        Salaries/
Wages
       Machining        Other        Total Cost
Order processing        $19,400                      $19,400
Production planning        34,800                      34,800
Purchasing        23,400                      23,400
Stamping $380,000        38,000        $36,200        $18,000        472,200
Welding 160,000        20,000        16,000        12,000        208,000
Cladding 65,000                             65,000
Testing        10,000                      10,000
Packaging and shipping        10,000                      10,000
Invoicing        14,200                      14,200
  Total $605,000        $169,800        $52,200        $30,000        $857,000

Required:

Note: Round ALL interim calculations to two decimal places. Uses these values in subsequent computations.

1. Assume initially that the value-stream costs and total units shipped apply only to one model (a single-product value stream). Calculate the unit cost.
Unit cost is $ per unit

2. Calculate the unit cost for Models A and B.

Unit Cost
Model A $
Model B $

3. What if Model A is responsible for 40 percent of the materials cost? Calculate the unit materials cost for Models A and B.

Unit Cost
Model A $
Model B $

Calculate the total unit cost for Models A and B.

Unit Cost
Model A $
Model B $

Solutions

Expert Solution

Part- A & B
Unit Cost := Total Cost / Total Unit
= 857000/(3400+12600) =53.5625 or 53.56
Eac Model A & B will be the same cost $53.56
PART B
Total cost of A= Total cost *   A units /Total Units
= 857000*3400/16000 = 182113
Unit cost = Total cost A / A units=182113/3400 =53.56
Total cost of B= Total cost *   B units /Total Units
= 857000*12600/16000 = 674888
Unit cost = Total cost B / Bunits=674888/12600 =53.56
Part-C
Model A ( Unit Material Cost )= Total Cost/ Total Unit  
=(605000*40%)/3400
=242000/3400=71.1765 or 71.18
Model B ( Unit Material Cost )= Total Cost/ Total Unit  
(605000*60%)/12600= 363000/12600
=28.8095 or 28.81
Computation of Conversion Cost
Unit Cost =Total Cost/ Total Unit
=(857000-605000)/(3400+12600)= $252000/16000
=15.75
Computation of Total Unit cost
Particular Material Cost Conversion Cost Total
Model A $71.18 $15.75 $86.93
Model B $28.81 $15.75 $44.56

Related Solutions

Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units of its aluminum wheels: 4,000 units of Model A and 12,400 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,600                      $19,600 Production planning        236,400                      236,400 Purchasing        23,400                      23,400 Stamping $380,000        38,000        $37,000        $20,000        475,000...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 15,400 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 15,400 units of its aluminum wheels: 3,000 units of Model A and 12,400 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,000                      $19,000 Production planning        243,000                      243,000 Purchasing        22,500                      22,500 Stamping $355,000        35,500        $36,600        $20,000        447,100...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 17,200 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 17,200 units of its aluminum wheels: 3,800 units of Model A and 13,400 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $20,000                      $20,000 Production planning        228,600                      228,600 Purchasing        22,500                      22,500 Stamping $365,000        36,500        $37,400        $20,000        458,900...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 18,000 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 18,000 units of its aluminum wheels: 5,000 units of Model A and 13,000 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,000                      $19,000 Production planning        199,800                      199,800 Purchasing        25,200                      25,200 Stamping $355,000        35,500        $37,800        $19,600        447,900...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units of its aluminum wheels: 3,600 units of Model A and 12,800 units of Model B. The following costs were incurred: Materials Salaries/ Wages Machining Other Total Cost Order processing $19,400 $19,400 Production planning 304,800 304,800 Purchasing 23,400 23,400 Stamping $380,000 38,000 $37,200 $19,200 474,400 Welding 160,000 20,000 16,000 12,000 208,000 Cladding 65,000 65,000 Testing 10,000 10,000 Packaging and shipping 10,000 10,000 Invoicing 14,200 14,200...
A value stream has three activities and two products. The units produced and shipped per week...
A value stream has three activities and two products. The units produced and shipped per week are 50 of the deluxe model (Model A) and 150 of the basic model (Model B). The resource consumption patterns are shown as follows: Model A Model B Costs of Value- Stream Activities Cell manufacturing 2,380 min. 7,140 min. $ 57,120 Engineering 65 hrs. 234 hrs. 26,013 Testing 95 hrs. 247 hrs. 27,360    Total $ 110,493 Required: 1. Calculate the ABC product cost for...
Value-Stream Product Costing, ABC, and DBC Brasher Company is transitioning to a lean manufacturing system and...
Value-Stream Product Costing, ABC, and DBC Brasher Company is transitioning to a lean manufacturing system and has just finalized two order fulfillment value streams. One of the value streams has two products, and the other has four products. The two-product value stream produces precision machine parts and the four-product value stream produces machine tools. Before moving to the value-stream structure, Brasher had a well-developed ABC system (one that used all duration drivers) and had experienced good success with the more...
Greeson Clothes Company produced 23,000 units during June of the current year. The Cutting Department used...
Greeson Clothes Company produced 23,000 units during June of the current year. The Cutting Department used 4,400 direct labor hours at an actual rate of $13.2 per hour. The Sewing Department used 7,300 direct labor hours at an actual rate of $12.9 per hour. Assume there were no work in process inventories in either department at the beginning or end of the month. The standard labor rate is $13.1. The standard labor time for the Cutting and Sewing departments is...
Direct Labor Variances The Freedom Clothes Company produced 15,000 units during June of the current year....
Direct Labor Variances The Freedom Clothes Company produced 15,000 units during June of the current year. The Cutting Department used 2,900 direct labor hours at an actual rate of $14.4 per hour. The Sewing Department used 4,800 direct labor hours at an actual rate of $14.1 per hour. Assume there were no work in process inventories in either department at the beginning or end of the month. The standard labor rate is $14.3. The standard labor time for the Cutting...
a) Mulwa Ltd a manufacturing company produced 10,000 units of 2kg unga product during the first...
a) Mulwa Ltd a manufacturing company produced 10,000 units of 2kg unga product during the first quarter of 2013. The following additional information is also provided Direct material – ksh 8 Direct labour - ksh 4 Variable manufactury – 2 Fixed manufacturing cost – ksh 36,000 Selling and administration cost – ksh 5,000 Selling price – ksh 20 per cent Closing stock at the end of the period = 1000 units. Required: Determine the unit production cost of the product...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT