In: Accounting
Test Company produces a product that passes through two departments: Department 1 and Department 2. Test Company determines product cost using a normal cost system. The company applies overhead using departmental overhead rates. Overhead in Department 1 is applied based on machine hours. Overhead in Department 2 is applied based on direct labor hours. The company prepared the following estimates at the beginning of the year.
Department 1 |
Department 2 |
Total |
|
Prime cost |
$375,000 |
$700,000 |
$1,075,000 |
Overhead cost |
$420,000 |
$240,000 |
$660,000 |
Direct labor hours |
16,000 |
50,000 |
66,000 |
Machine hours |
100,000 |
20,000 |
120,000 |
During the year, Test Company reported the following actual results.
Department 1 |
Department 2 |
Total |
|
Prime cost |
$475,000 |
$850,000 |
$1,325,000 |
Overhead cost |
$450,000 |
$300,000 |
$750,000 |
Direct labor hours |
20,000 |
60,000 |
80,000 |
Machine hours |
125,000 |
25,000 |
150,000 |
Q1. Calculate the predetermined overhead rate Test Company uses to apply overhead in Department 1.
a. |
$6.60 per machine hour |
|
b. |
$3.60 per machine hour |
|
c. |
$26.25 per direct labor hour |
|
d. |
$4.20 per machine hour |
Q2.
Calculate the overhead applied to production in Department 1 for the year.
Note: Give your answer using dollar signs and commas but not decimal points (cents).
Example: $12,345
Q3. Calculate the predetermined overhead rate Test Company uses to apply overhead in Department 2.
a. |
$13.20 per direct labor hour |
|
b. |
$4.80 per direct labor hour |
|
c. |
$12.00 per machine hour |
|
d. |
$5.00 per direct labor hour |
Q4. Calculate the overhead applied to production in Department 2 for the year.
Q5. Calculate the total overhead variance for the year.
a. |
$87,000 underapplied |
|
b. |
$63,000 underapplied |
|
c. |
$63,000 overapplied |
|
d. |
$87,000 overapplied |
1.
Estimated overhead cost = $420,000
Estimated machine hour = 100,000
Predetermined overhead rate = Estimated overhead cost/Estimated machine hour
= 420,000/100,000
= $4.2 per machine hour
Correct option is (d)
2.
overhead applied to production in Department 1 = Actual machine hours x Predetermined overhead rate
= 125,000 x 4.2
= $525,000
3.
Estimated overhead cost = $240,000
Estimated direct labor hour = 50,000
Predetermined overhead rate = Estimated overhead cost/Estimated direct labor hour
= 240,000/50,000
= $4.8 per direct labor hour
Correct option is (b)
4.
overhead applied to production in Department 2 = Actual direct labor hour x Predetermined overhead rate
= 60,000 x 4.8
= $288,000
5.
Total actual overhead incurred = Actual overhead in Department 1 + Actual overhead in Department 2
= 450,000 + 300,000
= $750,000
Total overhead applied = overhead applied to production in Department 1 + overhead applied to production in Department 2
= 525,000 + 288,000
= $813,000
Total overhead variance = Total overhead applied - Total actual overhead incurred
= 813,000 - 750,000
= $63,000 overapplied
Correct option is (c)