In: Finance
| 
 Case Study 3--Capital Budgeting  | 
|||||||||
| 
 (Comprehensive Spreadsheet Problem 11-23, page 408)  | 
|||||||||
| 
 Your division is considering two projects. Its WACC is 10%, and the projects' after-tax cash flows (in millions  | 
|||||||||
| 
 of dollars) would be as follows:  | 
|||||||||
| 
 Expected Cash Flows  | 
|||||||||
| 
 Time  | 
 Project A  | 
 Project B  | 
|||||||
| 
 0  | 
 ($30)  | 
 ($30)  | 
|||||||
| 
 1  | 
 $5  | 
 $20  | 
|||||||
| 
 2  | 
 $10  | 
 $10  | 
|||||||
| 
 3  | 
 $15  | 
 $8  | 
|||||||
| 
 4  | 
 $20  | 
 $6  | 
|||||||
| 
 a. Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks.  | 
|||||||||
| 
 WACC =  | 
 10%  | 
 Use Excel's NPV function as explained in  | 
|||||||
| 
 NPVA =  | 
 11model.xlsx. Note that the range does not include  | 
||||||||
| 
 NPVB =  | 
 the initial costs, which are added separately.  | 
||||||||
| 
 We find the internal rate of return with Excel's IRR function:  | 
|||||||||
| 
 IRRA =  | 
|||||||||
| 
 IRRB =  | 
|||||||||
| 
 We find the modified internal rate of return with Excel's MIRR function using the 10% WACC:  | 
|||||||||
| 
 MIRRA =  | 
|||||||||
| 
 MIRRB =  | 
|||||||||
| 
 Project A Payback Period:  | 
|||||||||
| 
 Time period:  | 
 0  | 
 1  | 
 2  | 
 3  | 
|||||
| 
 Cash flow:  | 
|||||||||
| 
 Cumulative cash flow:  | 
|||||||||
| 
 PaybackA:  | 
|||||||||
| 
 Project B Payback Period:  | 
|||||||||
| 
 Time period:  | 
 0  | 
 1  | 
 2  | 
 3  | 
|||||
| 
 Cash flow:  | 
|||||||||
| 
 Cumulative cash flow:  | 
|||||||||
| 
 PaybackB:  | 
|||||||||
| 
 Project A Discounted Payback Period:  | 
|||||||||
| 
 Time period:  | 
 0  | 
 1  | 
 2  | 
 3  | 
|||||
| 
 Cash flow:  | 
|||||||||
| 
 Disc. cash flow:  | 
|||||||||
| 
 Disc. cum. cash flow:  | 
|||||||||
| 
 Discounted PaybackA:  | 
|||||||||
| 
 Project B Discounted Payback Period:  | 
|||||||||
| 
 Time period:  | 
 0  | 
 1  | 
 2  | 
 3  | 
|||||
| 
 Cash flow:  | 
|||||||||
| 
 Disc. cash flow:  | 
|||||||||
| 
 Disc. cum. cash flow:  | 
|||||||||
| 
 Discounted PaybackB:  | 
|||||||||
| 
 b. If the two projects are independent, which project(s) should be chosen?  | 
|||||||||
| 
 c. If the two projects are mutually exclusive and the WACC is 10%, which project(s) should be chosen?  | 
|||||||||
| 
 d. Plot NPV profiles for the two projects. Identify the projects' IRRs on the graph.  | 
|||||||||
| 
 Hint: Before you can graph the NPV profiles for these projects, you must create a data table of project NPV relative to  | 
|||||||||
| 
 differing costs of capital--use Excel's NPV formula and the space below to do so. The graph will automatically create,  | 
|||||||||
| 
 as values are added.  | 
|||||||||
| 
 Project A  | 
 Project B  | 
||||||||
| 
 $0.00  | 
 $0.00  | 
||||||||
| 
 0.00%  | 
|||||||||
| 
 2.00%  | 
|||||||||
| 
 4.00%  | 
|||||||||
| 
 6.00%  | 
|||||||||
| 
 8.00%  | 
|||||||||
| 
 10.00%  | 
|||||||||
| 
 12.00%  | 
|||||||||
| 
 14.00%  | 
|||||||||
| 
 16.00%  | 
|||||||||
| 
 18.00%  | 
|||||||||
| 
 19.19%  | 
|||||||||
| 
 20.00%  | 
|||||||||
| 
 22.00%  | 
|||||||||
| 
 22.52%  | 
|||||||||
| 
 24.00%  | 
|||||||||
| 
 e. If the WACC was 5%, would this change your recommendation if the projects were mutually exclusive?  | 
|||||||||
| 
 If the WACC was 15%, would this change your recommendation? Explain your answers.  | 
|||||||||
| 
 f. The "crossover rate" is 13.5252%. Explain what this rate is and how it affects the choice between  | 
|||||||||
| 
 mutually exclusive projects.  | 
|||||||||
| 
 g. Is it possible for conflicts to exist between the NPV and the IRR when independent projects are being evaluated?  | 
|||||||||
| 
 Explain your answer.  | 
|||||||||
| 
 h. Now, look at the regular and discounted paybacks. Which project looks better when judged by the paybacks?  | 
|||||||||
| 
 i. If the payback was the only method a firm used to accept or reject projects, what payback should it choose  | 
|||||||||
| 
 as the cutoff point, that is, reject projects if their paybacks are not below the chosen cutoff? Is your selected  | 
|||||||||
| 
 cutoff based on some economic criteria, or is it more or less arbitrary? Are the cutoff criteria equally  | 
|||||||||
| 
 arbitrary when firms use the NPV and/or the IRR as the criteria? Explain.  | 
|||||||||
| 
 j. Define the MIRR. What's the difference between the IRR and the MIRR, and which generally gives a better  | 
|||||||||
| 
 idea of the rate of return on the investment in a project? Explain.  | 
|||||||||
| 
 k. Why do most academics and financial executives regard the NPV as being the single best criterion and  | 
|||||||||
| 
 better than the IRR? Why do companies still calculate IRRs?  | 
|||||||||
a)

Formula sheet
| A | B | C | D | E | F | G | H | I | J | 
| 2 | |||||||||
| 3 | |||||||||
| 4 | Cash Flows | ||||||||
| 5 | Time | Project A | Project B | ||||||
| 6 | 0 | -30 | -30 | ||||||
| 7 | 1 | 5 | 20 | ||||||
| 8 | 2 | 10 | 10 | ||||||
| 9 | 3 | 15 | 8 | ||||||
| 10 | 4 | 20 | 6 | ||||||
| 11 | |||||||||
| 12 | a) | ||||||||
| 13 | |||||||||
| 14 | WACC | 0.1 | |||||||
| 15 | |||||||||
| 16 | NPVA | =NPV(D14,D7:D10)+D6 | |||||||
| 17 | NPVB | =NPV(D14,E7:E10)+E6 | |||||||
| 18 | |||||||||
| 19 | IRRA | =IRR(D6:D10) | |||||||
| 20 | IRRB | =IRR(E6:E10) | |||||||
| 21 | |||||||||
| 22 | MIRRA | =MIRR(D6:D10,D14,D14) | |||||||
| 23 | MIRRB | =MIRR(E6:E10,D14,D14) | |||||||
| 24 | |||||||||
| 25 | |||||||||
| 26 | Project A Payback Period: | ||||||||
| 27 | Time period: | 0 | 1 | 2 | 3 | 4 | |||
| 28 | Cash flow: | =D6 | =D7 | =D8 | =D9 | =D10 | |||
| 29 | Cumulative cash flow: | =E28 | =E29+F28 | =F29+G28 | =G29+H28 | =H29+I28 | |||
| 30 | |||||||||
| 31 | PaybackA: | 3 | years | ||||||
| 32 | |||||||||
| 33 | Project B Payback Period: | ||||||||
| 34 | Time period: | 0 | 1 | 2 | 3 | 4 | |||
| 35 | Cash flow: | =E6 | =E7 | =E8 | =E9 | =E10 | |||
| 36 | Cumulative cash flow: | =E35 | =E36+F35 | =F36+G35 | =G36+H35 | =H36+I35 | |||
| 37 | |||||||||
| 38 | PaybackB: | 2 | Years | ||||||
| 39 | |||||||||
| 40 | Project A Discounted Payback Period: | ||||||||
| 41 | Time period: | 0 | 1 | 2 | 3 | 4 | |||
| 42 | Cash flow: | =E28 | =F28 | =G28 | =H28 | =I28 | |||
| 43 | Disc. cash flow: | =E42/((1+$D$14)^E41) | =F42/((1+$D$14)^F41) | =G42/((1+$D$14)^G41) | =H42/((1+$D$14)^H41) | =I42/((1+$D$14)^I41) | |||
| 44 | Disc. cum. cash flow: | =E43 | =E44+F43 | =F44+G43 | =G44+H43 | =H44+I43 | |||
| 45 | |||||||||
| 46 | Discounted PaybackA: | =3+(0-H44)/(I44-H44) | Years | ||||||
| 47 | |||||||||
| 48 | Project B Discounted Payback Period: | ||||||||
| 49 | Time period: | 0 | 1 | 2 | 3 | 4 | |||
| 50 | Cash flow: | =E35 | =F35 | =G35 | =H35 | =I35 | |||
| 51 | Disc. cash flow: | =E50/((1+$D$14)^E49) | =F50/((1+$D$14)^F49) | =G50/((1+$D$14)^G49) | =H50/((1+$D$14)^H49) | =I50/((1+$D$14)^I49) | |||
| 52 | Disc. cum. cash flow: | =E51 | =E52+F51 | =F52+G51 | =G52+H51 | =H52+I51 | |||
| 53 | |||||||||
| 54 | Discounted PaybackB: | =2+(0-G52)/(H52-G52) | Years | ||||||
| 55 | |||||||||