Question

In: Accounting

Question 1 BOBBY produces a specialized product GRINGO. The product passes through three (3) cost centers...

Question 1

BOBBY produces a specialized product GRINGO. The product passes through three (3) cost centers namely:machining, assembly and painting shop. Data relating to the cost centers is as below:

Machinin

g

Assembly

Painting shop

Engineering shop

Stores

Number of employees

81

51

39

30

24

Engineering shop-- service

18,000

12,000

10,000

-

-

Stores (orders)

180

135

90

45

-

At a management meeting dated 24th September 20X0, the following overheads were budgeted for the production and service cost centers exclusively for the ensuing period:

Cost centers

GHS 000

Machining

180,000

Assembly

160,000

Painting shop

130,000

Engineering shop

84,000

Stores

52,000

Canteen

75,000

Equally, the following budgeted data relates to the production cost centers:

Machining

Assembly

Painting shop

Machine hours

9,200

8,100

6,600

Labor hours

8,300

11,250

9,000

Labor cost (GHS)

40,000

88,000

45,000

Actual results for the production cost centers were:

Machining

Assembly

Painting shop

Machine hours

10,000

8,200

6,600

Labor hours

4,500

7,800

6,900

Labor cost (GHS)

25,000

42,000

35,000

Actual overheads (GHS)

290,000

167,000

155,000

Required:

  1. Apportion the production overhead costs of the service cost centers to the production cost centers and determine predetermined overhead absorption rates for the three (3) production cost centers on the following basis:

Machining - Machine hours.

Assembly - Labor hours.

Paint shop - Labor costs.

  1. Prepare a statement showing the under/over absorption per cost center for the period under review.

PLEASE SHOW WORKING ON THE PAPER!!......

What information?

Solutions

Expert Solution

note: if you have any doubts feel free to comment me i will help you. dont give direct thumbs down. if you are satisfied with the answer hit the like button.


Related Solutions

Question 1 AKWASI produces a specialized product CESAR. The product passes through three (3) cost centers...
Question 1 AKWASI produces a specialized product CESAR. The product passes through three (3) cost centers namely: machining, assembly and painting shop. Data relating to the cost centers is as below: Machinin g Assembly Painting shop Engineering shop Stores Number of employees 81 51 39 30 24 Engineering shop-- service 18,000 12,000 10,000 - - Stores (orders) 180 135 90 45 - At a management meeting dated 24th September 20X0, the following overheads were budgeted for the production and service...
ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost centers namely:...
ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost centers namely: machining, assembly and painting shop. Data relating to the cost centers is as below: Machining Assembly Painting shop Engineering shop Stores Number of employees 81 51 39 30 24 Engineering shop-service 18,000 12,000 10,000 - - Stores (orders) 180 135 90 45 - At a management meeting dated 24th September 20X0, the following overheads were budgeted for the production and service cost centers exclusively...
ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost centers namely:...
ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost centers namely: machining, assembly and painting shop. Data relating to the cost centers is as below: Machinin g Assembly Painting shop Engineering shop Stores Number of employees 81 51 39 30 24 Engineering shop-- service 18,000 12,000 10,000 - - Stores (orders) 180 135 90 45 - At a management meeting dated 24th September 20X0, the following overheads were budgeted for the production and service cost...
Question 1 ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost...
Question 1 ZABZUGU TATALE produces a specialized product KANZO. The product passes through three (3) cost centers namely: machining, assembly and painting shop. Data relating to the cost centers is as below: Machinin g Assembly Painting shop Engineering shop Stores Number of employees 81 51 39 30 24 Engineering shop-- service 18,000 12,000 10,000 - - Stores (orders) 180 135 90 45 - At a management meeting dated 24th September 20X0, the following overheads were budgeted for the production and...
FIFO Method, Single Department Analysis, One Cost Category Hatch Company produces a product that passes through...
FIFO Method, Single Department Analysis, One Cost Category Hatch Company produces a product that passes through three processes: Fabrication, Assembly, and Finishing. All manufacturing costs are added uniformly for all processes. The following information was obtained for the Fabrication Department for June: Work in process, June 1, had 90,000 units (40 percent completed) and the following costs: Direct materials $72,740 Direct labor 109,000 Overhead 36,000 During the month of June, 180,000 units were completed and transferred to the Assembly Department,...
Test Company produces a product that passes through two departments: Department 1 and Department 2. Test...
Test Company produces a product that passes through two departments: Department 1 and Department 2. Test Company determines product cost using a normal cost system. The company applies overhead using departmental overhead rates. Overhead in Department 1 is applied based on machine hours. Overhead in Department 2 is applied based on direct labor hours. The company prepared the following estimates at the beginning of the year. Department 1 Department 2 Total Prime cost $375,000 $700,000 $1,075,000 Overhead cost $420,000 $240,000...
Test Company produces a product that passes through two departments: Department 1 and Department 2. Test...
Test Company produces a product that passes through two departments: Department 1 and Department 2. Test Company determines product cost using a normal cost system. The company applies overhead using a plant-wide rate based on machine hours. The company prepared the following estimates at the beginning of the year. Department 1 Department 2 Total Prime cost $375,000 $700,000 $1,075,000 Overhead cost $420,000 $240,000 $660,000 Direct labor hours 16,000 50,000 66,000 Machine hours 100,000 20,000 120,000 During the year, Test Company...
Company produces a product that passes through two departments: Department 1 and Department 2. Test Company...
Company produces a product that passes through two departments: Department 1 and Department 2. Test Company determines product cost using a normal cost system. The company applies overhead using departmental overhead rates. Overhead in Department 1 is applied based on machine hours. Overhead in Department 2 is applied based on direct labor hours. The company prepared the following estimates at the beginning of the year. Department 1 Department 2 Total Prime cost $375,000 $700,000 $1,075,000 Overhead cost $420,000 $240,000 $660,000...
Kun pow produces canned chicken a la king. The chicken a la king passes through three​...
Kun pow produces canned chicken a la king. The chicken a la king passes through three​ departments: (1)​ Mixing, (2) Retort​ (sterilization), and​ (3) Packing. In the Mixing​ Department, chicken and cream are added at the beginning of the​ process, the mixture is partly​ cooked, and chopped green peppers and mushrooms are added at the end of the process. Conversion costs are incurred evenly throughout the mixing process. NovemberNovember data from the Mixing Department are as​ follows: LOADING... ​(Click the...
Bakul Mala Manufacturing, which uses the First-In, First-Out costing method, produces a product that passes through...
Bakul Mala Manufacturing, which uses the First-In, First-Out costing method, produces a product that passes through two departments: A and B. In the Department A, all materials are added at the beginning of the process and all other manufacturing inputs are added uniformly. The following information relates to Department A for the month of July:   a.       Beginning Work-In-Process, 1 July: 400,000 units (20% complete with respect to conversion costs). The costs assigned to this work are as follows: Direct Materials =...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT